United States Fidelity & Guaranty Co. v. United States ex rel. Griscom-Spencer Co.

178 F. 692, 1910 U.S. App. LEXIS 4550
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 4, 1910
DocketNo. 34
StatusPublished
Cited by17 cases

This text of 178 F. 692 (United States Fidelity & Guaranty Co. v. United States ex rel. Griscom-Spencer Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. United States ex rel. Griscom-Spencer Co., 178 F. 692, 1910 U.S. App. LEXIS 4550 (3d Cir. 1910).

Opinion

J. B. McPHERSON, District Judge.

The nature of this controversy appears in the opinion delivered by Judge Holland in the circuit court, which is reported in 172 Fed., at page 269. Little need be added to his satisfactory discussion of the questions involved, and we shall there[693]*693fore content ourselves with noticing briefly the argument of the plaintiff in error.

1. It was argued that the limitation of one year prescribed by the act of 1905 (IT. S. Comp. St. Supp. 1907, p. 709, 1909, p. 948) governs the dispute, and that the present action is barred, because it was not brought by the use-plaintiff, who was a subcontractor, until more than a year after the final settlement betw eeu the United States and the principal contractor, the Neafie & Levy Ship & Engine Building Company. This precise question arose in another suit upon the same bond that is now before the court, and was decided by Judge Banning. It is sufficient to refer to his opinion in United States, to Use of Williamson Bros. Co. v. United States Fidelity & Guaranty Co. (C. C.) 171 Fed. 347, for the reasoning that fully justifies his conclusion that the limitation-prescribed by the act of 1905 does not apply to the present contract, which was fully completed several months before the statute was passed.

8. But it is also contended that when the present use-plaintiff, or its predecessor in interest, accepted the promissory note of the Neafie & Levy Company and had it discounted for the plaintiff’s own benefit, the time wherein payment of the claim could be demanded from the principal contractor was thereby irrevocably extended until the due date of the note, and that such extension so injured the surety as to justify the present denial of its obligation. The injury is said to have been caused in the following manner: The note was given to the use-plaintiff on September 15, 1901, and was not due until December 15th. The plaintiff immediately had the note discounted by a bank, and the result of the transaction was that the right of the plaintiff to demand payment of its account from the Neafie & Levy Company was, if not impliedly transferred to the bank, at least suspended until December 3 5th, while the bank also could make no demand until the note fell due. Meanwhile the Neafie & Levy Company made a full settlement in October wfith the United States for all that was due upon the contract, and, having thus received and otherwise used money that ought to have been applied to the plaintiff’s claim, went into the hands of a receiver on December 9th, a few days before the note fell due. ft is therefore argued (to .use the language of the brief on behalf of the surety company) that:

“The effect of extending the time of payment by tailing the note of Ihe Neafie & Levy Company was to deprive the surety on the bond for iho i«iyment of claims of persons supplying labor and materials to the contractor of the opportunity of preventing the United States from paying over the retained percentages or the balance of the contract price to the Neafie & Levy Company until the materialmen were paid, or unless payment of the mate-rialmen out of the sums due by the United States was assured. This was sufficient to release the surety on the bond.”

As will be seen, this argument rests solely upon the assumpi ion that an injury to the surety is to be presumed, either prima facie or conclusively, from the mere fact that the Neafie & Levy Company received an extension of time, although there is no averment of actual injury to the surety in the affidavit of defense, and although no fact is set forth therein from which injury can be inferred, except the fact that [694]*694a receiver was appointed for the Neafie & Levy Company on December 9th before the maturity of the note. But, in suits upon bonds given to the government to secure a contractor’s faithful performance of his undertaking, the mere fact that the time of payment was extended for a reasonable time raises no presumption of injury to the surety. This was decided by the Supreme Court in Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 24 Sup. Ct. 142, 48 L. Ed. 242, and there is nothing in the affidavit of defense to bring the surety company within the exception stated by Mr. Justice Brown. His language is this:

“The facts of this case do not call for an expression of opinion as to whether, if an unusual credit were given, and in the meantime the principal obligor had become insolvent, or the surety were otherwise damnified by the delay, it might not be exonerated. Since neither of these contingencies supervened in this case, we are remitted to the naked proposition whether the giving of a customary credit, with no evidence of loss thereby occasioned, is sufficient to discharge the surety.”-

In the Circuit Court it was held by Judge Holland that a credit for three months was not “unusual,” and therefore that the situation referred to in the foregoing quotation had not arisen. We do not crit-icise this holding in the slightest degree — indeed, its correctness was admitted by the plaintiff in error as a general proposition — but we desire to point out another reason why such a situation is not now presented. And the reason is this: The surety company has not averred that the Neafie & Levy Company became insolvent before the maturity of the note, or that harm was done in any manner by the acceptance of the contractor’s note. We have no information whatever concerning the reason which induced the common pleas of Philadelphia county to appoint the receiver; but it is well known that such an appointment may be made on other grounds than insolvency — although this is, no doubt, the most frequent ground — and from the failure of the surety company to do more than aver the bare fact of the receivership we feel justified in supposing that the affidavit has gone as far as it properly could. And there is no averment of injury of any kind, either actual or contingent, caused by the extension of the time of payment. All that the affidavit contains on this- subj ect is to be found in the following paragraph:

“Before tbe maturity of said note, to wit, on or about October 31, 1904, tfie War Department of the United States made final settlement with the Neafie & Levy Ship & Engine Building Company for the contract price on the contract aforesaid, and on December 9, 1904, before the maturity of the said note, John W. Grange and Sommers N. Smith were appointed receivers of the Neafie & Levy Ship & Engine Building Company by the court of common pleas. No. 5, of the county of Philadelphia and state of Pennsylvania.
“The defendant had no knowledge of the acceptance of said note by the James Reilly Repair & Supply Company (the plaintiff’s predecessor) nor of the extension of time for the payment of the indebtedness of the Neafie & Levy Ship & Engine Building Company resulting therefrom.”

It should be remembered, we think, in considering this defense, that .there has been some change of attitude in the courts toward the obligation of a corporate surety. The subject has been recently passed upon in the case of Baglin v. Title, etc., Co. (C. C.) 166 Fed. 356, affirmed by [695]*695the Court of Appeals 178 Fed. 682, and we may be permitted to quote with approval what was there said by the Circuit Court:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fred Christensen, Inc. v. Hansen Construction Co.
21 P.2d 195 (Oregon Supreme Court, 1933)
Hammond Lumber Co. v. Richardson Bldg. & Eng'g Co.
285 P. 851 (California Supreme Court, 1930)
Maryland Casualty Co. v. Ohio River Gravel Co.
20 F.2d 514 (Fourth Circuit, 1927)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)
National Surety Co. v. Lincoln County
238 F. 705 (Ninth Circuit, 1917)
Standard Salt & Cement Co. v. National Surety Co.
158 N.W. 802 (Supreme Court of Minnesota, 1916)
American Bonding Co. v. United States
233 F. 364 (Third Circuit, 1916)
People ex rel. T. B. Townsend Brick & Contracting Co. v. Bowen
187 Mich. 257 (Michigan Supreme Court, 1915)
Pittsburg—Buffalo Co. v. American Fidelity Co.
219 F. 818 (Third Circuit, 1915)
City of Topeka v. Federal Union Surety Co.
213 F. 958 (Eighth Circuit, 1914)
Bross v. McNicholas
133 P. 782 (Oregon Supreme Court, 1913)
First National Bank v. Livermore
133 P. 734 (Supreme Court of Kansas, 1913)
United States ex rel. General Electric Co. v. Schofield Co.
182 F. 240 (U.S. Circuit Court for the District of Eastern Pennsylvania, 1910)
United States ex rel. J. B. Van Sciver Co. v. United States Fidelity & Guaranty Co.
178 F. 721 (U.S. Circuit Court for the District of Eastern Pennsylvania, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. 692, 1910 U.S. App. LEXIS 4550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-united-states-ex-rel-ca3-1910.