Sauer Inc. v. Honeywell Building Solutions SES Corp.

742 F. Supp. 2d 709, 2010 U.S. Dist. LEXIS 99368, 2010 WL 3824228
CourtDistrict Court, W.D. Pennsylvania
DecidedSeptember 21, 2010
DocketCivil Action 08-92J
StatusPublished
Cited by3 cases

This text of 742 F. Supp. 2d 709 (Sauer Inc. v. Honeywell Building Solutions SES Corp.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauer Inc. v. Honeywell Building Solutions SES Corp., 742 F. Supp. 2d 709, 2010 U.S. Dist. LEXIS 99368, 2010 WL 3824228 (W.D. Pa. 2010).

Opinion

MEMORANDUM OPINION AND ORDER OF COURT

GIBSON, District Judge.

I. SYNOPSIS

This matter comes before the Court on a motion for summary judgment (Doc. No. 24) filed by the Defendant, Honeywell Building Solutions SES Corporation (“Honeywell”), pursuant to Federal Rule of Civil Procedure 56. The Plaintiff, Sauer Incorporated (“Sauer”), opposes the Motion for Summary Judgment. For the rea *711 sons that follow, the motion will be granted in part and denied in part.

II. BACKGROUND

Sempra Energy Services (“Sempra”) was the general contractor for a construction project conducted at the Conemaugh Valley Memorial Hospital (“Conemaugh”) in Johnstown, Pennsylvania. Def.’s Statement of Facts & Pl.’s Counterstatement of Facts at ¶ 1; Doc. Nos. 25-1 & 27 at ¶ 1. At some point in 2006, Honeywell acquired Sempra and became the general contractor for the project. 1 On May 10, 2005, Sempra and Sauer executed a subcontract agreement, with an original value of $3,855,600.00, requiring Sauer to provide mechanical and plumbing work in connection with the project at Conemaugh. Id. at ¶ 2.

The relevant portions of the subcontract agreement provided as follows:

5.1 Progress Payments. Based upon applications for payment submitted to the Contractor by Subcontractor, Contractor will make progress payments to Subcontractor for the Work as provided below.
5.1.3 Each Application for Payment must be supported and accompanied by an executed lien waiver and affidavit attached hereto as Exhibit “B.” If Subcontractor has purchased materials or subcontracted for work in excess of Two Thousand Five Hundred Dollars ($2,500.00) from a single supplier or sub-contractor, said supplier or sub-contractor must also execute the lien waiver and affidavit, which shall be submitted with the Application for Payment. If satisfactory, the Application for Payment will be incorporated with the Contractor’s request for payment and forwarded to the Owner and/or Third-Party Lender. If required by Contractor, Owner or Third-Party Lender, Subcontractor shall furnish any additional documentation pertaining to the Application for Payment upon request of Contractor.

Def.’s Ex. 2, HON 004140; Doc. No. 25-5 at 4. The “Exhibit ‘B’ ” referenced in Article 5.1.3 contained the following language:

Exhibit “B”
Subcontract Lien Waiver and Affidavit Forms
WHEREAS, the undersigned, hereinafter called “Subcontractor,” has performed labor or furnished materials or done both pursuant to the undersigned’s contract with Sempra Energy Services, hereinafter called “Contractor,” in connection with the construction of improvements at [address ] owned by [name of ovmer], hereinafter called “Owner” and,
WHEREAS, as a result of the foregoing, $_is due and payable to Subcontractor from Contractor for the period ending [date ] and,
WHEREAS, Subcontractor has been requested to acknowledge receipt from Contractor of payment of a portion of such sums as are due for the period ending [date] and to release and waive any liens or claims Subcontractor may have or assert against Owner or Contractor or such improvements and real property, or such payment bonds applicable to the construction of improvements, that have arisen by virtue of Subcontractor in connection with construction.
*712 NOW, THEREFORE, based on payment of such sums due as of_, Subcontractor hereby waives, relinquishes, and releases its liens, claims, rights and charges of every nature whatsoever which have arisen at law, equity or contract by virtue of such labor and/or materials furnished by said Subcontractor, including any and all mechanic’s or materialman’s liens and payment bond claims to the extent such monies are due and have been paid as herein stated; provided, however, such waiver, relinquishment and release shall not affect Subcontractor’s lien claim and rights with respect to sums which are not due and payable by Contractor to Subcontractor, including sums retained by Contractor and Subcontractor, or Subcontractor’s lien claims and rights for sums that become due to Subcontractor after the above said date or which are not now due for the performance by Subcontractor in connection with the construction of such improvements pursuant to the agreement between Contractor and Subcontractor.

Def.’s Ex. 2, HON 004152; Doc. No. 25-5 at 16. During the course of the project, Sauer submitted twenty progress payment applications to Sempra and Honeywell. Def.’s Statement of Facts & Pl.’s Counter-statement of Facts at ¶ 7; Doc. Nos. 25-1 & 27 at ¶ 7.

In a letter dated October 3, 2005, Jim Manion (“Manion”), a project manager for Sauer, complained to John Schelmbauer (“Schelmbauer”), a Sempra official, about delays associated with the construction project and the delivery of pre-purchased equipment. Def.’s Ex. 4; Doc. No. 25-7 at 2. By that time, Sauer had already submitted four progress payment applications to Sempra. Doc. Def.’s Statement of Facts & PL’s Counterstatement of Facts at ¶ 8; Nos. 25-1 & 27 at ¶ 8. The first eighteen progress payment applications submitted by Sauer to Sempra and/or Honeywell were accompanied by signed “Subcontract and Lien Waiver and Affidavit Forms” in accordance with Article 5.1.3, Id. at ¶ 9. After the submission of the eighteenth progress payment application, the cumulative amount of money requested by Sauer constituted the original contract price of $3,855,600.00, including all retainage which had been withheld pursuant to the subcontract agreement, and a net amount of $189,500.00 attributable to change orders. Id. at ¶ 11. This application, which was dated December 26, '2006, requested payment for work provided through December 31, 2006. Id. at ¶ 10.

The nineteenth progress payment application was submitted by Sauer to Honeywell on February 16, 2007. Id. at ¶ 13. This application sought payment for $23,365.00 in change-order work that Sauer had performed in 2006 and $50,000.00 as a partial release of retention money that Honeywell had withheld pursuant to the contract. Id. at ¶ 14. The application was accompanied by a “Subcontract Lien Waiver and Affidavit Form” signed by Manion, but the language of the last two paragraphs appearing on the form had been crossed out. Def.’s Ex. 3, HON 004228; Doc. No. 25-6 at 58. On May 8, 2007, Honeywell agreed to release $64,647.84 in retention money. Def.’s Statement of Facts & PL’s Counterstatement of Facts at ¶ 15; Doc. Nos. 25-1 & 27 at ¶ 15. Honeywell withheld approximately $30,000.00 in retention money, claiming that Sauer had failed to provide “as-built drawings” and a warranty letter. Id.

On May 9, 2007, Sauer’s Vice President of Operations, Richard A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
742 F. Supp. 2d 709, 2010 U.S. Dist. LEXIS 99368, 2010 WL 3824228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauer-inc-v-honeywell-building-solutions-ses-corp-pawd-2010.