G.R. Sponaugle & Sons, Inc. v. Hunt Construction Group, Inc.

366 F. Supp. 2d 236, 2004 U.S. Dist. LEXIS 27724
CourtDistrict Court, M.D. Pennsylvania
DecidedSeptember 17, 2004
DocketCivil 1:CV-03-1118
StatusPublished
Cited by6 cases

This text of 366 F. Supp. 2d 236 (G.R. Sponaugle & Sons, Inc. v. Hunt Construction Group, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G.R. Sponaugle & Sons, Inc. v. Hunt Construction Group, Inc., 366 F. Supp. 2d 236, 2004 U.S. Dist. LEXIS 27724 (M.D. Pa. 2004).

Opinion

MEMORANDUM

CALDWELL, District Judge.

I. Introduction.

Plaintiff, G.R. Sponaugle & Sons, Inc., was the electrical subcontractor for defendant, Hunt Construction Group, Inc., the general contractor for the construction of the Giant Center (“the project”), a 306,-000-square-foot indoor arena in Hershey, Pennsylvania. The project fell behind schedule, occasioning additional costs for Sponaugle not contemplated by the subcontract. In this diversity action controlled by Pennsylvania law, Sponaugle is attempting to recover those additional costs, which it attributes to Hunt’s delay in seeing the project through to completion. It is also seeking to recover for sums it alleges it is due for work as authorized by the subcontract.

Plaintiff has set forth three causes of action. Count I is for breach of contract and alleges that Hunt failed to pay Spo-naugle for all the work it performed as specified in the subcontract. Count II is also for breach of contract, but for the additional costs Plaintiff incurred based on Hunt’s alleged delay and interference with Sponaugle’s work. Count III is for a violation of the Pennsylvania Prompt Payment Act, 62 Pa.C.S.A. §§ 3901-3942, and alleges that Hunt’s failure to pay Plaintiff all of the sums due for work originally authorized by the subcontract violated that act. The amount in controversy for Count II is about $1.25 million.

Wé are considering Defendant’s motion for summary judgment which makes three arguments. First, count II is barred because Sponaugle released Hunt from any claims stemming from the project when Plaintiff periodically applied for progress payments under the subcontract. Second, count II is also barred because Sponaugle did not comply with the subcontract’s procedural requirements for making claims against Hunt arising under the agreement. Third, counts I and III are barred because Hunt complied with its payment obligations under both the subcontract and the act. 1

We will evaluate Defendant’s motion under the well-established standard, see Anderson v. Consolidated Rail Corp., 297 F.3d 242, 246-47 (3d Cir.2002). The summary-judgment record is as follows, viewed in the light most favorable to Plaintiff, the nonmoving party. Id. at 247.

II. Background.

In September 2000, Hunt entered into a general' contract with Regional Area Management, LLC to build the arena. Regional Area Management was the agent for the local, development authority, the arena’s owner. On April 6, 2001, Hunt *238 subcontracted the project’s electrical work to Sponaugle, with the subcontract backdated to February 8, 2001.

Section 5.5 of the subcontract essentially provided, in pertinent part, that after Hunt received a payment from the owner on the general contract, it would pay Spo-naugle its proportional share of the payment. For Sponaugle to obtain payment for its work under the agreement, section 5.2 of the subcontract required it to submit “progress payment applications on forms approved by Hunt.” Each payment application also had to have “attached” a “fully-executed, current Monthly Statement of Subcontractor to Hunt and fully-executed Affidavit and Partial Waiver of Claims and Liens and Release of Rights, on forms acceptable to Hunt, reflecting all previous progress payments.” (Doc. 22, ex. B §§ 5.2 and 5.2(a)(6)).

These forms were prepared by Hunt. In pertinent part, the release, captioned “Affidavit and Partial Waiver of Claims and Liens and Release of Rights,” reads as follows:

In addition, for and in consideration of the amounts and sums received, [Spo-naugle] hereby waives, releases and relinquishes any and all claims, rights or causes of action whatsoever arising out of or in the course of the work performed on [the project], contract or event transpiring prior to the date hereof, excepting the right to receive payment for work performed and properly completed and retainage, if any, after the date of the above-mentioned payment application or invoices.

(Doc.22, ex. D). 2

Section 9.7 of the subcontract obligated Sponaugle to “work overtime and/or add additional manpower or shifts” if Hunt ordered it to do so. Subparagraphs (a) and (b) of this section allocated the extra expense of this additional work depending upon fault. If Sponaugle was not behind schedule, subparagraph (a) required Hunt to pay Sponaugle for the additional wages caused by the extra work but no overhead or profit. If Sponaugle was behind schedule “through its own sole or partial fault,” subparagraph (b) made Sponaugle responsible for the extra expense. (Doc. 22, ex. B).

Section 10.2 sets forth a procedure for Sponaugle to make claims against Hunt for extra costs caused by Hunt. The section also provided that Sponaugle’s failure to comply with the procedure would act as an irrevocable waiver of any claims. In pertinent part, section 10.2 provides as follows:

Delays Caused Solely by Hunt: Should Subcontractor’s Work be delayed, disrupted or interfered with solely as a result of acts or omissions of Hunt or anyone employed by Hunt on the Project, then, at Hunt’s sole discretion, Hunt shall provide Subcontractor either:
(a) ...; or
(b) additional compensation as provided in Section 9.7(a), but only if a written claim for delay is submitted to Hunt within forty-eight (48) hours from the *239 time of the commencement of such delay, disruption or interference.
Failure to provide such written claim within the prescribed time period shall result in an irrevocable waiver of any such claim. The extension of time or the additional compensation provided pursuant to this Section 10.2 shall be the sole and exclusive remedy that Subcontractor shall have against Hunt for delays, disruptions or interferences caused by the acts or omissions of Hunt- or anyone employed by Hunt on the Project. ...

(Id.).

Section 34.2 sets forth another claims procedure broader in scope than section 10.2. Section 34.2 provides, in pertinent part, that “[i]f the Subcontractor has a dispute with Hunt regarding the application or interpretation of any provision of this Subcontract or the breach thereof,” the subcontractor shall submit its claim in writing within ten days, “attaching all supporting documentation.”

The construction schedule called for substantial completion of the project by September 30, 2002. While this deadline was essentially met, 3 the goal was accomplished by changing and accelerating the work schedules for the various subcontractors, including Sponaugle, as the project fell behind. Plaintiff alleges it incurred additional costs when Hunt required it to work overtime, in a random and inefficient manner and in congestion with other subcontractors, (Compl., ¶¶ 18 and 24), attributing delays and disruptions to Hunt and other subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MARSHALL v. PRESTAMOS CDFI, LLC
E.D. Pennsylvania, 2023
Gillespie v. Dring
350 F. Supp. 3d 333 (M.D. Pennsylvania, 2018)
Thyssenkrupp Steel USA, LLC v. United Forming, Inc.
926 F. Supp. 2d 1286 (S.D. Alabama, 2013)
Sauer Inc. v. Honeywell Building Solutions SES Corp.
742 F. Supp. 2d 709 (W.D. Pennsylvania, 2010)
Quinn Construction, Inc. v. Skanska USA Building, Inc.
730 F. Supp. 2d 401 (E.D. Pennsylvania, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
366 F. Supp. 2d 236, 2004 U.S. Dist. LEXIS 27724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gr-sponaugle-sons-inc-v-hunt-construction-group-inc-pamd-2004.