Noland Company v. Realty Corporation

147 S.E.2d 105, 206 Va. 938, 1966 Va. LEXIS 173
CourtSupreme Court of Virginia
DecidedMarch 7, 1966
DocketRecord 6118
StatusPublished
Cited by6 cases

This text of 147 S.E.2d 105 (Noland Company v. Realty Corporation) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noland Company v. Realty Corporation, 147 S.E.2d 105, 206 Va. 938, 1966 Va. LEXIS 173 (Va. 1966).

Opinion

Carrico, J.,

delivered the opinion of the court.

*939 Noland Company, Incorporated, filed a motion for judgment against West End Realty Corporation, doing business as Kayhoe Construction Corporation, and Peerless Insurance Company.

The motion sought recovery of the sum of $6,288.58, alleged to be due for materials furnished by Noland to a subcontractor of Kay-hoe for use in certain construction work being performed by Kay-hoe for Hermitage Methodist Homes of Virginia, Inc. Peerless was surety on a labor and material payment bond given by Kayhoe to Hermitage and the motion sought recovery against the bond.

Kayhoe and Peerless filed grounds of defense asserting that they had fully performed under the bond and were not liable for Noland’s claim.

The parties entered into a stipulation of the facts in the case and the matter was submitted to the trial court, without a jury, for decision. The court ruled that Kayhoe and Peerless were not liable under the bond to Noland and entered final judgment accordingly, Noland was granted this writ of error.

From the stipulated facts, it is learned that Kayhoe, on January 19, 1962, entered into a contract with Hermitage for additions and alterations to a building owned by Hermitage. The contract price was $268,418.00. The contract required Kayhoe to “provide and pay for all materials [and] labor . . . necessary for the execution and completion of the work.”

A further provision of the contract required the general contractor, Kayhoe, to “furnish a surety bond ... in an amount at least equal to one hundred per cent (100%) of his contract price, as security for the faithful performance of this contract and as security for the payment of all persons performing labor and furnishing materials in connection with his contract. . . .”

The bond here in dispute was executed by Kayhoe and Peerless, pursuant to the requirement of the contract, in the sum of $268,-418.00, the amount of the contract price. Hermitage was named as the obligee, “for the use and benefit of claimants as hereinbelow defined.”

The bond was a labor and material payment bond only, but a note contained on its face stated that it was “issued simultaneously with another bond in favor of the owner conditioned for the full and faithful performance of the contract.”

The condition of the bond in question was “that if the Principal [Kayhoe] shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required *940 for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect. . . .”

A claimant was defined in the bond as “one having a direct contract with the Principal or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract. . . .” The bond, provided that if a claimant had not been paid for ninety days after last performing work or furnishing materials, then such claimant “may sue on this bond . . . prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon.”

The bond required a claimant, other than one having a direct contract with Kayhoe, to give written notice before “suit or action shall be commenced hereunder by any claimant.”

Finally, the bond contained this crucial provision in paragraph four:

“The amount of this bond shall be reduced by and to the extent of any payment or payments made in good' faith hereunder, inclusive of the payment by Surety of mechanics’ liens which may be filed of record against said improvement, whether or not claim for the amount of such lien be presented under and against this bond.”

In carrying out the construction work for Hermitage, Kayhoe entered into a subcontract with Dixie Plumbing and Heating Company, Inc., for the installation of heating, ventilating and air-conditioning systems, in the sum of $77,000.00.

Noland supplied Dixie with materials for use in the construction work. In the stipulation of facts, the parties agreed that the amount sued for by Noland, $6,288.58, was due and owing to Noland by Dixie; that Noland qualified under the definition of “claimant” in the bond,, and that Noland gave the necessary written notice of its claim.

Kayhoe paid Dixie in full for all amounts due for work performed under the subcontract. Dixie, however, became insolvent, without paying Noland, and was adjudicated bankrupt.

Kayhoe, in good, faith, paid the total sum of $270,636.02 to persons or corporations having direct contracts with Kayhoe and falling within the definition .of “claimants” .in the bond. • Peerless made no. payments under the bond here in dispute.

Against this factual background, Kayhoe and Peerless contend that they discharged all liability under the bond because Kayhoé made payments totaling $270,636.02, an amount in excess of the *941 contract price and of the penal sum of the bond, to persons and corporations having direct contracts with Kayhoe and falling within the definition of “claimants” in the bond.

Noland contends, on the other hand, that the payments relied upon by Kayhoe and Peerless were made in the normal course of Kayhoe’s business, and not under the bond, and did not operate to discharge the liability of Kayhoe and Peerless under the bond.

The question for determination, therefore, is whether the payments made by Kayhoe acted to discharge the liability of Kayhoe and Peerless under the bond.

The precise question here presented has not been previously before this court nor, from our research, does it appear to have been before any other court of last resort. Questions of a somewhat similar nature, dealing with bonds required by statutes or contracts where public work was involved, have been previously decided in cases upon which Noland now relies.

In those decided cases, the rule was established that liability under a bond is not affected by the fact that the general contractor has paid his subcontractor the full subcontract price, where claim is made against the bond by one who performs labor for or furnishes material to the subcontractor. See Mankin v. United States Use of Ludowici-Celadon Co., 215 U. S. 533, 54 L. ed. 315, 30 S. Ct. 174; United States v. Starrett Bros. & Eken, 18 F. Supp. 671; Dominion Culvert & M. Corp. v. United States F. & G. Co., 238 S. C. 452, 120 S. E. 2d 518.

But, Kayhoe and Peerless argue, those cases did not involve the situation which is before us, where the general contractor has paid to his subcontractors an amount equal to or in excess of the prime contract price and the penal sum of the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XL Specialty Ins. Co. v. Dept. of Transp.
611 S.E.2d 356 (Supreme Court of Virginia, 2005)
Colonial Mechanical Corp. v. Seaboard Surety Co.
14 Va. Cir. 178 (Chesterfield County Circuit Court, 1988)
Board of Supervisors v. Safeco Insurance Co. of America
310 S.E.2d 445 (Supreme Court of Virginia, 1983)
BD. OF SUP'RS OF STAFFORD CTY. v. Safeco Ins.
310 S.E.2d 445 (Supreme Court of Virginia, 1983)
Vulcan Materials Co. v. Betts
315 F. Supp. 1049 (W.D. Virginia, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
147 S.E.2d 105, 206 Va. 938, 1966 Va. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noland-company-v-realty-corporation-va-1966.