In re the Receivership of United Prairie Bank, Respondent, vs. Molnau Trucking LLC, et al., Defendants, Granite Re, Inc....

CourtSupreme Court of Minnesota
DecidedJuly 16, 2025
DocketA231478
StatusPublished

This text of In re the Receivership of United Prairie Bank, Respondent, vs. Molnau Trucking LLC, et al., Defendants, Granite Re, Inc.... (In re the Receivership of United Prairie Bank, Respondent, vs. Molnau Trucking LLC, et al., Defendants, Granite Re, Inc....) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Receivership of United Prairie Bank, Respondent, vs. Molnau Trucking LLC, et al., Defendants, Granite Re, Inc...., (Mich. 2025).

Opinion

STATE OF MINNESOTA

IN SUPREME COURT

A23-1478

Court of Appeals Hennesy, J. Took no part, Procaccini, J. In re the Receivership of United Prairie Bank,

Respondent,

vs.

Molnau Trucking LLC, et al.,

Defendants,

Granite Re, Inc., Filed: July 16, 2025 Office of Appellate Courts Appellant.

________________________

Thomas H. Boyd, Andrew J. Steil, Kyle R. Kroll, Winthrop & Weinstine, P.A., Minneapolis, Minnesota, for respondent.

Daniel R. Gregerson, Daniel A. Ellerbrock, Nicholas J. Sideras, Gregerson, Rosow, Johnson & Nilan, Ltd., Minneapolis, Minnesota, for appellant.

Joseph J. Witt, Teresa E. Rice, Minnesota Bankers Association, Eden Prairie, Minnesota, for amicus curiae Minnesota Bankers Association.

Patrick J. O’Connor, Jr., POConnor ADR LLC, Minneapolis, Minnesota, for amicus curiae Surety & Fidelity Association of America.

1 SYLLABUS

1. A performing construction surety need not show any mistake of fact to

exercise its right of equitable subrogation.

2. A surety’s right to equitable subrogation is not a security interest subject to

the Uniform Commercial Code (UCC), Minn. Stat. §§ 336.9-101 to 336.9-809 (2022), and

the UCC’s first-in-time priority rule. Instead, through the doctrine of equitable

subrogation, a performing surety has priority over a secured creditor as to contract funds

created by the surety’s performance on its bond obligations.

Reversed and remanded.

OPINION

HENNESY, Justice.

This appeal arises from a dispute between a surety bond company, appellant Granite

Re, Inc. (Granite), and a creditor bank, respondent United Prairie Bank (UPB), regarding

entitlement to funds held by a receiver in a receivership action. Granite issued payment

bonds to Molnau Trucking LLC (Molnau) for public works projects. Molnau defaulted on

the public works projects. Molnau also defaulted on loans from UPB. At issue is whether

Granite or UPB has priority to the bonded contract funds held by the receiver. Granite

argues that it has priority as a performing construction surety under the doctrine of

equitable subrogation because it paid laborers and suppliers for their work on the projects.

UPB argues that it has priority under the Uniform Commercial Code (UCC), Minn. Stat.

§§ 336.9-101 to 336.9-809 (2022), because UPB perfected its security interests in

Molnau’s accounts receivable before Granite issued the payment bonds. We conclude that

2 Granite, as the construction surety, has the superior interest in the bonded contract funds

as a matter of law, and we therefore reverse the court of appeals decision affirming the

district court’s grant of summary judgment in favor of UPB and we remand to the district

court.

FACTS

The relevant events in this receivership action took place between 2020 and 2023.

During this time, Molnau entered into financial relationships with both UPB and Granite. 1

From April to September 2020, UPB issued three loans to Molnau with a total loan amount

of $3,258,400. As collateral for the loans, Molnau granted UPB security interests in

Molnau’s business assets, which included Molnau’s “accounts,” “money,” “rights to

payment,” and “general intangibles,” all “whether now existing or hereafter arising.”

Immediately after issuing each loan, UPB perfected its security interests in Molnau’s

present and future accounts receivable by filing UCC financing statements with the

Minnesota Secretary of State.

For Molnau to enter into contracts to perform certain public works projects, Molnau

was required to provide bonds to ensure that it would complete the projects and pay the

laborers and suppliers. See Minn. Stat. § 574.26, subd. 2 (2024). In March 2020, Molnau

executed a general agreement of indemnity in favor of Granite, a surety company, as

1 Molnau was a party in the district court action UPB filed but is not a party to this appeal.

3 consideration for Granite issuing these bonds for Molnau as part of a surety relationship. 2

The next year, in the spring of 2021, Molnau entered into construction contracts with

Wright County, the City of Champlin, and the City of Saint Michael (collectively, the

government entities). Granite issued payment and performance bonds for each of these

public works projects. Only the payment bonds are at issue here. Granite issued the

payment bonds several days after the dates of the corresponding contracts. The payment

bonds imposed an obligation on Granite to promptly pay any unpaid claimant for any

undisputed amount, including interest, upon Molnau’s default.

Molnau later failed to pay some of the laborers and suppliers on the public works

projects. The laborers and suppliers filed claims against Granite’s payment bonds. Granite

paid a total of $741,998 to discharge its obligations under the payment bonds.

Molnau also defaulted on its loan agreements with UPB. In December 2021, UPB

sued Molnau for its default and requested that the district court appoint a receiver over

Molnau’s assets, among other relief. The district court appointed a limited receiver to

manage Molnau’s assets.

During the spring and summer of 2022, the receiver worked to identify Molnau’s

assets that were subject to the receivership, which included accounts receivable owed to

2 In this agreement, Molnau agreed to indemnify Granite from any loss or liability resulting from the bonds and agreed that Granite would be subrogated to all Molnau’s rights in any such bonded contracts, “including deferred and reserved payments, current and earned estimates and final payments.” This contractual subrogation right is a distinct remedy from the equitable subrogation right at issue in this opinion.

4 Molnau. The receiver reported on Molnau’s failure to pay laborers and suppliers on the

public works projects, stating:

A number of the Molnau Trucking projects for local municipalities required a performance bond and/or retainage escrow funds to be established as a condition of the various contracts. The Receiver is discovering that a number of these projects were either not completed, had remaining “punch list” issues to address, had unpaid sub-contractors or were generally deficient (per the customer) and the retainage funds and/or underlying performance bonds have or may be accessed to complete these projects. Therefore, much of the accounts receivable asset is either overstated or non-existent.

The receiver contacted Granite and the government entities for information about the

projects. Through this process, the receiver identified certain contract funds in which both

Granite and UPB claimed an interest. These funds would have been due to Molnau under

its contracts with the government entities. Molnau, however, had defaulted on these

contracts, and Granite claimed it was entitled to the funds under the doctrine of equitable

subrogation. At the time the receiver identified the funds, the government entities were

holding some of the funds as retainage 3 and had paid the rest to an escrow company Granite

was using to hold contract funds and disburse payments to claimants. The receiver,

Granite, and UPB all agreed that the funds in dispute should be paid to the receiver, who

would hold them in a segregated account until the dispute was resolved.

At the end of 2022, the receiver filed a motion requesting that the district court set

a briefing schedule for UPB and Granite to assert their claims to the disputed funds. The

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prairie State Bank v. United States
164 U.S. 227 (Supreme Court, 1896)
Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
In The Matter Of J. V. Gleason Co., Inc.
452 F.2d 1219 (Eighth Circuit, 1971)
Citizens State Bank v. Raven Trading Partners, Inc.
786 N.W.2d 274 (Supreme Court of Minnesota, 2010)
First Nat. Bank of St. Paul v. McHasco Electric, Inc.
141 N.W.2d 491 (Supreme Court of Minnesota, 1966)
Nelson Roofing & Contracting, Inc. v. C. W. Moore Co.
245 N.W.2d 866 (Supreme Court of Minnesota, 1976)
Carl H. Peterson Co. v. Zero Estates
261 N.W.2d 346 (Supreme Court of Minnesota, 1977)
Commerce Bank v. West Bend Mutual Insurance Company
870 N.W.2d 770 (Supreme Court of Minnesota, 2015)
Melrose Gates, LLC v. Chor Moua
875 N.W.2d 814 (Supreme Court of Minnesota, 2016)
Ceco Steel Products Corp. v. Tapager
294 N.W. 210 (Supreme Court of Minnesota, 1940)
Barrett Bros. Co. v. County of St. Louis
206 N.W. 49 (Supreme Court of Minnesota, 1925)
Hartford Accident & Indemnity Co. v. Federal Construction Co.
209 N.W. 911 (Supreme Court of Minnesota, 1926)
First National Bank v. Schunk
276 N.W. 290 (Supreme Court of Minnesota, 1937)
Cassan v. Maxwell
40 N.W. 357 (Supreme Court of Minnesota, 1888)
Emmert v. Thompson
52 N.W. 31 (Supreme Court of Minnesota, 1892)
Elliott v. Tainter
93 N.W. 124 (Supreme Court of Minnesota, 1903)
National Surety Co. v. Berggren
148 N.W. 55 (Supreme Court of Minnesota, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
In re the Receivership of United Prairie Bank, Respondent, vs. Molnau Trucking LLC, et al., Defendants, Granite Re, Inc...., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-receivership-of-united-prairie-bank-respondent-vs-molnau-minn-2025.