Ganley v. City of Pipestone

191 N.W. 738, 154 Minn. 193, 1923 Minn. LEXIS 604
CourtSupreme Court of Minnesota
DecidedJanuary 12, 1923
DocketNo. 22,968
StatusPublished
Cited by24 cases

This text of 191 N.W. 738 (Ganley v. City of Pipestone) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ganley v. City of Pipestone, 191 N.W. 738, 154 Minn. 193, 1923 Minn. LEXIS 604 (Mich. 1923).

Opinion

Taylor, C.

In July, 191G, plaintiffs, a copartnership doing business under the firm name of Ganley Construction Company, entered into a contract with the city of Pipestone to pave certain streets in that city for the sum of $55,264.42 and executed the statutory bond to secure the performance of their contract and the payment of all claims for labor and material furnished therefor with defendant casualty company as surety thereon. Shortly thereafter they made an arrangement with defendant bank by which they opened an account with the bank in the name of J. H. & J. S. Ganley, and agreed to deposit therein all payments received under the contract with the city, and by which the bank agreed to advance them money as needed to pay claims incurred for labor and material in performing the contract. As a part of this arrangement, plaintiffs gave the bank an order directing the city to repay the bank all sums so advanced by it out of any moneys which should become due plaintiffs under the contract, which order was filed with the city clerk. Part of the paving was done in 1916 and the remainder in 1917. The claims growing out of the work done in 1916 were paid and satisfied and are not involved in this controversy.

In March, 1917, two of plaintiffs together with other parties organized a corporation under the name of Ganley Construction Com[195]*195pany, the same name under which the partnership had done business, and it was evidently understood that the contract in question was to be transferred from the partnership to the corporation. But the city would not consent to the proposed transfer, and the city charter prohibited the assignment or transfer of any contract with the city without the consent of the city. For this, reason, the contract was not transferred but was completed by the plaintiffs as copartners. They seem, however, to have performed the work done in 1917 through the corporation; at least, they gave G. A. Thayer, an officer of the corporation and not a member of the partnership, full charge of the work and he carried it to completion for them.

On June 7, 1917, J. S. Ganley, who was a member of the partnership and also an officer of the corporation, went to the bank with Thayer and made an agreement with the bank to continue in force, during 1917, the arrangement made in 1916 with the single change that the account with the bank was to be carried in the name of G. A. Thayer by whom the checks drawn upon it were to be signed. Thayer began work under the contract in June and completed it September 14, 1917. He deposited in the bank all funds received, including the monthly payments made by the city, and made all payments by checks drawn on the bank. To cover the advances made by the bank he deposited notes from time to time executed by the corporation and received credit for the amount of the notes in his account. The arrangement between plaintiffs and the corporation under which the corporation executed these notes does not clearly appear. When the contract was completed plaintiffs owed considerable sums for labor and material which they were unable to pay and for which the casualty company was liable under its bond, and also a balance to the bank for advances made. The city refused to pay the final instalment of the contract price until all claims for labor and material had been paid and satisfied. Thereupon plaintiffs brought this action to have the court determine the rights, obligations and liabilities of the several parties concerned and to distribute the fund held by the city to those entitled thereto.

Before the trial the casualty company paid and satisfied all claims for labor and material outstanding when the action was brought and [196]*196the present controversy is narrowed to the question whether the casualty company or the bank has the superior right to the money remaining in the hands of the city. The court found that the balance due from the city on this contract was the sum of $7,379.00; that the amount of the claims for labor and material paid by the casualty company under its bond exceeded that sum, and that the balance due the bank for money furnished to pay claims for labor and material on this contract was the sum of $3,466.52. The court held that the bank was entitled to this sum and interest thereon out of the fund in the hands of the city, and that the casualty company was entitled to the remainder of that fund, and rendered judgment accordingly. Both the findings and the judgment cover numerous other matters, some of which will be referred to later. The casualty company appealed.

Thayer began work under the contract held by the partnership in June, 1917, and'completed that contract September 14, 1917. On August 20, 1917, the corporation entered into a contract with the city o'f Pipestone to do certain paving therein specified for the sum of $10,783.24, and the casualty company was the surety on the bond given by the corporation to secure the*performance of this contract. This contract wras entirely separate and distinct from the contract of the previous year with the partnership, but Thayer was also placed in charge of the work under this contract. He commenced the work at once and completed it in November. After beginning work on the corporation contract, all expenditures on both contracts were made in the same manner by checks drawn against the same account and all funds received on both contracts were placed in this account.

The casualty company contends that the bank account in the name of Thayer was a single, continuous account from the time it was opened at the beginning of work on the first or partnership contract in June, 1917, until it was finally closed after the completion of the work on the second or corporation contract; that the deposits therein were credited on the account generally without being applied on any particular indebtedness by either Thayer or the bank; that these deposits must be applied on the oldest debit items of the account; [197]*197that all the advances on the first contract were made prior to September 20, 1917, and, so far as they remained unpaid, were covered by and included in a note of $2,400 made on that date and a prior note of $1,800 made September 8, and. that, as both the advances and the deposits made after that date largely exceeded any amount then due, all amounts advanced on account of the first or partnership contract must be taken as fully paid and satisfied.

In support of this contention the casualty company invokes the well-established rule, announced in Hersey v. Bennett, 28 Minn. 86, 9 N. W. 590, 41 Am. Rep. 271, and other subsequent cases, that where a debtor makes payments on a running account without applying them on specific items of the account and the creditor makes mo such application, the law will apply them on the earliest items. Perhaps it may be said that this is the universal rule where the debtor makes the payments with money or property belonging to himself and which he is free to use or dispose of as he pleases. But the rule does not go to the extent of requiring or permitting payments to be so applied which are made with funds belonging to a third party or impressed with an equity in favor of a third party whose rights would be prejudicially affected by so applying them. Where payments are made from such funds they must be applied so as to protect the interests of the third party, and the creditor will not be permitted to apply them to the earliest items of the account, if doing so be to the detriment of the third party.

In Merchants Ins. Co. v. Herber, 68 Minn. 420, 71 N. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missouri Valley Steel Co. v. New Amsterdam Casualty Co.
148 N.W.2d 126 (Supreme Court of Minnesota, 1966)
First Nat. Bank of St. Paul v. McHasco Electric, Inc.
141 N.W.2d 491 (Supreme Court of Minnesota, 1966)
General Electric Co. v. Anchor Casualty Co.
87 N.W.2d 639 (Supreme Court of Minnesota, 1958)
Goss v. Iverson
238 P.2d 1151 (Idaho Supreme Court, 1951)
County of Audrain Ex Rel. First National Bank of Mexico v. Walker
155 S.W.2d 251 (Missouri Court of Appeals, 1941)
Seaboard Surety Co. v. First Nat. Bank & Trust Co.
121 F.2d 288 (Eighth Circuit, 1941)
Farmers State Bank v. Anderson
263 N.W. 443 (Supreme Court of Minnesota, 1935)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
United States Fidelity & Guaranty Co. v. Armstrong
142 So. 576 (Supreme Court of Alabama, 1932)
Maryland Casualty Co. v. Dupree
136 So. 811 (Supreme Court of Alabama, 1931)
Investors Syndicate v. Fidelity & Deposit Co.
223 N.W. 139 (Supreme Court of Minnesota, 1929)
First National Bank of Chisholm v. O'Neil
223 N.W. 298 (Supreme Court of Minnesota, 1929)
Dickson v. United States Fidelity & Guaranty Co.
117 So. 245 (Mississippi Supreme Court, 1928)
State ex rel. Spillman v. Security State Bank
218 N.W. 407 (Nebraska Supreme Court, 1928)
Strimling v. McDonald
210 N.W. 388 (Supreme Court of Minnesota, 1926)
Kubatzky v. Pittsburgh Plate Glass Co.
1926 OK 734 (Supreme Court of Oklahoma, 1926)
Hartford Accident & Indemnity Co. v. Federal Construction Co.
209 N.W. 911 (Supreme Court of Minnesota, 1926)
Farmers & Merchants State Bank v. S. J. Groves & Sons Co.
210 N.W. 37 (Supreme Court of Minnesota, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
191 N.W. 738, 154 Minn. 193, 1923 Minn. LEXIS 604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ganley-v-city-of-pipestone-minn-1923.