The Winston Corporation v. Continental Casualty Company

508 F.2d 1298, 1975 U.S. App. LEXIS 16545
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 17, 1975
Docket73-1886
StatusPublished
Cited by23 cases

This text of 508 F.2d 1298 (The Winston Corporation v. Continental Casualty Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Winston Corporation v. Continental Casualty Company, 508 F.2d 1298, 1975 U.S. App. LEXIS 16545 (6th Cir. 1975).

Opinion

McCREE, Circuit Judge.

This is an appeal from a judgment in a diversity action for defendant-appellee on a performance and payment bond executed by Continental Casualty Company, as surety, in favor of appellant, The Winston Corporation, as obligee. The parties agree that Georgia law applies.

The facts of the case are virtually undisputed. In 1967, Diversified Engineering and Sales Corporation (Diversified) agreed to build for The Winston Corporation (Winston) a nursing home at a cost of $752,874.00. The construction contract required Diversified to obtain a performance and payment bond from an acceptable bonding company. Diversified purchased a bond from Continental Casualty Company (Continental) for a premium of $6,444.00. A copy of the bond, drafted by Continental on its own printed form, was delivered to Winston on October 3, 1967.

The bond expressly incorporated the provisions and specifications of the construction contract and provided, inter alia:

NOW, THEREFORE, THE CONDITION OF THE ABOVE OBLIGATION IS SUCH, that if the above bounden Principal shall well and faithfully perform the things agreed by him to be performed, according to the terms, conditions, and requirements of the foregoing contract; and shall pay all persons who have furnished labor or material for use in or about the improvement; and shall indemnify and save harmless the Obligee, and its officers, agents and employees, from any and all claims for damages, costs, judgments, and other expenses, arising or growing out of this contract; then, this obligation shall be null and void, otherwise, the same shall remain in full force and effect.

Continental issued the bond without reading the construction contract and never even requested a copy of it until approximately two and one-half years later. Continental did, however, investigate the financial condition of Diversified and its principal before it issued the bond. It learned that Diversified had comparatively thin assets, a not uncommon condition for some construction companies, but that Diversified’s principal was financially stable. Before construction began several weeks later, however, Continental discovered that Diversified’s principal was suffering a serious financial setback and that he would no longer be participating in the project. Continental did not object to his withdrawal, and accepted another officer of Diversified as a substitute, even though he had submitted to Continental financial statements overstating his own and Diversified’s net worth.

Continental never communicated any of this unfavorable financial information to Winston.

On December 4, 1967, Winston obtained a construction loan for which it executed a $1,250,000.00 promissory note and security deed. On December 11, the construction lender, the permanent lender, and Winston agreed that the permanent lender would purchase the loan from the construction lender upon completion of the project.

On the next day, Winston instructed Diversified to begin construction in accordance with their contract which provided that the project be completed within 300 calendar days after commencement of construction.

Shortly thereafter, construction began with completion scheduled for mid-October 1968. Upon expiration of the 300 day period, however, the building was far from finished despite Winston’s repeated exhortations. Continental watched closely the developments at the construction site and was fully aware of *1300 the construction delays and problems. In addition, Continental had initiated a lawsuit against Diversified in that same year for non-performance of another construction contract and eventually obtained a favorable judgment.

After the scheduled completion date had passed, Winston officials met with Diversified in January and again in April 1969. In April, the project was still not finished even though more than five months had elapsed since the scheduled completion date. Continental was asked on more than one occasion to attend these meetings convened to resolve construction delays and problems. The surety, however, refused to attend. During discovery proceedings, Winston learned that Continental, as early as April 1968, shortly after construction had begun, had discussed denying that the bond was still in force. These discussions were not communicated to Winston.

In early spring of 1969, Winston faced the following crisis: the construction loan was about to mature; the permanent loan commitment was about to expire; and no progress was being made on the project. Accordingly, on April 7, 1969, after an earlier meeting to which Continental had been invited but refused to attend, Winston and Diversified entered into a letter agreement designed to accelerate construction. This agreement, intended as an assignment of the construction contract, permitted Winston to take possession of the premises, to assume construction of the project, and to take an assignment of Diversified’s subcontracts and other rights. It specifically contemplated, however, Diversified’s continuing participation in the contract. Moreover, one of its provisions stated that the agreement “does not modify or change the existing bond on the project which exists for the owner’s benefit.” The agreement, considered to be the most efficacious method of completing construction at the lowest cost and with the least delay, was believed to be authorized by Contract Article 33 governing assignment.

On the same day, April 7, 1969, Diversified notified Continental by telephone of the letter agreement and mailed a copy of it. Within a few days, Winston took over construction of the nursing home, and it was completed in mid-October 1969, approximately twelve months after the scheduled completion date. Winston took possession of the premises and began nursing operations a month later.

In December 1969, Winston submitted a claim to Continental on the performance and payment bond. When Continental refused to honor the bond, Winston brought this action in United States District Court on June 18, 1970.

The amended complaint alleged that the performance and payment bond had been executed by Continental to guarantee performance of the construction contract between Winston and Diversified; that the construction contract required Diversified to furnish all labor and materials for the construction of a nursing home in Georgia in accordance with certain plans and specifications; that Diversified had failed to do so; and that Continental had failed to honor the bond it issued in connection with the project. It also alleged that Continental had acted tortiously toward Winston by failing to relay to Winston information it learned concerning Diversified’s precarious financial condition.

In 1972, the case was tried before the district court sitting without a jury. Its decision was issued on March 2, 1973, and judgment was entered in favor of Continental. After a motion for reconsideration was denied, notice of appeal was filed on June 19, 1973.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
Kenneth I. Brown v. Herman Miller, Inc.
890 F.2d 443 (D.C. Circuit, 1989)
VanHaverbeke v. Bernhard
654 F. Supp. 255 (S.D. Ohio, 1986)
McInnis v. Harley-Davidson Motor Co., Inc.
625 F. Supp. 943 (D. Rhode Island, 1986)
Leach v. Newport Yellow Cab, Inc.
628 F. Supp. 293 (S.D. Ohio, 1985)
James D. Arms v. State Farm Fire & Casualty Company
731 F.2d 1245 (Sixth Circuit, 1984)
Miami Paper Corp. v. Magnetics, Inc.
591 F. Supp. 52 (S.D. Ohio, 1984)
Bruce Bagwell v. Canal Insurance Company
663 F.2d 710 (Sixth Circuit, 1981)
Tufts v. Madesco Inv. Corp.
524 F. Supp. 484 (E.D. Missouri, 1981)
Sims' Crane Service, Inc. v. Reliance Insurance
514 F. Supp. 1033 (S.D. Georgia, 1981)
Kohr v. Raybestos-Manhattan, Inc.
505 F. Supp. 159 (E.D. Pennsylvania, 1981)
Holcomb Construction Co. v. Armstrong
590 F.2d 811 (Ninth Circuit, 1979)
Holcomb Construction Co., Inc. v. Armstrong
590 F.2d 811 (Ninth Circuit, 1979)
Industrial Equipment Corp. v. Builders Insurance
108 P.R. Dec. 290 (Supreme Court of Puerto Rico, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
508 F.2d 1298, 1975 U.S. App. LEXIS 16545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-winston-corporation-v-continental-casualty-company-ca6-1975.