Dominion Culvert & Metal Corp. v. United States Fidelity & Guaranty Co.

120 S.E.2d 518, 238 S.C. 452, 92 A.L.R. 2d 1244, 1961 S.C. LEXIS 110
CourtSupreme Court of South Carolina
DecidedJune 12, 1961
Docket17797
StatusPublished
Cited by12 cases

This text of 120 S.E.2d 518 (Dominion Culvert & Metal Corp. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dominion Culvert & Metal Corp. v. United States Fidelity & Guaranty Co., 120 S.E.2d 518, 238 S.C. 452, 92 A.L.R. 2d 1244, 1961 S.C. LEXIS 110 (S.C. 1961).

Opinion

Lewis, Justice.

This is an action by the appellant against the respondent, as surety on a contractor’s bond executed in connection with the construction of a public improvement, to recover for materials furnished to a subcontractor. The appeal is from an order of nonsuit entered by the trial court at the conclusion of appellant’s testimony.

C. P. Neal Construction Company, hereafter called Neal, entered into a contract with School District No. 3 of York County for the construction of a school building at Clover, South Carolina, and filed a bond with the respondent, United States Fidelity and Guaranty Company, as surety, guaranteeing the faithful performance of the contract and the pay *455 ment for all labor and materials used in the construction. Neal subcontracted the roofing work on the school building to Rollins and Company, hereafter called Rollins. Rollins purchased from the appellant, Dominion Culvert and Metal Corporation, materials which were used on the school job in the performance of its subcontract with Neal. Before final completion of the subcontract, Rollins went into bankruptcy, owing to appellant a balance for materials furnished for the school building.

Before Rollins went into bankruptcy, Neal had paid to it a part of the subcontract price, a portion of which had been paid, at the request of Rollins, jointly to it and the appellant. After the business of Rollins was taken over by the bankruptcy court, Neal paid to the trustee in bankruptcy, upon demand of the trustee, the balance due Rollins and received from said trustee a release of Neal and the School District from any liability to Rollins arising by virtue of the subcontract.

The appellant filed its claim for the balance due it by Rollins in the bankruptcy proceedings as a common creditor and received its pro rata share in the distribution of the assets of the bankrupt. After receipt of this payment from the trustee in bankruptcy, this action was instituted against respondent as surety of the contractor to recover the balance due on the claim of appellant for materials furnished to Rollins, the subcontractor.

This appeal presents the following question for decision: Is the surety on a contractor’s bond, executed in connection with the construction of a public improvement, liable for unpaid claims of a materialman of a subcontractor who has become bankrupt, where (1) the subcontractor has been paid in full by the contractor, (2) a release has been executed by the trustee in bankruptcy releasing the contractor and the owner from any liability to the bankrupt subcontractor arising by virtue of the subcontract, and (3) the materialman has filed his claim in the bankruptcy court as a common *456 creditor and received his pro rata share of the proceeds of the bankrupt estate ?

The contract entered into with the School District by the contractor required the contractor to furnish all materials and perform all of the work as shown on the drawings and specifications for the school building. The bond required by the School District in connection with the contract, and signed by the respondent as surety, guaranteed that the contractor would “pay all persons who have furnished labor or materials for use in or about the improvement”; and provided, that “all persons who have furnished labor or material for use in or about the improvement shall have a direct action under the bond.” It is undisputed in this appeal that the materials furnished by the appellant to the subcontractor were used in the construction of the school building.

It is now settled by the decisions of this Court that a contractor and the surety on his bond, given to secure payment for labor and materials furnished in the construction of a public improvement, whether the bond be required by statute or not, are liable not only for labor and materials furnished to the contractor, but also for those furnished to a subcontractor. Molony & Carter Co. v. Pennell & Harley, 169 S. C. 462, 169 S. E. 283; Miller v. Cornell-Young Co., 171 S. C. 228, 171 S. E. 790; and that a materialman, may bring a direct action against the surety on such bond. Mack Mfg. Co. v. Massachusetts Bonding & Insurance Co., 103 S. C. 55, 87 S. E. 439; Standard Oil Co. of New Jersey v. Powell Paving & Contracting Co., 139 S. C. 411, 138 S. E. 184; American Hardware & Equipment Co. v. Detroit Fidelity & Surety Co., 159 S. C. 263, 156 S. E. 770.

The contractor and the respondent, as surety, assumed the obligation to pay all persons who furnished labor or material for use in or about the construction of the school building. Their obligation arises by virtue of their contract, required by the public authorities, to pay for *457 the labor and materials furnished for the public improvement. If the contractor elects to furnish the labor and materials thiough a subcontractor, he and his surety are still liable under their contract to pay for them upon default of the subcontractor, for, as stated in the case of United States for the Use of Hill v. American Surety Company, 200 U. S. 197, 26 S. Ct. 168, 171, 50 L. Ed. 437: “If the contractor see fit to let the work to a subcontractor, who employs labor and buys materials which are used to carry out and fulfil the engagement of the original contract to construct a public building, he is thereby supplied with the materials and labor for the fulfilment of his engagement as effectually as he would have been had he directly hired the labor or bought the materials.”

The fact that the subcontractor became insolvent does not affect the liability of the contractor and the surety on his bond. Insolvency of the subcontractor in such cases is a risk of the contractor and his surety. If the contractor or his surety desire to protect themselves against unpaid claims of a subcontractor, it would be very easy for them to require that the subcontractor provide adequate bond or other security which would indemnify them against any loss by reason of the subcontractor’s insolvency. Moore v. Builders’ Material Co., 192 N. C. 418, 135 S. E. 113. Standard Accident Insurance Co. v. Simpson, 4 Cir., 64 F. (2d) 583, 589. In the last cited case the court said:

“Each of the bonds, signed by the contractor as well as the surety, guaranteed that the contractor would ‘pay when and as due all lawful claims for labor performed or materials and supplies furnished for use in and about the construction of said highway or highway structures’; and we do not see how the letting of a part of the work to a subcontractor could be held to absolved the contractor or the surety from the obligation so undertaken. The public authorities were interested in providing that those who furnished labor or materials for the construction of *458

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frost v. Williams Mobile Offices, Inc.
795 F.2d 372 (Fourth Circuit, 1986)
Rock Hill National Bank v. Honeycutt
344 S.E.2d 875 (Court of Appeals of South Carolina, 1986)
Frost v. Williams Mobile Offices, Inc.
343 S.E.2d 441 (Supreme Court of South Carolina, 1986)
Bell v. Forrest Paschal Machinery Co.
282 S.E.2d 232 (Supreme Court of South Carolina, 1981)
L. M. White Contracting Co. v. St. Joseph Structural Steel Co.
488 P.2d 196 (Court of Appeals of Arizona, 1971)
Wells-Stewart Construction Co. v. Martin Marietta Corp.
442 P.2d 119 (Arizona Supreme Court, 1968)
Bradley v. Straus-Frank Company
414 S.W.2d 504 (Court of Appeals of Texas, 1967)
Noland Company v. Realty Corporation
147 S.E.2d 105 (Supreme Court of Virginia, 1966)
Roberts v. Lawrence
133 S.E.2d 74 (Supreme Court of South Carolina, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
120 S.E.2d 518, 238 S.C. 452, 92 A.L.R. 2d 1244, 1961 S.C. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dominion-culvert-metal-corp-v-united-states-fidelity-guaranty-co-sc-1961.