Barrett Bros. Co. v. County of St. Louis

206 N.W. 49, 165 Minn. 158, 1925 Minn. LEXIS 1110
CourtSupreme Court of Minnesota
DecidedNovember 27, 1925
DocketNo. 24,908.
StatusPublished
Cited by22 cases

This text of 206 N.W. 49 (Barrett Bros. Co. v. County of St. Louis) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barrett Bros. Co. v. County of St. Louis, 206 N.W. 49, 165 Minn. 158, 1925 Minn. LEXIS 1110 (Mich. 1925).

Opinion

Stone, J.

Action on an assignment of the earnings of the builder under two contracts with the county of St. Louis for the construction of public highways. Other issues involving other parties were litigated be *159 low, but the only remaining question is one of priority as between plaintiff’s assignment and! the surety’s equity of subrogation. The county and the contractors were the original defendants, the claims of certain laborers, materialmen and Maryland Casualty Company, the surety, having been litigated on complaints in intervention. After findings and an order for judgment in favor of the surety, plaintiff appeals from the judgment.

The contractor was the Mountain Iron General Contracting Company, a copartnership. Its contracts with the county of St. Louis for the two jobs in question and the statutory bond of the surety took effect in January, 1922. The contracts were in the form then in use by the State Highway Department. Although they did not expressly require the contractor to pay for all of the labor and materials used in the work, they did obligate him “to furnish” all such materials and “perform all the work and labor” required to complete the jobs according to plans and specifications which, by reference, were made a part of the agreements. The particular specifications for the two jobs were in evidence below and are before us. The general specifications are not in evidence and we do not consider them except insofar as it is conceded that they called for the payment to the contractor, on progress estimates, of not to exceed 85 per cent of the moneys earned by him, and the retention of the remaining 15 per cent pending completion of the work to the satisfaction of the county. We assume that the contract in that respect availed itself of the unnecessary permission of section 22, chapter 323, L. 1921, under which “the county board may agree * * * to pay the contractor, on account of the contract price, an amount not exceeding eighty-five per cent of the value of the work from time to time actually completed, as shown by monthly estimates thereof, based on the contract price.” Neither the contracts, so far as they are before us, nor the statute, says that this reserved percentage is for the benefit of laborers, materialmen or the contractor’s surety, an omission which, so far as the latter is concerned, we consider immaterial.

*160 Plaintiff, a wholesale grocer, furnished the contractor a large quantity of provisions for use not only on the jobs in question, but on others as well. It has no rights under the contractor’s bond. Its only claim is under the assignment (bearing date of April 21, 1922), from the contractor of all of his earnings under the two contracts. That assignment is absolute in form, and, when this action was commenced to enforce it, there was due from the county to the contractor $5,782.24, which happened to be $2,190.64 more than the retained percentage of $3,591.60. Plaintiff’s demand is for only $828.21.

Plaintiff makes no claim upon the reserved percentage, but argues that its assignment puts its title to the earnings of the assignor, over and above the reserved percentage, beyond attack by the surety. That position is based upon Dowling v. City of Seattle, 22 Wash. 592, 61 Pac. 709; Puget Sound State Bank v. Gullucci, 82 Wash. 445, 144 Pac. 698, Ann. Cas. 1916A, 767; Maryland Casualty Co. v. Washington Nat. Bank, 92 Wash. 497, 159 Pac. 689; N. W. Nat. Bank v. Guardian C. & G. Co. 93 Wash. 635, 161 Pac. 473, Ann. Cas. 1918D, 644; The Title G. & S. Co. v. First Nat. Bank, 94 Wash. 55, 162 Pac. 23; Van Doren R. & C. Co. v. Guardian C. & G. Co. 99 Wash. 68, 168 Pac. 1124. Those cases, if followed, would compel adoption of the argument for appellant. They hold in substance (see particularly Dowling v. Seattle) that, where a public contractor defaults, his surety has no rights “in or to the fund earned and assigned by the contractor,” in excess of the “reserved percentage,” i. e. whatever portion of the builder’s earnings could be or were reserved by express provision of the contract, for the protection of the owner, surely, laborers and materialmen or all of them.

We have examined those cases with deferential care and must' disagree so far as they deny the surety’s equity of subrogation any application to the earnings of his principal in excess of the reserved percentage. The Washington rule seems not to have been followed to any great extent elsewhere. See annotation of Labbe v. Bernard [196 Mass. 551, 82 N. E. 688], in 14 L. R. A. (N. S.) 457.

To sustain that rule, a distinction must be made between two parts of the same fund, the earnings of the contractor being the *161 fund and the two otherwise indistinguishable parts consisting of the reserved percentage on the one hand and the excess on the other. In this case, the former is 15 per cent and the latter 85 per cent of the total. The distinction, if allowed, makes the surety’s equity of subrogation, which in principle is applicable to all rights of the contractor, effective in practice on only 15 per cent of those rights. At least it would enable the contractor, by assignment, to deprive the surety of 85 per cent of the fund, all of w7hieh he is otherwise entitled to claim as subrogee.

That result disregards the fact that the surety’s equity of subrogation attaches to the contract and the prospective earnings of the contractor thereunder at the very moment he becomes surety. The right of subrogation and its automatic equitable assignment “relate to the date of the suretyship, as against the principal and those claiming under him.” McArthur v. Martin, 23 Minn. 74. That “equitable assignment” to the surety of the “principal’s rights and remedies” when completed by the surety's performance of his principal’s obligation “relates back * * * to that earlier time” when the surety first obligated himself as such. Labbe v. Bernard, supra; Prairie State Nat. Bank v. U. S. 164 U. S. 227, 17 Sup. Ct. 142, 41 L. ed. 412. See also Benson v. Saffert-Gugisberg C. Const. Co. 159 Minn. 54, 198 N. W. 297; 161 Minn. 269, 201 N. W. 424.

In this case the contracts and bonds took effect at the same time. In consequence and from that moment, the rights of the contracting parties, the builder and the county, were qualified insofar as they became subject to the surety’s equity of subrogation. It follows that there was no part of the prospective earnings, whether reserved or unreserved, which the contractor could assign to a mere stranger, such as plaintiff, having no independent equity, and thereby given to the assignee a right superior to that of the surety. That is the precise holding, as we understand the decision, in Henningsen v. U. S. F. & G. Co. 208 U. S. 404, 28 Sup. Ct. 389, 52 L. ed. 547, where the surety of a government building contractor was held entitled to all of the earnings of a contractor as against the latter’s assignment to a creditor. True, the effect of the “reserved percentage” provi *162 sion, if any, of the controlling contract was not considered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drewes v. United States (In Re Bukowski)
109 B.R. 932 (D. Minnesota, 1990)
First Nat. Bank of St. Paul v. McHasco Electric, Inc.
141 N.W.2d 491 (Supreme Court of Minnesota, 1966)
HAAF v. Hjelle
130 N.W.2d 217 (North Dakota Supreme Court, 1964)
Peerless Insurance Co. v. Cerny & Associates, Inc.
199 F. Supp. 951 (D. Minnesota, 1961)
Farmers State Bank of Madelia, Inc. v. Burns
4 N.W.2d 330 (Supreme Court of Minnesota, 1942)
Farmers State Bank v. Anderson
263 N.W. 443 (Supreme Court of Minnesota, 1935)
Central Tractor & Equipment Co. v. Betz
260 N.W. 269 (South Dakota Supreme Court, 1935)
Carney v. United States Guarantee Co.
177 A. 157 (Court of Appeals of Maryland, 1935)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
Kelley v. the Northwest Paper Co.
251 N.W. 274 (Supreme Court of Minnesota, 1933)
National Surety Co. v. Wittich
237 N.W. 690 (Supreme Court of Minnesota, 1931)
Fraser v. Farmers Co-Operative Co.
223 N.W. 785 (Supreme Court of Minnesota, 1929)
Investors Syndicate v. Fidelity & Deposit Co.
223 N.W. 139 (Supreme Court of Minnesota, 1929)
Marthaler MacHine & Engineering Co. v. Meyers
218 N.W. 127 (Supreme Court of Minnesota, 1928)
Fidelity & Deposit Co. v. Union State Bank
21 F.2d 102 (D. Minnesota, 1927)
Hartford Accident & Indemnity Co. v. Federal Construction Co.
209 N.W. 911 (Supreme Court of Minnesota, 1926)
Standard Oil Co. v. Remer
209 N.W. 315 (Supreme Court of Minnesota, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
206 N.W. 49, 165 Minn. 158, 1925 Minn. LEXIS 1110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barrett-bros-co-v-county-of-st-louis-minn-1925.