Fidelity & Deposit Co. v. New York City Housing Authority

140 F. Supp. 298, 49 A.F.T.R. (P-H) 1072, 1956 U.S. Dist. LEXIS 3457
CourtDistrict Court, S.D. New York
DecidedApril 18, 1956
StatusPublished
Cited by6 cases

This text of 140 F. Supp. 298 (Fidelity & Deposit Co. v. New York City Housing Authority) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. New York City Housing Authority, 140 F. Supp. 298, 49 A.F.T.R. (P-H) 1072, 1956 U.S. Dist. LEXIS 3457 (S.D.N.Y. 1956).

Opinion

DIMOCK, District Judge.

Fidelity and Deposit Company of Maryland, surety on the bond of CarusoStureey Corporation, a building contractor, brings this action to recover the sum of $46,392.51 from defendant New York City Housing Authority, hereinafter referred to as the owner. That sum is an amount equal to the unpaid balance of the contract price for heating and ventilating work that the contractor agreed to do at Ravenswood Houses. By its agreement with the owner, the building contractor had engaged not only to do the -required construction but also to pay its ..laborers and materialmen. However, while it completed the construction, it failed to pay all the laborers and materialmen. Because of this default, tie owner withheld final payment pursuant to a requirement of the contract. The surety on the contract, pursuant to the. obligation of its bond, paid the laborers and materialmen. The surety seeks reimbursement of the amount it paid to them.

Defendant United States of America asserts a claim., to the withheld funds because of tax .liens against the property of the contractor.

Granting recovery to either the surety or the Government will exhaust the withheld funds. Since the owner must not be required to pay twice, the question here presented is as to the relative superiority'of the respective claims of the surety and the Government against the owner.

The Government’s right to a lien is created by section 3670 of the 1939 Internal Revenue Code, 26 U.S.C. § 3670, which reads as follows:

“§ 3670. Property subject to lien.
“If any person liable to pay any tax neglects or refuses to pay the. same after demand, the amount (including any interest, penalty, additional amount, or addition to such. tax, together with any costs that may accrue in addition thereto) shall be a lien in favor of the United States upon all property and rights to property, whether real or personal, belonging to such person.”

The period of the Government’s lien is fixed by section 3671, 26 U.S.C. § 3671, which reads as follows:

“§ 3671. Period, of lien
“Unless another date is specifically fixed by law, the lien shall arise at the time the assessment list was received by the collector and shall continue until the liability for such amount is satisfied or becomes unenforceable by reason of lapse of time.”

Section 3672(a), 26 U.S.C. § 3672(a), makes the Government’s lien invalid against a subsequent mortgagee, pledgee, purchaser, or judgment creditor unless notice thereof has been filed by the collector. It reads:

“§ 3672. Validity against mortgagees, pledgees, purchasers, and judgment creditors
“(a) Invalidity of lien without notice. Such lien shall not be valid as against any mortgagee, pledgee, purchaser, or judgment creditor until notice thereof has been filed, by the collector * *

The chronology is as follows:

The contract and the surety bond were executed before any payments by the surety to the contractor’s laborers and materialmen and before any of the Government’s liens accrued. The surety’s payments to the contractor^ laborers and materialmen were made during the period from December 11, 1950, to November 13, 1951. The Government’s liens accrued during the period from April 4, 1950, to September 12, 1951. It thus appears that, if the relative rights of the surety and the Government defend upon the chronology of the surety’s •payments to the laborers and material-men and of the accrual of the liens of the .Government, the method of determining the respective amounts ..due would ,be *301 to arrange the payments of laborers and materialmen and of tax liens in a single list in chronological order and to allocate a sufficient amount to meet each payment of a creditor and each tax lien beginning with the oldest until the withheld funds were exhausted.

The surety argues that, when a surety, at the request of the contractor, agrees with the owner to make good the default of the contractor, there is an implied term of the arrangement between the three that the owner will pay to the surety any part of the unpaid contract price necessary to reimburse the surety for his expenditures in making good the contractor’s default. Thus, under the terms of the arrangement, the surety’s rights would not be derivative through the contractor but direct against the owner. The property competed for would not be the property of the contractor at all. The surety would not have a lien on the chose in action. A claimant against the contractor, like the Government here, would have no standing to assert rights against this chose in action running directly from the owner to the surety. Thus no questions of priority or “relating back” would be involved.

The Supreme Court in United States v. Munsey Trust Co., 332 U.S. 234, 67 S.Ct. 1599, 91 L.Ed. 2022, has expressly rejected this theory that a surety is the promisee of a promise by the owner to reimburse him out of withheld funds for expenditures made in fulfillment of his obligation to make good the default of the contractor in failing to pay laborers and materialmen. In the Munsey Trust case a contractor had failed to carry out its obligation to pay its laborers and materialmen in accordance with its contract with the Government which occupied the position of owner in that case. The surety had paid the laborers and materialmen and sought to recover retained percentages from the Government. The Government pleaded as set-offs sums due from the contractor on account of breaches of other contracts. The surety urged the very point here under discussion, saying that there was a direct promise by the Government to the surety which could not be affected by any sum owed by the. contractor to the Government under some other contract. The court rejected the argument saying, 332 U.S. at page 243, 67 S.Ct. at page 1604:

“Respondent’s contention then comes to this: that by requiring the contractor to furnish assurances that he will perform his obligations to laborers and materialmen, the government has deliberately decreased the ordinary safeguards it would have had to enforce the contractor’s obligations to it. We see nothing in the words of the contract or the statute to lead us to this conclusion.”

The owner certainly could not have set off against the obligation to pay the withheld cash a debt due from the contractor as permitted in the Munsey Trust case if, as the surety here contends, the obligation ran direct to the surety.

The surety advances another theory under which, as is asserted, the contractor would be without any interest in the withheld funds to which the Government tax liens could attach. It is contended that, at the time of the accrual of the Government’s tax liens against the contractor, the contractor, not having paid his laborers and materialmen, had no right to the withheld funds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Dutcher Construction Corporation
197 F. Supp. 441 (W.D. New York, 1961)
National Surety Corporation v. Fisher
317 S.W.2d 334 (Supreme Court of Missouri, 1958)
Wolverine Insurance Company v. Phillips
165 F. Supp. 335 (N.D. Iowa, 1958)
Colusa-Glenn Production Credit Ass'n v. Phoenix Insurance
145 F. Supp. 844 (N.D. California, 1956)
COLUSA-GLENN PRODUCTION CR. ASS'N v. Phoenix Ins. Co.
145 F. Supp. 844 (N.D. California, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
140 F. Supp. 298, 49 A.F.T.R. (P-H) 1072, 1956 U.S. Dist. LEXIS 3457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-new-york-city-housing-authority-nysd-1956.