Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co.

271 F.3d 1309, 2001 U.S. App. LEXIS 24235, 2001 WL 1397893
CourtCourt of Appeals for the Eleventh Circuit
DecidedNovember 9, 2001
Docket00-10784
StatusPublished
Cited by8 cases

This text of 271 F.3d 1309 (Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co., 271 F.3d 1309, 2001 U.S. App. LEXIS 24235, 2001 WL 1397893 (11th Cir. 2001).

Opinion

JOHN R. GIBSON, Circuit Judge:

Associated Mechanical Contractors, Inc., a subcontractor on a Georgia prison construction project, appeals from the district court’s entry of summary judgment against it in its suit against the prime contractor on the project, Martin K. Eby Construction Company, Inc. Associated attacks the district court’s holding that its claim for delay and inefficiency damages was barred because it failed to give Eby timely notice of its intent to seek those damages. Associated also argues that the district court should have awarded it interest on the final or “retainage” -payment under the subcontract. We reverse and remand as to the part of the claim for delay damages caused by events occurring *1311 after July 1990, affirm as to the part of that claim arising out of the events of May-July 1990, and affirm as to the interest claim.

We state the facts in the light most favorable to Associated, the non-movant. Associated and Eby signed a $3,150,000 subcontract under which Associated was to perform the mechanical, heating, ventilation, air-conditioning, and plumbing work in building the Dooly Correctional Center. The subcontract specified that Associated’s work would begin on or before May 2,1990 and would be complete by July 19, 1991. The subcontract contained the following provision governing compensation for delays:

SECTION 11. DELAYS.... Any damages which Subcontractor alleges that the Owner, Architect-Engineer, Contractor, other Subcontractor, or any other party for whom Contractor may be liable has caused him or is causing him must be filed in writing with the Contractor within ten (10) days from the commencement of the alleged damage and a full accounting filed within ten (10) days after the extent of damage is known or the cause for damage ceases, whichever is the sooner; otherwise, any such claims will be considered void.

The subcontract also provided that Associated would be bound by the Prime Contract documents, specifically Article E-37 of the Prime Contract’s General Conditions. Under Article E-37, the subcontractor agreed to make all claims for damages against the prime contractor in the same manner provided in the Prime Contract for claims by the prime contractor against the owner, which was spelled out at Article E~16(b). That article provided: “No claim of the contractor for damage shall be valid unless written notice thereof shall have been received by the owner by registered mail within 15 days after occurrence of the event on which the claim is based.”

From the beginning, the prison project was plagued by delays. Because the footings for the buildings were not finished on time, Associated could not begin work until June 18, 1990, in contrast to its scheduled start date of May 2. According to Associated’s project manager, Daniel Harrity, Eby acknowledged the delay at project meetings on July 6 and 10, but announced at an August 7 meeting that it would make up the lost time by revising the construction schedule.

By letter of August 11, 1990, Associated complained to Eby that Associated’s excavation and backfilling work was being held up improperly by the people who were supposed to supervise and inspect Associated’s compaction for the owner.

The project continued to fall further behind schedule over the next month, mainly due to problems with the masonry work, which affected Associated’s work schedule because Associated’s work had to be imbedded in the masonry. By September 4, Associated’s work on two of the buildings had ground to a halt. The next day, September 5, 1990, Associated wrote Eby complaining that it could not be responsible for making sure the masonry contractor’s work was up to specifications.

On September 13, 1990, Associated wrote Eby complaining of delay from yet another source-Eby’s failure to transmit Associated’s “submittal data” to the project architect or engineer for approval. According to the letter, Associated had just learned of the problem, although it had been going on since April.

Associated sent letters on October 1, 1990 and November 8, 1990, notifying Eby *1312 that Associated was suffering delay damage from the project being twenty-nine days behind schedule.

At the November 13 project meeting, Eby announced that the masonry subcontractor had defaulted. Associated wrote Eby again on November 26, 1990, saying that without any bricklayers on site, Associated would have to lay off workers on November 30 because there was nothing for them to do. Associated said it would incur expenses from this delay and would expect compensation. Again, on February 15, 1991, Associated wrote Eby complaining that the masonry problem and other changes had delayed its own work, and that Eby’s attempt to make up lost time by accelerating the work was going to cost Associated money.

From early 1991 through the end of 1992, when the project was finally finished, there was a constant stream of correspondence between Associated and Eby about the delays and problems on the project. Sometimes the letters showed them negotiating a resolution of responsibility and costs for delays and the consequent need to reschedule and accelerate remaining work, and sometimes they were simply blaming each other for the problems. Associated cited a variety of failures by other contractors that interfered with its ability to get its own work done, including continuing problems with the masonry work (especially condemnation of the walls on one building), problems with painting and flooring, and unclear or inadequate specifications in the building plans. Associated repeatedly described in its letters expenses it incurred from the rescheduling of its work, which sometimes left it with idle hands and sometimes caused it to have to pay overtime or to be short of workers. In November 1992 Associated presented Eby with a Request for Equitable Adjustment, asking for compensation of $737,343.96 and a 462-day time extension on its contract completion date (originally July 19,1991).

When Eby denied Associated’s request, Associated brought this diversity action for breach of contract, equitable adjustment, and quantum meruit. Two years after filing suit, Associated amended its complaint to add a claim for unpaid retainage.

Eby moved for summary judgment four times on a variety of theories. First, Eby argued that language in Associated’s periodic applications for payment released Eby from all claims relating to the work performed through the date of each application. At that time Eby was being sued by another subcontractor on the Dooly project, Allgood Electric Company, and Eby made a similar argument in the Allgood case. The district court granted summary judgment in Allgood, but this court reversed. Allgood Elec. Co. v. Martin K. Eby Construction Co., 85 F.3d 1547 (11th Cir.1996) (Allgood I). Because of the similarity between Eby’s argument in Allgood I and its argument against Associated in this case, once we handed down Allgood I, the district court in this case denied Eby’s first motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Equal Employment Opportunity Commission v. PMT Corp.
40 F. Supp. 3d 1122 (D. Minnesota, 2014)
Chesnut v. Ethan Allen Retail, Inc.
17 F. Supp. 3d 1367 (N.D. Georgia, 2014)
Bloodworth v. Colvin
17 F. Supp. 3d 1245 (N.D. Georgia, 2014)
Shedrick v. District Board of Trustees of Miami-Dade College
941 F. Supp. 2d 1348 (S.D. Florida, 2013)
Pendergast v. Sprint Nextel Corp.
592 F.3d 1119 (Eleventh Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
271 F.3d 1309, 2001 U.S. App. LEXIS 24235, 2001 WL 1397893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-mechanical-contractors-inc-v-martin-k-eby-construction-co-ca11-2001.