Wolf v. Aetna Indem. Co. of Hartford

126 P. 470, 163 Cal. 597, 1912 Cal. LEXIS 445
CourtCalifornia Supreme Court
DecidedAugust 26, 1912
DocketS.F. No. 5867.
StatusPublished
Cited by6 cases

This text of 126 P. 470 (Wolf v. Aetna Indem. Co. of Hartford) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolf v. Aetna Indem. Co. of Hartford, 126 P. 470, 163 Cal. 597, 1912 Cal. LEXIS 445 (Cal. 1912).

Opinion

ANGELLOTTI, J.

This is an action on a bond given by B. W. Lattimore, as principal, and the Aetna Indemnity Com- *599 party of Hartford, Connecticut, a corporation, as surety, in the penal sum of four thousand dollars, upon a building contract. Lattimore, who was a party defendant, defaulted. The case was tried as between plaintiffs and the surety defendant, and judgment was given in favor of plaintiffs and against the surety and Lattimore for four thousand dollars. This is an appeal by the surety from the judgment and from an order denying its motion for a new trial.

The complaint alleged the making of the building contract by plaintiffs (the owners) .and Lattimore, a copy of which (exclusive of the plans and specifications according to which the building was to be built) was annexed, the giving by Lattimore and the surety of the bond in suit, a copy of which was also annexed, that Lattimore began work under the contract and was paid in accord with the terms of the contract on account of the contract price of sixteen thousand dollars, the first, the second, and third payments, aggregating eight thousand five hundred dollars; that on or about July 20, 1908, he, without fault on plaintiffs’ part, ceased and abandoned work under the contract, and refused to go on therewith; that plaintiffs notified the surety thereof and demanded that it assume and complete the contract as provided in its bond, but that it refused to do so; and that thereafter plaintiffs proceeded to complete such contract and did complete it in accord with the terms thereof at a necessary cost of twelve thousand dollars. It was further alleged that Lattimore had failed to keep said building free and clear of claims of lien, claims to the extent of two thousand dollars having been recorded and being charges against the same, but on the trial plaintiffs introduced no evidence on this score and waived all claim against the surety on account thereof. The trial court adopted, probably because the findings were so prepared by counsel, the unsatisfactory method of finding simply generally “that each and all of the allegations of the plaintiffs’ complaint are true and are sustained by the evidence and that each and all of the denials and allegations in the answer of the said defendant The Aetna Indemnity Company are untrue and are not sustained by the evidence.’’ Clearly, in the respect just mentioned there is no evidence to sustain the findings, but, of course, this fact is immaterial if the findings are sustained in all other respects. The amount of the bond and, consequently, *600 the amount of the judgment is only four thousand dollars, which is less than the amount alleged to have been necessarily expended by plaintiffs in the completion of the contract, over and above the amount of the contract price remaining after making the three alleged payments to Lattimore.

It is claimed that the second and third payments by plaintiffs to Lattimore were prematurely made, and that the evidence was insufficient to support a contrary conclusion, with the result that the surety should be held discharged from liability. The contract provided in regard to the first three payments that the first payment, three thousand dollars, was to be made “when entire concrete foundation walls are in and second story floor joists are laid,” the second payment, three thousand dollars, “when entire frame is up, building enclosed and roof on,” and the third payment, two thousand five hundred dollars, “when entire building is brown coated.” It was expressly provided therein: “that when each payment, or installment shall become due, and at the final completion of the work, certificates in writing shall be obtained from the said architect, stating that the payment or installment is due or work completed, as the case may be, and the amount then due; and the said architect shall at said times deliver said certificates under his hand to the contractor, or, in lieu of such certificates, shall deliver to the contractor in writing, under his hand, a just and true reason for not issuing the certificates, including a statement of the defects, if any, to be remedied, to entitle the contractor to the certificate or certificates. ’ ’ The three payments were made respectively April 18, 1908, May 3, 1908. and June 20, 1908. Each was made on the certificate of the architect, stating that the same was due to the contractor. It is claimed that the evidence is not sufficient to sustain a conclusion that at the time of the second payment the building was “enclosed” within the meaning of the contract, the provision of the contract as to this payment being “when entire frame is up, building enclosed and roof on. ’ ’ The entire frame was up and the roof on at such time. There -was ample evidence to sustain a conclusion that the sides and rear elevations were covered with the sheeting paper and rustic called for by the specifications, and that the Oregon pine sheeting called for on the front elevation had been put on. The plans and specifications required that rustic or ship-lap should be *601 put on the front elevation over the pine sheeting, and this had not been done, at least entirely, at the time of the second payment. Although the plans and specifications were in evidence in the lower court, they are not contained in the record on appeal, and we have no means of determining whether their provisions would throw any light upon the question what is meant by the term “building enclosed” in the provision that we have quoted from the contract, except so far as the testimony of Lattimore and the architect assist in that regard. Lattimore testified substantially that the “plans and specifications” required that the front should have both sheeting and rustic on at the time of such payment. There was no dispute that the specifications called for both sheeting and rustic on the front, and we think it is clear that this requirement is the whole basis of Lattimore’s testimony that both should be on before the second payment should become due, for we know that neither plans nor specifications would ordinarily contain any provision as to the times when payments shall be made. On the other hand, the architect testified most positively that all the payments “were made in conformity with the plans and specifications and the terms of the contract.” This was tantamount to saying that the building was “enclosed” within the meaning of the contract at the time of the second payment. With sufficient evidence as to the actual condition to warrant a conclusion that the sides and rear elevations were fully covered by rustic, and the front elevation by the Oregon pine sheeting, we are satisfied that it must be held there was enough in the testimony of the architect to sustain a conclusion that the building was “enclosed” within the meaning of that word as used in the contract, at the time of the making of the second payment. It is not disputed that the entire building was “brown coated” at the time the third payment was made, the objection as to such payment being the same as that in regard to the second payment, viz.: that the building had not then been “enclosed.” What we have said in regard to the second payment disposes of this objection. There is nothing in Bacigalupi v. Phoenix Building & Construction Co., 14 Cal. App. 632, [112 Pac. 892], in conflict with our conclusion herein.

It is further claimed that the finding that the third payment was made to Lattimore is not sustained by evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Verdugo Highlands, Inc. v. Security Insurance
240 Cal. App. 2d 527 (California Court of Appeal, 1966)
Calimpco, Inc. v. Warden
224 P.2d 421 (California Court of Appeal, 1950)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Somers v. United States Fidelity & Guaranty Co.
217 P. 746 (California Supreme Court, 1923)
Doyle v. Faust
153 N.W. 725 (Michigan Supreme Court, 1915)
Young Men's Christian Ass'n v. Ritter
133 P. 894 (Supreme Court of Kansas, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
126 P. 470, 163 Cal. 597, 1912 Cal. LEXIS 445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolf-v-aetna-indem-co-of-hartford-cal-1912.