George A. Hormel & Co. v. American Bonding Co.

128 N.W. 12, 112 Minn. 288, 1910 Minn. LEXIS 863
CourtSupreme Court of Minnesota
DecidedOctober 28, 1910
DocketNos. 16,611—(10)
StatusPublished
Cited by55 cases

This text of 128 N.W. 12 (George A. Hormel & Co. v. American Bonding Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George A. Hormel & Co. v. American Bonding Co., 128 N.W. 12, 112 Minn. 288, 1910 Minn. LEXIS 863 (Mich. 1910).

Opinions

Start, C. J.

On October 28, 1908, the plaintiff, hereinafter referred to as the owner, entered into a written contract with J. W. Hilliard, hereinafter referred to as the contractor, whereby he was to erect at Duluth a cold storage warehouse for the owner in accordance with the plans and specifications therefor which were a part of the contract. The contract price was $19,500, in consideration of which the contractor undertook to furnish all materials and perform all the labor for the erection of the warehouse, protect it from liens, and complete it by March 1, 1909. The other provisions of the contract, which are here material, are these:

“No alterations shall be made in the work, except upon written order of the architects. * * *

“The owner reserves the right to make changes in the plans and •specifications as may be necessary. If the alterations increase or [291]*291■decrease the cost, the contract price shall be increased or decreased in fair proportion. The architect is the arbiter of the amount, and it shall be fixed before the work proceeds. * * * Changes will not invalidate the contract nor increase the time within which the work is to be completed, unless it can be shown changes have caused delay. If extension of time is agreed to by the contractor and owner, the contractor is to notify the surety company.

“If the owner desires any extra work, it shall be on written order of the owner or architect. * * * Itemized bills for extras will be presented at the close of the week during which they are performed, and, if approved, paid at the next monthly payment day. * * *•

“Monthly payment certificates for eighty-five per cent, of the cost of the work performed and material delivered which is to become a part of the permanent structure shall be issued about the first of each calendar month by the architect or superintendent, on presentation from the contractor of a statement showing the cost of the materials and labor and the unwrought materials delivered. * * *

“The contractor will furnish a bond for thirty-three and one-third per cent, of the amount of his contract to guarantee the faithful performance thereof. The surety company’s terms are in no way to invalidate the terms of the contract between the parties hereto.”

The appellant, hereinafter referred to as the surety company, gave the required bond, which contained the provisions, with others following : “The owner shall keep, do and perform each and every, all and singular, the matters and things set forth and specified in said contract to be by the -owner kept, done and performed, exclusively at the times and in the manner as in said contract specified, provided-that, said surety shall be notified in writing of any breach of said contract by said principal, or of any act on the part of the said principal, or his agent or employees, which may involve a loss for which the said surety may be liable hereunder, immediately after the occurrence of such act shall have come to the knowledge of said owner.”

The contractor did not protect the warehouse from liens, and the -owner .was eompelled'to and did pay $7,615.65 in discharge of valid [292]*292liens thereon, and thereupon brought this action in the district court of the county of St. Louis against the surety company on its bond to recover the amount so paid. The surety company answered to the effect that the bond was released, for the reasons that changes in the work were made and extras ordered orally, and not on the written order of the owner or architect; that payments were made to the contractor in a manner not authorized by the contract; and, further, that immediate notice was not given to■ the surety company by the owner of the alleged failure of the contractor to complete the contract within the time limited and to pay his bills for materials and labor.

At the close of the evidence the surety company requested a directed verdict in its favor for the alleged reason, in effect, that upon the evidence the owner was not entitled to recover. The motion was denied, the ruling excepted to, and the issues tendered by the answer submitted to the jury, with instructions, none of which was excepted to at any time. Verdict for the owner in the sum of $1,725.19. No motion for a new trial was made, but a motion was made for judgment in favor of the surety company notwithstanding the verdict, which was denied, and judgment entered upon the verdict, from which this appeal was taken.

The sole question for our decision is whether, upon the record as it stood at the close of the evidence, the surety company was, as a matter of law, entitled to a verdict in its favor. The answer to the question depends upon whether there was any evidence, taking the most favorable view of it for the owner, reasonably tending to show that it was entitled to a verdict in any amount. If there was not, then a verdict should have been directed as requested. If there was, then the requested instruction was rightly refused.

The answer cannot be controlled in any respect by the instructions of the court to the jury in'submitting to them the issues made by the pleadings; for the charge of the court as to either the law or facts, although not excepted to, is not the law of the case, as appellant claims. If the refusal to direct a verdict as requested was wrong, because there was no evidence to support any different verdict, the error could not be corrected by any charge which did not in effect grant the request. On the other hand, if there was such. [293]*293evidence, the ruling was correct, and no instructions in submitting the issues could make it erroneous. The charge, however, is entitled to consideration so far as it indicates the opinion of the learned trial judge as to the law and facts of the case.

In considering the question whether the surety company was entitled to a directed verdict for any of the reasons here urged, we must keep in view the character of contracts of suretyship of corporations organized for the purpose of engaging, for profit, in the business of guaranteeing the fidelity or contracts of a third party, and the rules of construction applicable to their contracts. While such contracts in form resemble those of suretyship, they are in effect contracts of insurance, to which the rules of construction peculiar to contracts of suretyship proper do not apply, but to which the rules governing ordinary insurance contracts are applicable. 32 Cyc. 307. 27 Am. & Eng. Enc. (2d Ed.) 452, §§ 174, 179, and 208; Lakeside Land Co. v. Empire State Surety Co., 105 Minn. 213, 117 N. W. 431; Brandrup v. Empire State Surety Co., 111 Minn. 376, 127 N. W. 424.

The rule of construction applicable to a contract of insurance, in cases where, as in this one, the legislature has not prescribed a standard policy, is settled to the effect that if there is any ambiguity in the language of a condition, or it is fairly open to two constructions, one of which will uphold and the other defeat the claim of the insured, that should be adopted which is most favorable to the insured. The rule of strict construction against the insurer and the liberal one in favor of the insured must prevail under such circumstances. If, however, the terms of the contract be clear, and not fairly susceptible of two constructions, an ambiguity cannot be assumed, and the plain intention of the parties nullified by construction. Loy v. Home Ins. Co., 24 Minn. 315, 31 Am. Rep. 346; American Surety Co. v. Pauly, 170 U. S. 133, 18 Sup. Ct. 552, 42 L. ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haddock Construction Co. v. Wilber
169 P.2d 599 (Oregon Supreme Court, 1946)
Farmers State Bank of Madelia, Inc. v. Burns
4 N.W.2d 330 (Supreme Court of Minnesota, 1942)
MacNear v. Malow
276 N.W. 433 (Michigan Supreme Court, 1937)
Moore v. Maryland Casualty Co.
12 F. Supp. 90 (D. Massachusetts, 1935)
Cary v. National Surety Co.
251 N.W. 123 (Supreme Court of Minnesota, 1933)
American Surety Co. v. Plank & Whitsett, Inc.
165 S.E. 660 (Supreme Court of Virginia, 1932)
American Surety Co. of N.Y. v. Noe
53 S.W.2d 178 (Court of Appeals of Kentucky (pre-1976), 1932)
Young Men's Christian Association's Assignee v. Indemnity Insurance Co. of North America
51 S.W.2d 463 (Court of Appeals of Kentucky (pre-1976), 1932)
Tapping v. McIntosh
140 So. 773 (Supreme Court of Florida, 1932)
Title & Trust Co. v. United States Fidelity & Guaranty Co.
7 P.2d 805 (Oregon Supreme Court, 1931)
Bullock v. New York Life Insurance Co.
233 N.W. 858 (Supreme Court of Minnesota, 1930)
Maryland Casualty Co. v. Palmetto Coal Co.
40 F.2d 374 (Fourth Circuit, 1930)
Southern Surety Co. v. Austin
17 S.W.2d 774 (Texas Commission of Appeals, 1929)
Maglione v. Penta
266 Mass. 413 (Massachusetts Supreme Judicial Court, 1929)
National Surety Corp. v. Seward
165 N.E. 588 (Ohio Court of Appeals, 1928)
Mountrail County v. Farmers State Bank
208 N.W. 380 (North Dakota Supreme Court, 1926)
Farmers & Merchants State Bank v. Fidelity & Deposit Co. of Maryland
204 N.W. 33 (Supreme Court of Minnesota, 1925)
State ex rel. Davis v. Kilgore State Bank
201 N.W. 901 (Nebraska Supreme Court, 1924)
Smietanka v. Rawson
232 Ill. App. 411 (Appellate Court of Illinois, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
128 N.W. 12, 112 Minn. 288, 1910 Minn. LEXIS 863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-a-hormel-co-v-american-bonding-co-minn-1910.