Farmers State Bank of Madelia, Inc. v. Burns

4 N.W.2d 330, 212 Minn. 455, 1942 Minn. LEXIS 644
CourtSupreme Court of Minnesota
DecidedMay 22, 1942
DocketNos. 32,994, 32,995.
StatusPublished
Cited by6 cases

This text of 4 N.W.2d 330 (Farmers State Bank of Madelia, Inc. v. Burns) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmers State Bank of Madelia, Inc. v. Burns, 4 N.W.2d 330, 212 Minn. 455, 1942 Minn. LEXIS 644 (Mich. 1942).

Opinions

Julius J. Olson, Justice.

Defendant city of Owatonna and intervener, New York Casualty Company, separately appeal from orders denying their respective motions for amended findings or a new trial.

*457 In April 1939, defendant Burns, as contractor, entered into an agreement with the village of Madelia for the construction of certain street improvements. He applied to intervener, hereafter referred to as the surety, for the bond required by Mason St. 1927, § 9700, and it duly executed his performance bond as surety. By the terms of his application for the bond, Burns agreed that the surety should “be subrogated to all the rights and properties of the Indemnitor(Italics supplied.) This also included deferred and reserved payments due him or to become due, whether earned under progress estimates or final payments. He also pledged “all moneys and securities that may be due and payable * * * on * * * any other contract of the Indemnitor * * * on which the Surety * * * may become surety.” It is upon this instrument that the surety now rests its right of recovery, since it took a loss of something like $1,300 on that job.

In the performance of the Madelia contract, Burns from time to time secured from plaintiff funds with which to meet payments of laborers and materialmen. The $4,400 in the form of notes given plaintiff were credited to his account, and, Burns testified, “I used it for paying labor and material bills on the job.” It is thus evident that to the extent represented. by these obligations plaintiff is much more than a mere stranger, volunteer, or general creditor of Burns in these transactions.

On July 5, 1939, Burns took over a similar job for Owatonna, the earnings from which are presently involved. Under the terms thereof, Burns agreed to “furnish all of the material and perform all of the work” provided for by the contract. And the city agreed to “pay” him, upon progress estimates, “such sums as result from the following unit prices, and the actual quantities constructed, to the satisfaction of the Engineer.” On July 14, Burns assigned this contract to plaintiff to secure the indebtedness incurred on the Madelia job and “any future advances” to be made thereafter. The assignment adequately identifies the Owatonna contract, and conclusively embodies the purpose and intent by both Burns and the bank that further funds were to be made *458 available in the performance of the Owatonna job. ' Thereby Owatonna was authorized and directed “to make payment of any and all money due or to become due” Burns thereunder to plaintiff, which was authorized to “receive and receipt” for such payments in the “place and stead” of Burns. The bank wás appointed “his true and lawful attorney to sue for and recover and receive any and all sums due or to become due from the City.”. On July 18, Owatonna was properly notified of the assignment. In the performance of that job the bank financed Burns with additional sums, which were used by him at Owatonna in the same manner as he had theretofore employed on the Madelia job. Intervener is also surety on the Owatonna job.

. No notice was given by the ’ surety to Owatonna in respect to its claim under the application for bond in the Madelia deal until November 27, 1989, and “the city had no previous notice” of this claim. This took place after all the work had been finished, final estimate issued, and the job accepted. Owatonna' still holds $1,082.96 earned by Burns under his contract, “which it is willing to pay to the rightful owner thereof.”

For consideration and' decision here there are, primarily, the conflicting claims between plaintiff and' Owatonna (referred to hereafter as the “city”), Burns hot being a party to this appeal. A recital of some additional facts is deemed appropriate.

Included in the contract by reference is a written instrument labeled “General Conditions.” Paragraphs 13 and 15 thereof are important, and these provide (Plaintiff’s exhibit 1, p. 6):

“13. Contract Security: The contractor. shall furnish a surety bond * * * in an amount at least equal to 100 per cent of the contract price as security for the .faithful performance of this contract and for the payment of all persons performing labor and furnishing materials in connection with this contract.
“15. Payment: Not later than the 15th day of each calendar month the city will malee partial/ payment to the contractor on the *459 basis of a duly certified approved estimate of the work performed during the preceding' calendar month by the contractor, but the city will retain 10 per cent of the amount of each such estimate until final completion and acceptance of all work covered by this contract.” (Italics supplied.)

The italicized portion contains the only condition as to when the “city will make” its payments except as to the retained percentage.

On September 1, 1989, Burns had so far proceeded in the performance of his job that progress estimate No. 1 was issued, which, after deducting the agreed retained percentage, entitled him to the payment of $4,095.79. A check for that amount was promptly issued, payable to him, but left in the possession of the city attorney. Plaintiff’s demand for the check or its proceeds was refused upon the claim that there were some labor and material items to be paid. This dispute was adjusted, however, so that $2,316.19 thereof was left with the city attorney and used by him for that purpose. The remainder, $1,779.60, was turned over to. plaintiff. The next estimate came in October 2, entitling Burns to $5,159.75, and in that amount the city again issued its check payable to Burns, but again the possession of the check was left with the city attorney. Plaintiff’s demand for it or its proceeds was refused for the same reason as that assigned when the first payment was made. Without plaintiff’s consent, in fact over its protest, but with the assistance of Burns, the check was then cashed and “nearly all” of its proceeds used by . the city officers in payment of labor and material items going into, the job. Estimates 3, 4, and 5 shared the same fate. So nothing of Burns’s earnings reached plaintiff out of these estimates. Prior thereto, and until the October estimate came in, plaintiff had extended Burns’s credits going into the job in an amount exceeding $5,000. Due to “the insistence of the mayor, and [upon] the advice of our city attorney,” all checks were made payable to Burns but “were turned over to the city attorney” and the proceeds used in payment of *460 labor and material claims. Plaintiff’s interests and rights were wholly ignored; consequently it refused thereafter to honor Burns’s checks.

1. Plaintiff’s cause is founded upon the principles of law laid down in the Waseca case (American Surety Co. v. Board of Co. Commrs. 77 Minn. 92, 79 N. W. 649) and other subsequent cases. These were the facts in that case: The contractor had agreed to build a courthouse for Waseca county. He was to be paid in installments of 85 per cent on monthly estimates of the cost of labor performed and materials furnished. The remaining 15 per cent was to be retained by the county until the building was completed. Plaintiff was the surety on his performance bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iowa Concrete Breaking Corp. v. Jewat Trucking, Inc.
444 N.W.2d 865 (Court of Appeals of Minnesota, 1989)
First Nat. Bank of St. Paul v. McHasco Electric, Inc.
141 N.W.2d 491 (Supreme Court of Minnesota, 1966)
Harding v. Ohio Casualty Insurance
41 N.W.2d 818 (Supreme Court of Minnesota, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
4 N.W.2d 330, 212 Minn. 455, 1942 Minn. LEXIS 644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmers-state-bank-of-madelia-inc-v-burns-minn-1942.