Globe Indemnity Co. v. Southern Pac. Co.

30 F.2d 580, 1929 U.S. App. LEXIS 2460
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 11, 1929
DocketNo. 70
StatusPublished
Cited by7 cases

This text of 30 F.2d 580 (Globe Indemnity Co. v. Southern Pac. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Globe Indemnity Co. v. Southern Pac. Co., 30 F.2d 580, 1929 U.S. App. LEXIS 2460 (2d Cir. 1929).

Opinion

AUGUSTUS N. HAND, Circuit Judge.

This ease was tiled before the court on a stipulation waiving a jury. The action was to recover damages on a bond to secure the plaintiff in making advance payments on a contract to construct three vessels. The salient facts were stated in our opinion reported at 21 F.(2d) 288, on the former appeal. While the appellant has reargued most of the matters there disposed of, we see no reason to depart from our general conclusions. If the dictum in Prairie State Nat. Bank v. U. S. (U. S. v. Hitchcock) 164 U. S. 227, 17 S. Ct. 142, 41 L. Ed. 412, and the authority of kindred cases as to the complete release by advance payments of a surety who acquired rights when the contract was entered into might have been applicable in other circumstances, it cannot apply to this situation where the bonds were taken to secure the final payments before the final trial trips were run on El-Estero and El Isleo, and where the advance payment of $50,000 on El Lago was made the day before the abandonment of the contract, and therefore could not have diminished the incentive of the principal to perform. This last advance payment, while prejudicial because it lessoned security, consisting of the unpaid installments applicable to unfinished work, only released the surety pro tanto. No case is cited holding that the surety is completely released by an advance payment without consent of the surety, where it appears, as hero, that the payment was made on the eve of abandonment of the contract and the appointment of receivers of the principal, so that the contractor’s incentive to prosecute the work cannot have been affected. The release in such a situation is only pro tanto. St. John’s College v. Ætna Indemnity Co., 201 N. Y. 335, 94 N. E. 994; United States Fidelity & Guaranty Co. v. Golden Pressed & Fire Brick Co., 191 U. S. 416, 24 S. Ct. 142, 48 L. Ed. 242.

The questions to be considered on this appeal are:

(1) The effect of the “ready for delivery payment” of $71,606.66 on the steamer El Isleo, and of the advance payment on January 3, 1921, on the steamer El Lago, upon the adjustment of the damages.

(2) The amount of liquidated damages at $1,333 per day due on El Lago after the abandonment of the contract.

(3) The allowance of interest.

The “ready for delivery” payment of $71,666.66 on El Isleo was made on January 6, 1921, after the abandonment of the contract on January 4th, and operated pro tanto to release the surety. In other words, this sum, because it would have been available to complete the work if it had been withheld, as it should have been, must be treated as a credit to the surety company. The same is true of the $50,000 advance payment on the El Lago, which was paid to the prejudice of the surety company, without its consent, and cannot bo included in the claim against it. These conclusions necessarily follow from our decision on the former appeal. The advance final payments of $71,666.66 each, on El Estero and El Isleo, are proper credits to the plaintiff, because the bond was furnished to enable these advances to he made.

The plaintiff claims liquidated damages amounting to a total of $137,299. Of these $57,319 are on the three vessels under construction prior to abandonment of the contract on January 4, 1921, and $15,996 on El Isleo subsequent to abandonment. The remaining $63,984 represents liquidated damages on El Lago subsequent to the abandonment of the contract. This last item is the only one of the three, the amount of which is in dispute.

It is contended, however, that plaintiff should have deducted any liquidated damages that had accrued before making an advance, and that the failure to do this operated at least pro tanto as a release. But the construction contract did not require the reduction of the installments by such accruals. It only provided that, in ease of delayed completion, the contractor “shall ho liable to pay to” plaintiff this damage at the rate of $1,333 per day. Liquidated damages did not constitute a pro tanto reduction of the purchase price, though they doubtless, if plaintiff had desired, might have been set off.

Plaintiff’s proof shows that the boilers [582]*582were installed in El Lago on December 4, 1920, and that it would have taken two months after that date to complete the work on the vessel with normal progress. She was completed by the plaintiff on March 3d following. Her delivery was due under the extended contract on December 4th. Thus she should have been completed February 4th, though she was not completed until March 3d.' The plaintiff seeks to obtain liquidated damages from December 4th until March 3d, by extending the two months after December 4th required to complete her. Its argument is based on statements by plaintiff’s witness Marks that El Lago was held back six or eight weeks, while El Estero was being finished. But this additional time obviously cannot be added, unless the delay was after December 4th, when the boilers were installed. There is no proof that the delay was not prior, and it seems practically certain that it must have been, for El Estero was delivered on November 24th, and little work was done to complete her after that date. Between January 4th and February 4th there were 27 working days. Therefore there would be damages during that period on El Lago, at $1,333 per day, to the amount of $35,991. If this sum be added to the other undisputed items of liquidated damages, amounting to $73,315, the total is $109,306.

Now the original contract price for building the three ships was $4,300,000. Prior to November 24, 1920, it was agreed that windlasses less costly than those provided in the contract might be installed by the contractor, and that the plaintiff might deduct $9,350 from the contract price for the windlass furnished to each ship, or $28,050 altogether. The windlasses so substituted were installed before the contract was abandoned. Extra work on the ships was done by the contractor to the amount of $3,930, so that the total amount due from the Southern Pacific Company to complete the work was $4,275,880, or $4,300,000 — (—$3,930—$28,050=$4,275,880.

It appears from Exhibit 1 in the agreed statement of facts that there was paid by the Southern Pacific Company, to or for the account of the contractor, $4,063,333.29. This included, however, the “ready for delivery” payment of $71,666.66 made January 6,1921, on El Isleo after the contract was abandoned, and the $50,000 advance “ready for delivery” payment made January 3, 1921, on El Lago before such sum had become due under the terms of the contract. The payment of $71,-666.66 cannot serve as a charge against the surety, because it was paid after the contract was abandoned on January 4th, and the payment of $50,000 also cannot be charged. It seems convenient to credit both these items to the plaintiff, seeing that it paid out both sums on account of the construction contract, and then to charge them both on the other side of the account, because they cannot be included in the claim for damages against the defendant.

The credits to the plaintiff based upon plaintiff's proofs that it would take two months after the installation of the engines and boilers to complete the El Lago are as follows:

Paid on El Estero......................... $1,433,333 32

Paid on El Isleo without including ready for delivery payment made January 6,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)
Fidelity & Deposit Co. v. New York City Housing Authority
140 F. Supp. 298 (S.D. New York, 1956)
Ætna Casualty & Surety Co. v. B. B. B. Const. Corp.
173 F.2d 307 (Second Circuit, 1949)
United States v. Anchor Warehouses, Inc.
92 F.2d 57 (Second Circuit, 1937)
United States v. Bornn
20 F. Supp. 336 (E.D. New York, 1937)
Maryland Casualty Co. v. Dunlap
68 F.2d 289 (First Circuit, 1933)
Prudence Co. v. Fidelity & Deposit Co.
2 F. Supp. 454 (S.D. New York, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
30 F.2d 580, 1929 U.S. App. LEXIS 2460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/globe-indemnity-co-v-southern-pac-co-ca2-1929.