The Hardaway Company, Plaintiff-Counter-Defendant-Appellant v. Amwest Surety Insurance Company, Defendant-Counter-Claimant-Appellee

986 F.2d 1395
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 21, 1993
Docket92-8153
StatusPublished
Cited by4 cases

This text of 986 F.2d 1395 (The Hardaway Company, Plaintiff-Counter-Defendant-Appellant v. Amwest Surety Insurance Company, Defendant-Counter-Claimant-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Hardaway Company, Plaintiff-Counter-Defendant-Appellant v. Amwest Surety Insurance Company, Defendant-Counter-Claimant-Appellee, 986 F.2d 1395 (11th Cir. 1993).

Opinion

DUBINA, Circuit Judge:

In this construction case involving the bonded performance of a now defunct subcontractor, B & F Contractors, Inc. (“B & F”), the plaintiff prime contractor, Harda *1396 way Company (“Hardaway”), appeals the district court’s order granting summary judgment to the defendant surety company, Amwest Surety Insurance Company (“Amwest”). The district court found that Hardaway's release of its claims against B & F terminated Hardaway’s rights against Amwest as a matter of state law, despite the explicit reservation of those rights in the release agreement between Hardaway and B & F.

The district court determined that under Georgia law a surety is discharged when the principal debtor is discharged unless (1) the discharging creditor reserves all rights against the surety and (2) the discharge of the principal debtor is done with the knowledge and consent of the surety. Since Hardaway explicitly reserved its rights to proceed against Amwest when releasing B & F, the first requirement was not in issue. Regarding the second requirement, the district court concluded that Amwest had not consented to Hardaway’s release of B & F, and thus found that Amwest was discharged.

As in the district court, the first requirement is not at issue in this appeal. Regarding the second requirement, we must first determine whether Amwest consented to the release, because if Amwest consented we would have no need to reach the issue of whether consent is required. Because we agree with the district court that Amwest did not consent to the release, we must determine whether Georgia law requires consent. Since there is confusion in Georgia law regarding this issue, we certify the question to the Supreme Court of Georgia.

I. STATEMENT OF THE FACTS

This case concerns the construction of a public works project for the Georgia Department of Transportation (“DOT”). Hardaway as prime contractor secured B & F as subcontractor to perform earthmoving services needed to prepare the site. Am-west guaranteed B & F’s performance.

When B & F encountered difficulty in paying vendors, it demanded payment from Hardaway for additional costs incurred. Pursuant to its interpretation of a clause in the subcontract, Hardaway referred the claim to the DOT and refused to make payment on its own. When B & F continued experiencing difficulty in performing, Hardaway notified B & F that it was in default and demanded that Amwest fulfill the subcontract. Under an agreement with Hardaway (the “Takeover and Hold Harmless Agreement”), Amwest took over performance of the subcontract and agreed to finish the job, using B & F’s own resources to do so.

B & F then commenced a civil action against Hardaway in South Carolina state court for payment of the additional cost overruns. After being removed to federal court, that litigation was settled by an agreement between Hardaway and B & F to which Amwest was not a party. Paragraph six of the settlement agreement purported to “release” Hardaway’s claims against B & F for its default under the subcontract, while preserving any warranty claims against B & F and specifically providing that Hardaway retained its rights against Amwest. 1

Alleging diversity of citizenship as the basis for federal jurisdiction, Hardaway then sued Amwest in the United States District Court for the Southern District of Georgia to recover damages for B & F’s default. Amwest defended that Hardaway's release of its claims against B & F also terminated its rights against the surety, notwithstanding the parties’ attempt to preserve those rights. In the alternative, Amwest counterclaimed for the cost overruns, to which it claimed to be entitled as *1397 subrogee of B & F. The district court agreed with Amwest, granted summary judgment to Amwest, denied Hardaway’s cross-motion for summary judgment, and dismissed the alternative counterclaim pursuant to Amwest’s voluntary withdrawal. This appeal followed.

II. ANALYSIS

A. DID AMWEST CONSENT TO HARDAWAY’S RELEASE OF B & F?

The district court determined that since the language of the surety contract does not explicitly mention release of the principal or diminishment of security as a permissible modification, Amwest’s consent to modifications in the surety contract was not advance consent to Hardaway’s discharge of B & F. We review the district court’s interpretation of state law de novo. Salve Regina College v. Russell, — U.S. —, —-—, 111 S.Ct. 1217, 1221-25, 113 L.Ed.2d 190 (1991); Forbus v. Sears Roebuck & Co., 958 F.2d 1036, 1041 (11th Cir.), cert. denied, — U.S. —, 113 S.Ct. 412, 121 L.Ed.2d 336 (1992).

Hardaway argues that it has the power to modify the subcontract and that this power includes the power to release B & F. Thus, it argues that the surety contract constitutes Amwest’s consent to Hardaway’s release of B & F. The surety contract provides that

[the] terms and conditions of said Principal Contract [the subcontract between Hardaway and B & F] may be changed, amended, altered, or modified at any time, without notice to the Surety and without procuring the consent, approval or waiver of the Surety, and any such change, amendment, alteration or modification shall not release the Surety from liability under this bond.

Both parties agree that a surety may consent in advance to conduct which would otherwise discharge him, Regan v. United States Small Business Admin., 926 F.2d 1078, 1082 (11th Cir.1991) (applying Georgia law), but Amwest argues that the common usage of the word “modify” means something different from “release” and that the contract should be interpreted according to its plain meaning. The district court agreed with Amwest, finding that modification means “a change, alteration or amendment that ‘introduces new elements into the details, or cancels some of them, but leaves the general purpose and effect of the subject matter intact.’ ” (Order at 10 (quoting Black’s Law Dictionary 905 (5th ed. 1979)). Cf. Delta Diversified, Inc. v. Citizens & Southern Nat’l Bank, 171 Ga.App. 625, 320 S.E.2d 767, 772 (1984) (holding that surety consented to subordination of collateral in advance where contract expressly provided that modification or release of principal’s obligations would not discharge surety).

In response, Hardaway points to other provisions in the subcontract itself, incorporated into the surety bond by reference, which already granted Hardaway the right to make the kind of changes that the district court held were encompassed by the term “modify.” Hardaway premises its argument on the rule that nothing permitted in the subcontract and incorporated in the surety bond can be taken to discharge the surety, see Winston Corp. v. Continental Casualty Co., 508 F.2d 1298, 1301 (6th Cir.), cert. denied, 423 U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
986 F.2d 1395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-hardaway-company-plaintiff-counter-defendant-appellant-v-amwest-ca11-1993.