Paxton v. Spencer

265 P. 751, 71 Utah 313, 1928 Utah LEXIS 59
CourtUtah Supreme Court
DecidedMarch 8, 1928
DocketNo. 4619.
StatusPublished
Cited by5 cases

This text of 265 P. 751 (Paxton v. Spencer) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paxton v. Spencer, 265 P. 751, 71 Utah 313, 1928 Utah LEXIS 59 (Utah 1928).

Opinion

GIDEON, J.

On the 5th day of September, 1924, plaintiffs (appellants) entered into a contract with the state road commission of this state for the construction of a highway in Southern Utah. On the 9th day of September, 1924, the appellants sublet to the defendants (respondents) Walter Spencer, Edward H. Parry, William Pearce, and Archie D. Ryan the construction of a portion of said highway. A written contract bearing that date was entered into between the appellants and respondents. In this contract the work to be done was classified, and the agreed price per cubic yard and per linear foot was named. The respondents immediately entered upon the performance of the work specified in the contract of September 9, 1924.

In this opinion the plaintiffs will be designated appellants, and defendants Spencer, Parry, Pearce, and Ryan, respondents, and the Fidelity & Deposit Company, cross-appellant.

The cross-appellant, Fidelity & Deposit Company of Maryland, executed a surety bond on behalf of the respondents *316 in which the appellants were the obligees. After reciting the making of the contract between the appellants and respondents, the bond provided as follows:

“Now therefore, the conditions of this obligation are such that if the principal shall indemnify the obligee against any loss or damage directly arising by reason of the failure of the principal to faithfully perform said contract and shall promptly and faithfully pay the account contracted for material furnished and labor performed under and by virtue of said contract, then this obligation to be void; otherwise, to remain in full force and effect.
“This bond shall inure to the direct benefit of every materialman, subcontractor, or mechanic or other person or concern that may furnish materials or perform labor for or upon the work or contract for which this bond is given, and such persons shall have a direct right of action against the principal and surety herein, in accordance with the provisions of chapter III, tit. 62, Laws of Utah 1917.”

The respondents failed to complete the contract. This suit is to recover damages alleged to have been sustained by appellants by reason of the failure of respondents to complete the work as provided in the contract. Both the respondents and surety company are made defendants. When the issues were joined, a trial was had before the court and a jury that resulted in a verdict in favor of appellants and against the respondents in the sum of $8,184.97, and against the cross-appellant in the sum of $4,482.97. The plaintiffs appeal, and the surety company is also a cross-appellant.

The appellants assign as error the giving of one of the court’s instructions known as No. 6%. It appears from the undisputed evidence that in the month of January, 1925, the subcontractors went to the appellants for financial assistance. The appellants were advised by the subcontractors that they had exhausted their credit and were not financially able to procure the money then needed to pay their labor and for materials. Appellants, or one of them, went with the subcontractors to Millard County Bank and a loan of $2,500 was obtained. This loan *317 was obtained by the appellants and the money immediately placed to the credit of tbe respondents and was used by them in paying their labor and for material used in the road construction. At this time the subcontractors gave a written order to the bank, by the terms of which the bank had the right to take from the next monthly estimate made upon, the work done by the subcontractors the sum of $1,500 and apply the same upon the indebtedness evidenced by the $2,500 note. This payment was made and the amount credited accordingly. Thereafter, in March, 1925, the subcontractors were again unable to meet the payments for labor and material used in doing the road work. The appellants again procured and advanced or loaned to the subcontractors an additional $2,500. This money was placed to the credit of the subcontractors and also went to pay for labor done on the work provided for in the contract and also for materials used in connection with the doing of said work. Neither this note of $2,500 nor the $1,000 remaining due on the note of January was paid by the subcontractors. The court instructed the jury that these items of $2,500 and $1,000, making a total of $3,500, were not a loss chargeable against the surety company. The giving of that instruction is the only error assigned by appellants requiring serious consideration.

The appellants contend, and it is the basis of their argument, that the advancement or loan was to enable the subcontractors to continue the work and properly complete the contract and moreover that the moneys so advanced or loaned were used by the subcontractors to pay for labor done on the highway and for materials used in carrying on the construction of the road as provided in the contract, and to that extent reduced the amount of damages that the appellants would have, by the terms of the bond, the right to recover against the surety company and which the surety obligated itself to pay.

It is material and should be noted that the advances or loans made were not in payment of any estimates that had *318 been made or were due and payable under the terms of the contract and the amount of the loans was not based upon any estimated work then completed. It is not contended, nor is there any evidence, that the cross-appellant was advised of these advances or knew anything about the fact that the subcontractors were unable to finance the project at the date the advancements were made, nor, in fact, until about April 20, 1925. Among the conditions specified in the bond under which the surety became liable are the following:

“ (a) That in the event of any default on the part of the principal a written statement of the particular facts showing such default and the date thereof shall be delivered to the surety by registered mail at its office at Salt Lake City, Utah, promptly, and in any event within 10 days after the obligee or his representative, or the architect, if any, shall learn of such default; that the surety shall have the right within 30 days after the receipt of such statement to proceed, or procure others to proceed, with the performance of such contract, shall also be subrogated to all of the rights of the principal; and any moneys or property that may at the time of such default be due, or that thereafter may become due to the principal under said contract, shall be credited upon any claim which the obligee may then or thereafter have against the surety, and the surplus, if any, applied as the surety may direct.
“ (b) That no claim, suit, or action, by reason of any .default, shall be brought by the obligee against the surety after the 1st day of June, 1925, nor shall recovery be had for damages accruing after that date. * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)
Bower v. Tebbs
314 P.2d 731 (Montana Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
265 P. 751, 71 Utah 313, 1928 Utah LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paxton-v-spencer-utah-1928.