F. H. McGraw & Co. v. Sherman Plastering Co.

60 F. Supp. 504, 33 A.F.T.R. (P-H) 1359, 1943 U.S. Dist. LEXIS 1659
CourtDistrict Court, D. Connecticut
DecidedApril 10, 1943
DocketCivil Action 368
StatusPublished
Cited by25 cases

This text of 60 F. Supp. 504 (F. H. McGraw & Co. v. Sherman Plastering Co.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. H. McGraw & Co. v. Sherman Plastering Co., 60 F. Supp. 504, 33 A.F.T.R. (P-H) 1359, 1943 U.S. Dist. LEXIS 1659 (D. Conn. 1943).

Opinion

HINCKS, District Judge.

This is an action of interpleader brought by F. H. McGraw & Company, the general contractor for the construction of a State Hospital at Newtown, Fairfield County, Connecticut, against Sherman Plastering Company, Inc., a subcontractor, and John T. D. Blackburn, Inc., and Milcor Steel Company, both materialmen of the Sherman Company, all of whom were named as adverse claimants to a fund of some $5,000 claimed to comprise the unpaid balance in the plaintiff’s hands of the payments promised to the Sherman Company under the subcontract. Other defendants, citizens both of New York and Connecticut named in the complaint, were defaulted for failure to plead.

The defendants Blackburn, Inc., and Mil-cor Steel each answered and filed both a counterclaim against the plaintiff and a cross-complaint against the Aetna Casualty & Surety Company, which as the surety on the plaintiff’s bond they had cited in as a third-party defendant.

Findings.

Jurisdictional and General Facts.

1. F. H. McGraw & Company, Inc. (hereinafter referred to as McGraw), is a New Jersey corporation and McGraw at all times mentioned in the complaint was engaged in business as a general contractor and builder, authorized to do business in Connecticut.

2. The Aetna Casualty and Surety Company (hereinafter referred to as Aetna) is-' a Connecticut corporation, and is authorized to engage in the business of a surety company in Connecticut.

3. Milcor Steel Company (hereinafter referred to as Milcor) is a Delaware corporation.

4. John T. D. Blackburn, Inc. (hereinafter referred to as Blackburn) is a New York corporation.

5. Sherman Plastering Company, Inc. (hereinafter referred to as Sherman) is a New York corporation.

6. On August 16, 1938, McGraw was awarded by the State of Connecticut the contract for the construction of the Continued Treatment Units, Fairfield State Hospital, Newtown, Connecticut, hereinafter referred to as the “Fairfield job.”

7. On August 16, 1938, McGraw, as principal, and Aetna, as surety, executed and delivered to the State of Connecticut a bond in the principal amount of $1,446,-000 to secure stated obligations of McGraw under its contract with the State.

8. Said bond has been and now is held by the Commissioner of Public Works of the State of Connecticut for the use and benefit of materialmen on the said Fair-field job.

9. The condition of said bond is as follows:

“Now therefore, if the .said Principal shall promptly pay for all materials furnished and labor supplied or performed in the prosecution of the work included in and under the aforesaid contract whether or not the material or labor enter into and becomes *507 a component part of the real asset, then this obligation shall be null and void, otherwise it shall remain and be in full force and effect.

“Any party, whether a subcontractor or otherwise, who furnishes materials or supplies or perform labor or services in the prosecution of the work under this contract and who is not paid therefor, may bring a suit on this bond in the name of the State, prosecute the same to a final judgment and have execution thereon for such sum or sums as may be justly due, provided, however, that the State .shall not be liable to furnish counsel nor for the payment of any costs or expenses of any such suit.”

10. On September 1, 1938, McGraw subcontracted in writing, Exhibit 2, with Sherman for the latter to do certain work, and to furnish certain materials upon the Fairfield job, including the metal furring, metal lathing, corner beads, base beads and plastering. Under this subcontract Sherman promised to furnish labor and material for the Fairfield job “in accordance with the .specifications, general conditions,” etc., of McGraw’s principal contract with the State of Connecticut. And by the terms of the general conditions of the principal contract every subcontractor was to agree “to be bound to the contractor * * * and to assume toward him all the obligations and responsibilities that he * * * assumes toward the owner.” And the owner, i. e., the State of Connecticut, reserved the right not only to withhold from the contractor so much of the approved payments due him as might be necessary “to assure the payment of just claims then due and unpaid of any person supplying labor or materials for the work” but also to terminate the contract if “the contractor shall fail to make prompt payment to persons supplying labor or materials for the work.” Moreover, the subcontract contained an express provision requiring Sherman “in case of any lien or liens upon .said work or materials by reason of any indebtedness for labor and materials accrued against the contractor (Sherman), to pay the same or cause the same to be discharged by giving a bond.”

11. McGraw discharged all its obligations to Sherman under its subcontract but withheld payment of the sum of $5,382.90 which sum upon the bringing of this action McGraw deposited in the registry of the court.

12. Blackburn and Milcor both supplied materials to Sherman which were used under Sherman’s contract with McGraw in the Fairfield job and each has made claim in excess of $5,382.90 against McGraw and against Aetna on account of the materials thus sold and used.

13. Prior to action brought, neither Sherman nor Milcor made any claim against McGraw to moneys claimed to be due from McGraw under its subcontract with Sherman described in Paragraph 10 hereof. By counterclaim and third-party complaint both claimed against McGraw and Aetna under the bond referred to in Paragraphs 7, 8 and 9 hereof.

14. Prior to action brought, Blackburn made claim against McGraw for moneys claimed to be due and owing from McGraw to Sherman under the subcontract. And by counterclaim and third-party complaint herein Blackburn also is pressing its claim against McGraw and Aetna under said bond.

Facts Bearing Particularly upon McGraw-Milcor Relationship.

15. The materials furnished by Milcor as set forth in Paragraph 12 were delivered on the job in Connecticut between August 30, 1939 and October, 1939, and were sold to Sherman at prices which in the aggregate amounted to $6,372.51.

16. No part of the purchase price therefor has been paid, and Sherman is still indebted to Milcor therefor.

Facts Bearing Particularly upon McGraw-Blackburn Relationship.

17. The materials furnished by Blackburn as set forth in Paragraph 12 were delivered on the job in Connecticut between March 24, 1939, and January 9, 1940. Those delivered prior to July 19, 1939, were fully paid for by Sherman and are not involved • in this action. Those delivered after July 19, 1939, were sold to Sherman at prices which in the aggregate (exclusive of an item of $68. for materials returned) amounted to $9,009.64.

18. The Blackburn sales were made on orders made and accepted in the State of New York, and possession of the goods sold passed from Blackburn or its agent in New York or Ohio to common carriers through whom the goods were delivered to Sherman on the job in Connecticut. From its contract as interpreted in the light of *508

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Yano
997 P.2d 68 (Hawaii Intermediate Court of Appeals, 2000)
Trinity Universal Insurance Co. v. Bellmead State Bank of Waco
396 S.W.2d 163 (Court of Appeals of Texas, 1965)
K & G CONSTRUCTION CO. v. Harris
164 A.2d 451 (Court of Appeals of Maryland, 1960)
United States v. Peden Iron & Steel Co.
330 S.W.2d 635 (Court of Appeals of Texas, 1959)
Catalina Properties, Inc. v. United States
166 F. Supp. 763 (Court of Claims, 1958)
Central Surety & Insurance Corp. v. Martin Infante Co.
164 F. Supp. 923 (D. New Jersey, 1958)
Pollyea v. Grodsky
315 S.W.2d 460 (Missouri Court of Appeals, 1958)
General Electric Co. v. Anchor Casualty Co.
87 N.W.2d 639 (Supreme Court of Minnesota, 1958)
Steelcraft Manufacturing Co. v. Hewkin
148 F. Supp. 872 (E.D. Illinois, 1956)
United States Fidelity and Guaranty Co. v. Miller
143 F. Supp. 941 (W.D. North Carolina, 1956)
Fidelity & Deposit Co. v. New York City Housing Authority
140 F. Supp. 298 (S.D. New York, 1956)
Transmix Concrete of Rockdale v. United States
142 F. Supp. 306 (W.D. Texas, 1956)
Tanenbaum Textile Co. v. Vogue Foundations, Inc.
116 A.2d 697 (New Jersey Superior Court App Division, 1955)
Scott v. Zion Evangelical Lutheran Church
70 N.W.2d 326 (South Dakota Supreme Court, 1955)
Bankers Title and Abstract Co. v. Ferber Co.
105 A.2d 408 (Supreme Court of New Jersey, 1954)
United States v. Crosland Const. Co.
120 F. Supp. 792 (E.D. South Carolina, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
60 F. Supp. 504, 33 A.F.T.R. (P-H) 1359, 1943 U.S. Dist. LEXIS 1659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-h-mcgraw-co-v-sherman-plastering-co-ctd-1943.