Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co.

964 F. Supp. 1576, 1997 U.S. Dist. LEXIS 6945
CourtDistrict Court, M.D. Georgia
DecidedMay 14, 1997
Docket1:95-cr-00003
StatusPublished
Cited by5 cases

This text of 964 F. Supp. 1576 (Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co., 964 F. Supp. 1576, 1997 U.S. Dist. LEXIS 6945 (M.D. Ga. 1997).

Opinion

ORDER

OWENS, District Judge.

This case is before the court on defendant’s second motion for summary judgment. Oral arguments were held March 3, 1997. Based upon the oral arguments of counsel, the relevant case law, and the record as a whole, the court issues the following order.

I. Background

The dispute between the parties arises out of the construction of the Dooly Correctional Institution in Unadilla, Georgia. Plaintiff Associated Mechanical Contractors, Inc. (“AMC”), was a subcontractor on the project, and defendant Martin K. Eby Construction Company, Inc. (“Eby”), was the general contractor. AMC was responsible under its written subcontract for performance of the mechanical, heating, ventilation, air conditioning and plumbing work, in consideration of an original subcontract amount of more than $3,000,000. The project was ultimately completed in 1992. AMC has been paid the full agreed-upon subcontract price, except for retainage, as adjusted and increased by several change orders. Payment of the subcontract amount was made by interim payments, which were based on twenty-six separate applications for payment which AMC submitted at various times during progress of the construction. AMC’s claim for retainage in the amount of $255,763.37 has not been made a part of this lawsuit since the amount is not due to AMC until the owner releases the corresponding amount to Eby under the prime contract.

The present lawsuit concerns AMC’s request for equitable adjustment by which it seeks additional compensation in the principal amount of $737,343.96. This amount is for delays and disruptions which AMC alleges it continually encountered on the project because of the actions of Eby and Eby’s *1578 other subcontractors, resulting in additional costs to AMC. AMC provided Eby notice numerous times throughout 1991 and 1992 of its delay claims. Discussions of the claims were conducted up until the spring and summer of 1992, when Eby and AMC negotiated submitting the delay claims of both Eby and the subcontractors to the owner. However, none of the claims submitted by AMC were ever paid, and in November of 1992 AMC submitted to Eby its request for equitable adjustment representing AMC’s final calculation as to all the cost impacts it claimed as a result of the alleged disruptions and delays. These claims remain unresolved and constitute the subject of this lawsuit.

On April 17,1995, Eby filed its first motion for summary judgment. Eby argued that the standard release language on each of the twenty-six applications for payment submitted by AMC operated as a waiver and release of all claims relating to the work performed through the date of each application, except for retainage. The same argument had been made in a related case in this court filed by another of Eby’s subcontractors, styled Allgood Electric Company, Inc. v. Martin K Eby Construction Company, Inc., Civil Action No. 93-125-l-MAC(WDO). Convinced by the argument in the Allgood case as to the effect of the release language, this court granted summary judgment for Eby. Thereafter, in Allgood Electric Co. v. Martin K. Eby Construction Co., 85 F.3d 1547 (11th Cir.1996), the Eleventh Circuit reversed the grant of summary judgment, holding that the release language on the application for payment forms did not release all causes of action Állgood may have had against Eby but rather released only claims or liens against the property itself. In dicta, however, the court of appeals turned its focus to the first paragraph of the standard release language, which had not been relied on by either party. This paragraph, which is identical to the language in the applications for payment which AMC signed, provides:

I hereby certify that the work performed and the materials supplied to date, as shown on this application represent the actual value of accomplishment under the terms of the contract (and all authorized changes thereto) between the undersigned
and Martin K. Eby Construction Co., Inc., relating to the above referenced project.

Referring to this provision, the court of appeals remarked that, “Unlike the completion certificate and the clause of the payment applications relied upon by Eby, this section of the payment applications specifically identifies Eby. By this provision of the applications, Allgood appears to have certified that the amount billed represented the actual value of its performance for the periods of time indicated by the dates of the applications. This would seem to bar recovery for any additional costs allegedly incurred by Allgood during the course of construction for the periods of time represented by the invoices.” Allgood, 85 F.3d at 1554. The court of appeals remanded the case for a determination by this court as to the effect of AUgood’s certification to Eby that the amounts sought by the periodic payment applications represented the actual value of Allgood’s performance for the specified periods of time, as well as for a determination whether Allgood had complied with the notice provisions of Section 11 of the subcontract. Id. at 1555.

Section 11 of the Allgood subcontract is identical to Section 11 of the subcontract between Eby and AMC. It provides:

SECTION 11. DELAYS. Subcontractor shall not be entitled to an adjustment in time or Subcontract price for delays or damages caused by the Owner and/or Architect-Engineer, inclement weather, strikes, or other delays or damages unless such price change or time extension is approved in writing by the Owner or its authorized representative. Any damages which Subcontractor alleges that the Owner, Architect-Engineer, Contractor, other Subcontractor, or any other party for whom Contractor may be liable has caused him or is causing him must be filed in writing with the Contractor within ten (10) days fi*om the commencement of the alleged damage and a full accounting filed within ten (10) days after the extent of damage is known or the cause for damage ceases, whichever is the sooner; otherwise, any such claims will be considered void.

*1579 Because Eby’s first motion for summary judgment in the case sub judice was based solely upon the argument squarely rejected in Allgood as to the release language contained in the payment applications, this court denied the first motion by order of July 12, 1996. 1 Thereafter, focusing upon the court of appeals’ comments as to the effect of the “actual value” language in the release language of the applications for payment, Eby filed its second motion for summary judgment.

II. Summary judgment standard

Federal Rule of Civil Procedure

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
964 F. Supp. 1576, 1997 U.S. Dist. LEXIS 6945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-mechanical-contractors-inc-v-martin-k-eby-construction-co-gamd-1997.