Bross v. McNicholas

133 P. 782, 66 Or. 42, 1913 Ore. LEXIS 338
CourtOregon Supreme Court
DecidedJuly 15, 1913
StatusPublished
Cited by26 cases

This text of 133 P. 782 (Bross v. McNicholas) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bross v. McNicholas, 133 P. 782, 66 Or. 42, 1913 Ore. LEXIS 338 (Or. 1913).

Opinion

Mr. Justice McNary

delivered the opinion of the court.

The initial error assigned and relied upon by counsel for the defendant, the Pacific Surety Company, is founded upon the refusal of the court to instruct the jury that, “upon the undisputed facts in evidence in this case, you are directed to return a verdict for the defendant the Pacific Surety Company.”

Fully to appreciate the ruling of the court, we deem important' a résumé of the testimony, as this assignment of error gives rise to the most vital phase of the case. Prior to March 30, 1911, the defendant McNicholas, doing business as the National Brick & Clay Company, was the owner of several brickyards in or near the city of Portland, Oregon. Plaintiff, who is a contractor operating in the city, gave testimony, and in corroboration thereof introduced in evidence two bills of sale, to the- effect that he had purchased from McNicholas, at various times between December 29, 1910, and February 8th following, large quantities of bricks, aggregating 750,000, that plaintiff had received on account thereof only 566,744 bricks, and that no delivery had been made under the contract of February 8, 1912, the faithful observance of which was guaranteed by the defendant surety company. It is admitted that bricks purchased, as evidenced by the bills of sale, were not delivered until after the execution of the contract and bond under consideration. True, counsel for the defendant surety company insist the bricks delivered to plaintiff were in virtue of the contract underwritten by the surety, and, if applied as the wisdom of the law directs, would exculpate the surety company from liability.

1, 2. While the authorities are not in harmonious accord, we think that, as a general proposition, the surety cannot direct the application of payments made [46]*46by the principal and the creditor, or either of them. However, this rule is applicable solely in those cases where the principal makes the payment from funds which are his own and are free from any equity in favor of the surety to have the money applied in payment of the debt of which the surety is liable, but where the specific money paid, or property delivered to the creditor, is the identical money or property for the payment and delivery of which the debtor and his surety obligated themselves by the contract and undertaking, the surety is not bound by an application of the money or property to some other debt for which the surety is not liable. In such cases the surety is equitably entitled to have the money paid, or the property delivered, applied to the payment of the debt or the liquidation of the contract for which he is liable: Merchants’ Ins. Co. v. Herber, 68 Minn. 420 (71 N. W. 624); United States v. American Bonding & Trust Co., 89 Fed. 925 (32 C. C. A. 420). Applying this rule to the case at hand, if the bricks delivered by defendant McNicholas to plaintiff were the specific bricks described in the contract, the performance of which the surety company had guaranteed, no liability would attach to the Pacific Surety Company, as the rule announced would require plaintiff to apply the bricks delivered on the contract guaranteed by the bond. But, on the other hand, if the bricks delivered to the plaintiff by McNicholas were the bricks sold or contracted to be sold to plaintiff prior to the execution of the contract and bond for which the surety company was liable, plaintiff had a legal right to place the bricks to the credit of the contract made at a prior time. Under the controversial state of the testimony, the lower court could not direct the jury to return a verdict in favor of the defendant, the Pacific Surety Company, and no error can be predicated thereon.

[47]*473, 4. It is claimed that the trial court erred in giving to the jury the following instructions:

“I instruct you that the words in said bond in this suit ‘shall be immediately notified’ mean promptly and without unnecessary delay after knowledge of a breach of the contract had come to the plaintiff, would not be technical knowledge of the plaintiff. Therefore I instruct you, if you find from the evidence in this case that McNicholas breached his contract in this case, and that such breach came to the knowledge of his representative having supervision of the completion of said contract, and that plaintiff thereafter failed to notify the defendant, Pacific Surety Company, in the manner required in the bond in this action, then plaintiff cannot recover, and your verdict must be for the defendant, Pacific Surety Company.”

Counsel for the surety company argue that plaintiff had knowledge of the breach of the contract on March 30, 1911, but he neglected to give notice thereof until April 7, 1911, which delay forecloses plaintiff to recover upon the bond, in view of the provision that the surety company should be immediately notified of any breach by the principal. To the contrary, plaintiff’s counsel insists the default of the principal was not known until April 7, 1911, and that notice thereof was given on the day following. Again, we are confronted with conflicting testimony. However, be the interim eight days or one day, all the plaintiff was required to do was to notify the surety company of the breach of the contract by the principal with due diligence and within a reasonable time after being apprised thereof. Whether that was done was a question solely for the jury to determine: 4 Cooley, Brief on Insurance, p. 3579; Fidelity & Deposit Co. v. Courtney, 186 U. S. 342 (46 L. Ed. 1193, 22 Sup. Ct. Rep. 833); Bacigalupi v. Phoenix Building Construction Co., 14 Cal. App. 632 [48]*48(112 Pac. 892); Dakin v. Queen City Fire Ins. Co., 59 Or. 269 (117 Pac. 419); Donahue v. Windsor Co. etc. Ins. Co., 56 Vt. 374.

5. The law of suretyship has undergone a considerable change in late years. The day of personal suretyship is fast slipping away, and in its stead comes the corporate surety for profit. This new condition has brought about a new construction of the law. The rules as applied to the insured have been softened, while the rules applicable to the surety have been drawn more stringently. The reason, therefore, lies in the very nature of the transformation. Formerly, a surety was an individual, or collection of individuals, actuated by beneficent motives to carry the burden of suretyship, receiving no profit or benefit, and, in consequence thereof, the law dealt tenderly with him or them. But, in this day and age of corporate sureties, when the burden is lightened by the payment of adequate premiums, and their final liabilities ofttimes secured by counter indemnity, the strictness of the old rule is relaxed, and the modern day surety company must show some injury done before they can be absolved from the contracts which they clamor to execute: Baglin v. Title Guaranty Co. (C. C.), 166 Fed. 356; United States Fidelity & Guaranty Co. v. United States, 178 Fed. 692 (102 C. C. A. 192); Guaranty Co. v. Press Brick Co., 191 U. S. 416 (48 L. Ed. 242, 24 Sup. Ct. Rep. 142); Atlantic Trust Co. v. Laurinburg, 163 Fed. 695 (90 C. C. A. 274). No claim is made by the surety company that the delay of which it complains worked to its injury.

6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Equipment Corp. v. Builders Insurance
108 P.R. Dec. 290 (Supreme Court of Puerto Rico, 1979)
Brock Construction Co. v. Houston General Insurance
243 S.E.2d 83 (Court of Appeals of Georgia, 1978)
State Ex Rel. Salem Pacific Corp. v. Combo Construction Co.
458 P.2d 410 (Oregon Supreme Court, 1969)
Sorge Ice Cream & Dairy Co. v. Wahlgren
137 N.W.2d 118 (Wisconsin Supreme Court, 1965)
National Surety Corp. v. City of Bowling Green
95 S.W.2d 1080 (Court of Appeals of Kentucky (pre-1976), 1936)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
N. O. Nelson Mfg. Co. v. Wallace
66 S.W.2d 505 (Court of Appeals of Texas, 1933)
Southern Surety Co. v. MacMillan Co.
58 F.2d 541 (Tenth Circuit, 1932)
Maryland Casualty Co. v. Fowler
31 F.2d 881 (Fourth Circuit, 1929)
Hogan v. Locke Paddon
267 P. 392 (California Court of Appeal, 1928)
Carey v. Herrick
263 P. 190 (Washington Supreme Court, 1928)
Fitzgerald v. Neal
231 P. 645 (Oregon Supreme Court, 1924)
City of Montpelier v. National Surety Co.
122 A. 484 (Supreme Court of Vermont, 1923)
Ganley v. City of Pipestone
191 N.W. 738 (Supreme Court of Minnesota, 1923)
Consolidated Naval Stores Co. v. Wilson
90 So. 461 (Supreme Court of Florida, 1921)
Alexander Lumber Co. v. Ætna Accident & Liability Co.
129 N.E. 871 (Illinois Supreme Court, 1921)
Sykes v. Sperow
179 P. 488 (Oregon Supreme Court, 1919)
Neilson v. Title Guaranty & Surety Co.
159 P. 1151 (Oregon Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
133 P. 782, 66 Or. 42, 1913 Ore. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bross-v-mcnicholas-or-1913.