Sims' Crane Service, Inc. v. Reliance Insurance

514 F. Supp. 1033, 1981 U.S. Dist. LEXIS 9561
CourtDistrict Court, S.D. Georgia
DecidedMay 15, 1981
DocketCiv. A. CV180-40
StatusPublished
Cited by19 cases

This text of 514 F. Supp. 1033 (Sims' Crane Service, Inc. v. Reliance Insurance) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sims' Crane Service, Inc. v. Reliance Insurance, 514 F. Supp. 1033, 1981 U.S. Dist. LEXIS 9561 (S.D. Ga. 1981).

Opinion

ORDER

BOWEN, District Judge.

The above-captioned case is presently before the Court on the parties’ cross motions for summary judgment, or, in the alternative, for partial summary judgment. On review of the pleadings, affidavits and discovery on file, the following facts emerge as uncontested:

Whalley Construction Company, Inc. [Whalley] entered into a general contract with Georgia Infirmary Non-Profit Housing Corporation [Georgia Infirmary] for the construction of an apartment complex in Savannah, Georgia. Financing for the project was provided by the Department of Housing and Urban Development [HUD], Pursuant to the requirements of the general contract, Whalley, as principal, and defendant Reliance Insurance Company [Reliance], as surety, executed and delivered a performance and payment bond on a printed HUD form, in favor of Georgia Infirmary and the Secretary of HUD, in the amount of $3,659,800.00. The bond is conditioned upon Whalley performing all undertakings of the general contract and satisfaction of all claims and demands incurred under such contract, including “all amounts due for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such work, and all insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise.”

Whalley subcontracted a portion of the work required by the general contract to H. S. Horn Construction Company, Inc. [Horn] on a cost plus a fee basis subject to an agreed maximum, after all change orders, of $438,308.43. In the performance of its subcontract, Horn leased cranes from plaintiff Sims’ Crane Service, Inc. [Sims’] on terms of an oral contract agreed to by Horn and Sims’ in accordance with the prior dealings between the parties and the custom and usage of the trade. Pursuant to this agreement, Sims’ furnished a crane, serial number 35228, without a crane operator, to Horn on or about March 8, 1979. At the *1036 time of delivery, a delivery receipt, No. 0357, recording the condition of the crane was signed by agents of Sims’ and Horn. On March 30, 1979, the crane was damaged at the job site while being operated by an employee of Horn, and subsequently was repaired by Sims’.

Shortly thereafter, another crane, serial number 35109, was leased by Horn. The lease began on March 31, 1979 and the crane remained at the job site until approximately June 22, 1979. Sims’ claims that rental charges for cranes supplied by Sims’ remain due and owing by Horn.

Sims’ brought this action on the payment bond, seeking to impose liability on the surety for the unpaid rent and repair costs on its cranes, and attorney’s fees for the cost of collection. In its motion for summary judgment, plaintiff contends that there is no genuine issue of material fact as to the validity of its claim under the terms and conditions of the bond and the concomitant liability of the surety. By cross motion, Reliance asserts that the terms of the bond, when construed in accordance with the Georgia law, do not permit recovery of any of the items sought by plaintiff. The issue presented is whether plaintiff, as a materialman in the status of lessor of machinery to a subcontractor of the prime, is, as a matter of law, an intended beneficiary under the general contractor’s surety bond entitled to recovery on the bond for the default of the subcontractor.

Ordinarily, as a matter of construction, “the liability of a surety on a bond which is plain and unambiguous is governed, like any other contract, by the intention of the parties as expressed in the instrument.” American Casualty Co. v. Irvin, 426 F.2d 647, 650 (5th Cir. 1970); see Barge & Co., Inc. v. Oakwood, 128 Ga.App. 597, 598, 197 S.E.2d 405 (1973) (materialman’s right to sue on a private, voluntary bond must be determined from the intent of the parties); 17 Am.Jur.2d Contractors’ Bonds § 17 (1964). Such construction and interpretation of a written contract is matter of law for the court, see King v. Gilbert, 445 F.Supp. 479, 483 (N.D.Ga.1977), aff’d, 5 Cir., 569 F.2d 398 (1978), and, therefore, is properly subject to disposition by summary judgment. See R. C. Craig Limited v. Ships of Sea, Inc., 345 F.Supp. 1066, 1069 (S.D.Ga.1972). If, however, an ambiguity remains after application of all applicable rules of construction, then a jury question is presented. See National Car Rental System, Inc. v. Council Wholesale Distributors, Inc., 393 F.Supp. 1128, 1132 (M.D.Ga.1974). It should be noted that “a contract is not ambiguous, even though difficult to construe, unless and until an application of the pertinent rules of interpretation leaves it uncertain as to which of two or more permissible meanings represents the true intention of the parties.” Runyan v. Economics Laboratory, Inc., 147 Ga.App. 53, 55, 248 S.E.2d 44 (1978). Thus, in deciding the propriety of summary disposition on one or more of plaintiff’s claims, the task before the Court is to analyze the language of the bond, in light of the pertinent rules of construction, and determine whether: (1) it is a certainty, as a matter of law, that the intention of the parties to the payment bond, as reflected in the terms and conditions of the bond and gleaned therefrom, is to include Sims’ as a beneficiary of the bond, or, conversely, (2) it is a certainty, as a matter of law, the plaintiff is not such an intended beneficiary.

Turning, then, to the material language of the bond, it provides that:

the Principal shall . . . satisfy all claims and demands incurred under [the general] contract, and shall promptly make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work provided for in [the general] contract ..., including all amounts due for materials, .. . repairs on machinery, equipment and tools, consumed or used in connection with the construction of such work, .. ., and for all labor, performed in such work whether by subcontractor or otherwise ....

The operative phrase “furnishing materials for ... the prosecution of the work provided for in [the general] contract” clearly *1037 denotes an intent by the parties to endow materialmen, not just subcontractors, with a beneficial interest in the bond. Whether this beneficial interest is intended to extend only to materialmen in privity or having a direct relationship with the general contractor is not express by the terms of the bond. Yet, the language “all persons, firms, subcontractors, and corporations furnishing materials . .. consumed or used in connection with the ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hard Hat Workforce Solutions, LLC v. Mechanical HVAC Services, Inc.
750 S.E.2d 921 (Supreme Court of South Carolina, 2013)
National Loan Investors L.P. v. First Equities Corp.
261 A.D.2d 518 (Appellate Division of the Supreme Court of New York, 1999)
Seckinger-Lee Co. v. Allstate Insurance
32 F. Supp. 2d 1348 (N.D. Georgia, 1998)
Coffee v. General Motors Acceptance Corp.
5 F. Supp. 2d 1365 (S.D. Georgia, 1998)
Bio-Systems, Inc. v. BioWaste Systems, Inc.
874 F. Supp. 48 (E.D. New York, 1994)
Westinghouse Credit Corp. v. Hall
144 B.R. 568 (S.D. Georgia, 1992)
Anderson Chemical Co. v. Portals Water Treatment, Inc.
768 F. Supp. 1568 (M.D. Georgia, 1991)
Smith v. Freeport Kaolin Co.
687 F. Supp. 1550 (M.D. Georgia, 1988)
Kusan, Inc. v. Puritan Mills, Inc.
693 F. Supp. 1118 (N.D. Georgia, 1987)
Acrotube, Inc. v. J.K. Financial Group, Inc.
653 F. Supp. 470 (N.D. Georgia, 1987)
Dallis v. Aetna Life Insurance
574 F. Supp. 547 (N.D. Georgia, 1983)
Maggard Truck Line, Inc. v. Deaton, Inc.
573 F. Supp. 1388 (N.D. Georgia, 1983)
Hall v. Simkins Industries, Inc.
584 F. Supp. 955 (N.D. Georgia, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
514 F. Supp. 1033, 1981 U.S. Dist. LEXIS 9561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sims-crane-service-inc-v-reliance-insurance-gasd-1981.