Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co.

983 F. Supp. 1121, 1997 U.S. Dist. LEXIS 18610, 1997 WL 728891
District Court, M.D. Georgia·Decided November 19, 1997·No. 5:95-cv-00003·Published·Cited by 1 cases

Opinion

ORDER

OWENS, District Judge.

This case is before the court on defendant Martin K. Eby Construction Company’s (“Eby’s”) third motion for summary judgment. At issue is whether plaintiff Associated Mechanical Contractors, Inc. (“AMC”) complied with the prime and subcontracts in attempting to submit notice of its intent to bring delay claims against Eby. Oral argument was heard on the motion on October 21, 1997. In addition, defendant Eby orally presented a motion to strike the affidavits of Kenneth Yakel and Daniel Harrity, both of which were submitted by AMC in support of its contention that summary judgment should be denied. Based upon the arguments of counsel, the relevant ease law, and the record as a whole, the court issues the following order.

BACKGROUND

The case arises out of the primary and subcontracts to build the Dooley Correctional Facility in Unadilla, Georgia. The basic facts of the case were set forth in the court’s order of May 14, 1997, in which the court denied defendant’s second motion for summary judgment. See Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co., Inc., 964 F.Supp. 1576 (M.D.Ga.1997). In addition, the argument currently before the court — that the subcontractor failed to provide timely notice of its intent to bring delay claims as dictated by the express terms of the contract — was made by defendant Eby against another of the subcontractors, All-good Electric Company (“Allgood”), in a separate but related case. See Allgood Electric Co., Inc. v. Martin K. Eby Construction Co., Inc., 959 F.Supp. 1573 (M.D.Ga.1997). In that case, the court granted summary judgment for the defendant, finding that the plaintiff’s notice of the delay claims was indeed delinquent and therefore that the delay claims were void under the express terms of the contract. Id. The Allgood matter is currently on appeal from the court’s granting of summary judgment.

The court recognizes that these two cases are factually and legally separate and distinct. Nevertheless, because both cases involve the same construction project, the prime contract and subcontract at issue as well as many other relevant facts are identical in both cases. Therefore, while some facts may differ, the same basic analysis used in the Allgood case applies in this matter as well.

*1123 FACTS

J. The Prime Contract and Subcontract

Two contract provisions are relevant to the issue of the timeliness of notice. First, the prime contract between Eby, the prime contractor, and the Georgia Building Authority, the owner of the project, contained a provision stating that the subcontractor agreed to make all claims for damages to the contractor in the same manner and within the same time as the contractor had to make claims to the owner — that is, within 15 days of the occurrence of the event giving rise to the damage claim. See Allgood, 959 F.Supp. at 1575-76 (laying out relevant contract provisions).

Second and more importantly, Section 11 of the subcontract between Eby and AMC specifically addressed the parties’ respective rights and duties in the event of project delays. See Allgood, 959 F.Supp. at 1576. Because of its centrality to the present motion, that section is reprinted here in its entirety.

SECTION 11. DELAYS. Subcontractor shall not be entitled to an adjustment in time or Subcontract price for delays or damages caused by the Owner and/or Architect-Engineer, inclement weather, strikes, or other delays or damages unless such price change or time extension is approved in writing by the Owner or its authorized representative. Any damages which Subcontractor alleges that the Owner, Architect-Engineer, Contractor, other Subcontractor, or any other party for whom Contractor may be liable has caused him or is causing him must be filed in writing with the Contractor within ten (10) days from the commencement of the alleged damage and a full accounting filed within ten (10) days after the extent of damage is known or the cause for damage ceases, whichever is the sooner; otherwise, any such claims will be considered void.

IT. Project Delays and Notice of Delay Claims

AMC asserts in its complaint that from the very beginning the project was “substantially delayed and disrupted during the Start-Up portion of the Project as a result of several changes issued by Eby and by Eby’s extensive resequencing of work” (Complaint, ¶ 13). AMC claims these delays resulted in there being little or no work to do on some days, while the work was accelerated on other days to make up for lost time. In addition, AMC claims the resequencing of the project resulted in the work being performed less efficiently, thereby adding to AMC’s costs. At a September 20, 1990, Project Managers Meeting, at which AMC’s representatives were in attendance, it was estimated that the project was 29 calendar days behind schedule.

AMC submitted to Eby ten letters relating to the delays involved with the project which it argues constituted adequate notice of its intent to bring delay claims. The first of these letters is dated August 11, 1990, while the last one was sent over a year later on August 21,1991. Some of these letters detail delays and costs associated with a specific portion of the job, while others address the delay in the overall schedule of the project. 1

It is clear from the minutes of the Project Manager Meetings that Eby acknowledged the delays throughout the course of the project, and worked with the subcontractors to regain the original project schedule. In addition, Eby worked with AMC to quantify the effects of the delays and to facilitate resolution of all claims. Eby’s correspondence with AMC is set forth in relevant part below.

On September 9, 1991, Eby sent AMC. a letter advising that: ■ •

Eby acknowledges that there have been days added to the original contract completion date. Enumeration for these changes is strictly governed by the Prime Contract General Conditions authored by the Georgia Building Authority. Article E-l 5 of this document is explicit as to the allowable cost that Eby will receive for contract changes. This document is made part of your subcontract by reference on page 14, item 23.1.

On April 20,1992, Eby advised AMC that:

*1124 Upon review of AMC’s claim, Eby questions whether AMC has properly provided the necessary notices.
Neither the content of this letter nor any effort by Eby to aid AMC in its prosecution of this claim are to be construed as an acknowledgement by Eby as to the validity of any claim submitted by AMC, nor shall either act as a waiver of any rights or defenses available to Eby. Eby hereby reserves all of its rights and defenses against AMC which are provided by the contract between the parties and the applicable law.

DISCUSSION

Because jurisdiction in this case was based on diversity of citizenship, the substantive law of Georgia controls. Flintkote Co. v. Dravo Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co., 983 F. Supp. 1121, 1997 U.S. Dist. LEXIS 18610, 1997 WL 728891 (M.D. Ga. 1997).

983 F. Supp. 1121 (Associated Mechanical Contractors, Inc. v. Martin K. Eby Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related