United States ex rel. General Electric Co. v. Schofield Co.

182 F. 240, 1910 U.S. App. LEXIS 5642
CourtU.S. Circuit Court for the District of Eastern Pennsylvania
DecidedOctober 13, 1910
DocketNo. 1,034
StatusPublished
Cited by13 cases

This text of 182 F. 240 (United States ex rel. General Electric Co. v. Schofield Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. General Electric Co. v. Schofield Co., 182 F. 240, 1910 U.S. App. LEXIS 5642 (circtedpa 1910).

Opinion

J. B. McPHERSON, District Judge.

This is a suit by a subcontractor upon a bond given to the United States by the principal contractor to insure the faithful performance of certain work. It is brought in the Eastern district of Pennsylvania against both principal and surety, but the surety alone has made defense. Judgment is resisted! on three grounds; one being that the suit has been pre[242]*242maturely brought,-and another that in any event it has been brought in the wrong district. The facts upon which these two defenses rest are as follows:

The original contract was entered into between the United States and the Schofield Company on March 9, 1903. The subcontract with the use plaintiff,. the General Electric Company, was made on May 10, 1903. The Title Guaranty & Surety Company became surety on May 24, 1904, taking the place of another company whose bond had become unsatisfactory. The contract had been previously modified by supplemental agreements dated December 14, 1903, and March 1, 1904, and the title company’s obligation covered the contracts thus modified. Afterwards, on June 21, 1904, another supplemental agreement was made to which the title company consented. Up to this point the right of action upon the contract, and the consequences to follow from such a suit, were undoubtedly governed by Act Aug. 13, 1894, c. 280, 28 Stat. 278 (U. S. Comp. St. 1901, p. 2523); no other act having then been passed. Under this statute the right of the subcontractor to sue upon the bond was not limited in time or by any other express condition, and the United States had no priority of lien upon the fund recovered. United States, to Use, etc., v. Fidelity, etc., Co. (C. C.) 171 Fed. 247, approved in Fidelity, etc., Co. v. U. S. (C. C. A.) 178 Fed. 692; American Surety Company v: Cement Co. (C. C.) 96 Fed. 25; U. S. v. Heaton, 128 Fed. 414, 63 C. C. A. 156.

On February 24, 1905, Congress passed another act (Act Feb. 24, 1905, c. 778, 33 Stat. 811 [U. S. Comp. St. Supp. 1909, p. 948]) on this subject which makes important changes in the rights of a subcontractor. Under this statute no suit can be brought on the bond by any' one until after the completion and final settlement of the contract. During six months thereafter the United States alone can sue. If no such suit is brought, a subcontractor may sue during the six months immediately succeeding; but he may not sue at all after the expiration of one year from the completion of the work. Priority is also given to the claim of the United States. After the date of this act, three additional supplemental contracts were made between the United States and the Schofield Company, to all of which the surety agreed.

The present suit was brought July 5, 1910, and the parties agree that all the work done and the materials furnished by the General Electric Company were done and furnished after the act of 1905 was passed. Is the suit to be governed by the act of 1894 or by the act of 1905 ? As it seems to me, the answer should be — the act of 1894. It is undoubtedly true that some provisions of the act of 1905 are concerned with the remedy alone, and, if it were clear that Congress intended these provisions to apply to suits or to contracts then pending, the courts would be bound to obey the act as far as possible. But there is one provision at least which seems to be not a mere matter of procedure, but of substantial importance, namely, the clause that gives to the United States priority over a subcontractor. Under the act of 1894 the General Electric Company entered into this subcon[243]*243tract and thereby acquired the right to sue. without special limitation or condition, and the right also to share in the fund recovered proportionately with all other claimants, including the United, States. This right thus to share was valuable, and upon well-established principles it is not to be presumed that Congress intended to disturb it, although the power so to do may exist. Indeed, the contrary presumption is to be applied. In the words of the Supreme Court in U. S. Fidelity Co. v. Struthers Co., 209 U. S. 314, 28 Sup. Ct. 539 (52 L. Ed. 804):

“There are certain principles which have been adhered to with great strictness by the courts in relation to the construction of statutes as to whether they are or are not retroactive in their effect. The presumption is very strong that a statute was not meant to act retrospectively, and it ought never to receive such a construction if it is susceptible of any other. It ought not to receive such a construction unless the words used are so clear, strong, and imperative that no other meaning can be annexed to them, or unless the intention of the Legislature cannot be otherwise satisfied. Dash v. Van Kleeck, 7 Johns. 499 [5 Am. Dec. 291]; Jackson v. Van Zandt, 12 Johns. 169; United States v. Heth, 3 Oranch, 399, 414 [2 L. Ed. 479]; Southwestern Coal Co. v. McBride, 185 U. S. 499, 503 [22 Sup. Ct. 763, 46 L. Ed. 1010]; United States v. American Sugar Co., 202 U. S. 563, 577 [26 Sup. Ct. 717, 50 L. Ed. 1149].”

Applying this rule of construction, the court went on to decide that the act of 1905 does not show an intention ón the part of Congress to affect contracts made before its passage, and that it is not retrospective in any respect.

After February 24, 1905, the Schofield Company and the use plaintiff with the consent of the surety entered into certain supplemental agreements; but these were not new and independent transactions. They were parts and incidents of the original contract, and should be regarded as matters omitted therefrom and afterwards supplied. They all recognized the desirability of certain changes; declared that they do not in any manner or degree affect, modify, alter, omit, or vitiate any provision or requirement of the original contract except as specifically stated; and expressly provided:

“That nothing contained or stated in this agreement, and nothing done or required under its terms, shall operate or be held to in any manner release, reduce, or otherwise affect, the bond attached to the aforesaid contract, but the same shall be and remain in full force and virtue in the same manner and with like effect as though the modifications herein provided for had been included in and made a part of the aforesaid contract at the time of the execution of the aforesaid seal,” etc.

Assuming this conclusion to be correct, has the Circuit Court for the Eastern District of Pennsylvania lawfully acquired1 jurisdiction of the person of the surety? The statute governing this question was passed on August 13, 1894 (Act Aug. 13, 1894, c. 282, 28 Stat. 279 [U. S. Comp. St. 1901, p. 2315]), the same day on which the other act already referred to was approved. It provides:

“Sec. 5. That any surety company doing business under the provisions of this act may be sued in respect thereof in any court of the United States which has now or hereafter may have jurisdiction of actions or suits upon such recognizance, stipulation, bond, or undertaking, in the district in which said recognizance, stipulation, bond, or undertaking was made or guaranteed, or in the district in which the principal office of such company is located. [244]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wolfskill v. Egan
504 A.2d 326 (Supreme Court of Pennsylvania, 1986)
Tellez v. Canton Railroad Co.
129 A.2d 809 (Court of Appeals of Maryland, 1983)
AMERICAN AIR FILTER CO. INC. v. Innamorati Bros. Inc.
260 N.E.2d 718 (Massachusetts Supreme Judicial Court, 1970)
Jordan v. Morgan, Adm'x
249 A.2d 124 (Court of Appeals of Maryland, 1969)
Whalen v. Devlin Lumber & Supply Corp.
246 A.2d 247 (Court of Appeals of Maryland, 1968)
Dominion Culvert & Metal Corp. v. United States Fidelity & Guaranty Co.
120 S.E.2d 518 (Supreme Court of South Carolina, 1961)
Molesworth v. Schmidt
75 A.2d 100 (Court of Appeals of Maryland, 1950)
National Surety Corp. v. Wunderlich
111 F.2d 622 (Eighth Circuit, 1940)
United States v. Ætna Casualty & Surety Co.
5 F.2d 412 (Sixth Circuit, 1925)
United States ex rel. Hollinger v. Stannard
206 F. 326 (M.D. Pennsylvania, 1913)
United States ex rel. Harlan & Hollingsworth v. Scofield Co.
191 F. 944 (U.S. Circuit Court for the District of Middle Pennsylvania, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
182 F. 240, 1910 U.S. App. LEXIS 5642, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-general-electric-co-v-schofield-co-circtedpa-1910.