Galin Corporation and Petropak, Inc. v. MCI Telecommunications Corporation

12 F.3d 465, 1994 WL 8175
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 16, 1994
Docket92-2649
StatusPublished
Cited by14 cases

This text of 12 F.3d 465 (Galin Corporation and Petropak, Inc. v. MCI Telecommunications Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galin Corporation and Petropak, Inc. v. MCI Telecommunications Corporation, 12 F.3d 465, 1994 WL 8175 (5th Cir. 1994).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

This is a diversity suit for breach of a construction contract. The district court granted judgment denying relief to plaintiffs at the outset of trial, but without allowing the parties to present evidence to the jury. We agree with the district court that plaintiffs’ claims are barred by the terms of the release and notice of claim provisions of the construction contract. We also conclude that the district court’s unusual grant of judgment at the outset of trial was effectively a grant of summary judgment that had been argued earlier. We affirm.

I

In March 1987, MCI Telecommunications Corporation invited bids on a fiber optic cable installation route comprising eight sections to extend through Georgia, Alabama and Tennessee. Galin Corporation and Pe-tropak, Inc., met with MCI personnel, made extensive visits to various future work sites, *467 and analyzed MCI’s plans, specifications, and bid instructions. Galin and Petropak then submitted bids on six of the eight sections. MCI accepted no bids on the project. In late August of the same year, MCI issued new instructions for the installation of a shorter version of the same fiber optic cable route. Before requesting a second set of bids, MCI released to the prospective contractors an estimate of the amount of subsurface rock that lay along the cable route. Galin and Petropak again submitted a bid, this time at a lower price, which MCI accepted. The parties executed a written contract.

Galin and Petropak commenced work in early November. During the project, MCI complained to Galin and Petropak of their lack of timely progress and, on December 18, MCI gave Galin and Petropak notice of termination by default for failure to meet the contract schedule. On December 30, MCI eliminated the last seven miles of the cable route from the contract.

Galin and Petropak say that they completed the installation of the cable on or about February 21, 1988, “except for areas where MCI had failed to obtain necessary permits or easements and where MCI had misrepresented the existence of rocks”; and that they then commenced cleaning up their work sites.

On April 22, 1988, MCI issued a proposed Final Modification of Contract, which Galin and Petropak did not sign. As the project had progressed, however, Galin and Petropak had signed a series of releases in exchange for incremental payments from MCI. They signed the last of these releases on May 13, 1988. Finally, in July of 1988, MCI terminated the contract for non-performance.

Settlement negotiations failed and Galin and Petropak filed this suit in a Texas court seeking compensation from MCI for breach of contract, in quantum meruit, and in tort. MCI removed to federal district court invoking the court’s diversity jurisdiction. MCI and Galin and Petropak then both moved for summary judgment. The district court granted judgment to MCI on Galin and Pe-tropak’s claim for breach of a covenant of good faith and fair dealing, but left the remaining issues for trial.

When the case was called for trial, MCI asserted that the district court should render judgment. The district court granted the requested relief treating it as a motion for judgment as a matter of law under Federal Rule of Civil Procedure 50(a). Applying New York law, the court dismissed the case before the first witness was called. Galin and Petropak appeal.

II

Galin and Petropak pursue several claims. Galin and Petropak allege that MCI deliberately underestimated the amount of subsurface rock that lay along the route to decrease the cost of construction. The subcontractor who performed the rock probes, Galin and Petropak assert, did not work long enough to produce the results that MCI released. Ga-lin and Petropak argue that MCI must have fabricated either some or all of the site information. They claim to have relied on this falsely optimistic information in their bid.

According to Galin and Petropak, MCI engaged in other questionable business practices. They allege that MCI’s designs for installing the cable were faulty, that MCI failed to obtain timely permission for them work on several stretches of the route, that MCI interfered'in their operations, that MCI forced them to meet more exacting standards during the clean up process than the contract required, and that MCI otherwise failed to support them.

Galin and Petropak sue for recovery on the contract, in quantum meruit for extra-contractual work performed, for compensation for MCI’s wrongful interference with their contract performance, and for compensation for MCI’s breach of its duty of good faith and fair dealing. 1 The district court decided the case based on provisions in the contract that protect MCI from liability and on the releas *468 es that Galin and Petropak signed. Galin and Petropak argue that the protective provisions and releases are inapplicable to their claims and, further, that MCI waived application of the provisions. The parties agree that New York law controls.

A.

At the outset, Galin and Petropak argue that the district court improperly invoked Federal Rule of Civil Procedure 50(a) in dismissing their case. First, they argue that Rule 50(a) required that MCI move for judgment as a matter of law and that when the court ruled MCI had not done so. Second, they argue that they had not been fully heard by the court, as required by Rule 50(a), before it rendered judgment. We need not address these contentions as we construe the court’s order as a grant of summary judgment and affirm on that basis.

The district court early in the case denied MCI’s motion for summary judgment, to which Galin and Petropak had fully responded. On reconsidering, the court concluded that the case did turn on the notice and release provisions of the contract. This interpretation presented no issues of fact and protected MCI from liability. The court therefore ruled in MCI’s favor, albeit under Federal Rule of Civil Procedure 50(a).

Where a case does not require the resolution of material facts, summary judgment is appropriate. See Seneca v. Phillips Petroleum Co., 963 F.2d 762, 765 (5th Cir.1992). We have in the past affirmed summary judgment on grounds different than those adopted by the trial court. Id. at 765; Church of Scientology v. Cazares, 638 F.2d 1272, 1281 (5th Cir.1981). Since both parties had adequate opportunity to address the issues involved in summary judgment prior to the district court’s ruling, we see no impediment to treating the judgment below as a grant of summary judgment. Having so concluded, we consider the propriety of that judgment.

B. The Releases

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
12 F.3d 465, 1994 WL 8175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/galin-corporation-and-petropak-inc-v-mci-telecommunications-corporation-ca5-1994.