The Hardaway Company, Plaintiff-Counter-Defendant-Appellant v. Amwest Surety Insurance Company, Defendant-Counter-Claimant-Appellee

15 F.3d 172, 1994 U.S. App. LEXIS 3648, 1994 WL 41301
CourtCourt of Appeals for the Eleventh Circuit
DecidedMarch 1, 1994
Docket92-8153
StatusPublished
Cited by6 cases

This text of 15 F.3d 172 (The Hardaway Company, Plaintiff-Counter-Defendant-Appellant v. Amwest Surety Insurance Company, Defendant-Counter-Claimant-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Hardaway Company, Plaintiff-Counter-Defendant-Appellant v. Amwest Surety Insurance Company, Defendant-Counter-Claimant-Appellee, 15 F.3d 172, 1994 U.S. App. LEXIS 3648, 1994 WL 41301 (11th Cir. 1994).

Opinion

PER CURIAM:

In this construction case involving the bonded performance of a now defunct subcontractor, B & F Contractors, Inc. (“B & F”), the plaintiff prime contractor, Hardaway Company (“Hardaway”), appeals the district court’s grant of summary judgment to the defendant surety company, Amwest Surety Insurance Company (“Amwest”). The district court found that Hardaway’s release of its claims against B & F terminated Harda-way’s rights against Amwest as a matter of state law, despite the explicit reservation of those rights in the release agreement between Hardaway and B & F.

The district court determined that under Georgia law a surety is discharged when the principal debtor is discharged unless (1) the discharging creditor reserves all rights against the surety and (2) the discharge of the principal debtor is done with the knowledge and consent of the surety. Since Hard-away explicitly reserved its rights to proceed against Amwest when releasing B & F, the first requirement was not in issue. Regarding the second requirement, the district court concluded that Amwest had not consented to Hardaway’s release of B & F, and thus found that Amwest was discharged.

We agreed with the district court that Amwest did not consent to the release. See Hardaway Company v. Amwest Surety Insurance Company, 986 F.2d 1395, 1396 (11th Cir.1993). However, we then had to determine whether under Georgia law consent is required. Because we found confusion in the decisions of the Georgia courts regarding this issue, we certified the following question for consideration by the Supreme Court of Georgia:

*173 Whether a creditor’s agreement to release a principal debtor, which contains an express reservation of rights against the surety, is a release of the surety’s liability to the creditor on the surety bond or a mere covenant by the creditor not to sue the principal debtor when the surety has not consented to the creditor’s release of the principal debtor?

The Supreme Court of Georgia has answered the question by holding that “the creditor’s release of the principal debtor without the consent of the surety does not discharge the surety if the creditor, in the instrument of release, reserved its rights against the surety. However, the debtor’s waiver of its claims in consideration of that release may not defeat the surety’s right to assert those claims to reduce its liability to the creditor.” Hardaway Company v. Am-west Surety Insurance Company, 263 Ga. 697, 436 S.E.2d 642, 645 (1993). In light of the Supreme Court of Georgia’s opinion, attached hereto as an appendix, we vacate the district court’s grant of summary judgment in favor of Amwest and remand this case for further proceedings.

VACATED and REMANDED.

APPENDIX

The Hardaway Co.

v.

Amwest Surety Insurance Co.

S93Q1083.

In the Supreme Court of Georgia.

Decided Nov. 22, 1993.

BENHAM, Justice.

This case is before us on a certified question from the United States Court of Appeals for the Eleventh Circuit. The facts and procedural history of the case, as established in the opinion of the Eleventh Circuit 1 may be summarized as follows. Hardaway was prime contractor on a project of the Georgia Department of Transportation. Hardaway contracted with B & F Contractors, Inc. for the performance of certain grading work. Amwest guaranteed B & F’s performance. B & F demanded payment from Hardaway for additional costs incurred on the job, but Hardaway referred B & F to the Department of Transportation. When B & F continued to experience financial difficulty, Hardaway demanded that Amwest fulfill the subcontract, which Amwest did. B & F subsequently sued Hardaway for payment of the additional costs. In a settlement of that suit, Hardaway agreed to release B & F from Hardaway’s claims regarding default under the subcontract, but specifically reserved its warranty claims against B & F and specifically provided that it retained its rights against Amwest. For its part, B & F bargained away all claims it might have against Hardaway. Hardaway then sued Amwest for damages for B & F’s default. Amwest defended on the basis of the release from Hardaway to B & F, contending that the release terminated Hardaway’s rights against Amwest as surety. Amwest also filed a counterclaim for cost overruns which it contended it was entitled tp do as subrogee of B & F. The district court granted summary judgment to Amwest and, pursuant to a voluntary withdrawal, dismissed Amwest’s counterclaim. The Eleventh. Circuit reviewed the district court’s holdings and agreed that the surety contract did not contain Amwest’s consent to Hardaway’s release of B & F. However, noting confusion in Georgia case law on the subject, the Eleventh Circuit declined to rule on the effect of Hardaway giving the release without Am-west’s consent, and certified to this court the following question:

Whether a creditor’s agreement to release a principal debtor, which contains an express reservation of rights against the surety, is a release of the surety’s liability to the creditor on the surety bond or a mere covenant by the creditor not to sue the principal debtor when the surety has not consented to the creditor’s release of the principal debtor.

Hardaway Co. v. Amwest Sur. Ins. Co., 986 F.2d 1395, 1401 (11th Cir.1993).

*174 The correct rule is that stated in Schwitzerlet-Seigler Co. v. C & S Bank, 155 Ga. 740, 746, 118 S.E. 365 (1923):

[T]he release of the principal debtor, without the consent of the surety, releases the surety, unless the right to go against the surety is reserved in the instrument of release, or it appears from the whole transaction that the surety should remain bound.

The confusion the Eleventh Circuit perceived between the rule as stated in Schwit-zerlet-Seigler, supra, and the statement of the rule by the Georgia Court of Appeals in Hendricks v. Davis, 196 Ga.App. 286, 395 S.E.2d 632 (1990), apparently arose from the use of the conjunctive rather than the disjunctive in Hendricks, 2 requiring both consent by the surety and reservation of rights by the creditor. To that extent, Hendricks is overruled. Either the consent of the surety or the reservation of rights by the creditor will suffice to ensure the survival of the surety’s obligation after the release of the principal debtor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
15 F.3d 172, 1994 U.S. App. LEXIS 3648, 1994 WL 41301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-hardaway-company-plaintiff-counter-defendant-appellant-v-amwest-ca11-1994.