Vulcan Materials Co. v. Betts

315 F. Supp. 1049, 1970 U.S. Dist. LEXIS 10519
CourtDistrict Court, W.D. Virginia
DecidedAugust 19, 1970
DocketNo. 67-C-42-H
StatusPublished
Cited by6 cases

This text of 315 F. Supp. 1049 (Vulcan Materials Co. v. Betts) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vulcan Materials Co. v. Betts, 315 F. Supp. 1049, 1970 U.S. Dist. LEXIS 10519 (W.D. Va. 1970).

Opinion

OPINION

WIDENER, District Judge.

Vulcan Materials Company commenced this action to recover $44,989.39 from the prime contractor, his bondsman, and a supplier of crushed rock, under a public construction contract. Jurisdiction is based on diversity of citizenship.

The case is submitted for decision on a stipulation of facts, exhibits, and a single deposition. Defendant, Oman Construction Company (hereinafter referred to as Oman), entered into a contract dated December 3, 1965, with the Commonwealth of Virginia for the con[1050]*1050struction of a 5.183 mile portion of Route 256 in Augusta County. By the terms of the contract, Oman agreed to “do all the work and furnish all the materials” necessary to carry out the agreement.

On the same date, Oman, as principal, and Reliance Insurance Company (hereinafter referred to as Reliance), as surety, executed the contract bond required by statute in the amount of $796,860.00 in favor of the Commonwealth of Virginia. That bond guaranteed that Oman would “promptly pay * * * for labor and material incurred by said principal.”

By purchase order dated July 18, 1966, Oman contracted to purchase from defendant, Fred K. Betts, III, Quarry, Inc., (hereinafter referred to as Betts) 47,030 tons of stone and material to be used by Oman on the aforesaid project. The purchase order called principally for “C.B.R. 30 Select Material, Type 1, to be delivered in proper condition to meet C. B.R. 30 compaction” and specifications of the Department of Highways. The material was to be delivered to Oman’s spreader boxes on the grade at the rate of at least 4,000 tons per 9-hour day, on 72 hour notice. A smaller item of 1,100 tons of crusher run %" rock mentioned in the purchase order to Betts is not mentioned in the contract between Oman and the Highway Department, is not referred to in any of the stipulations, and will not be further considered.

By letter of August 18, 1966, Betts, in turn, ordered from plaintiff, Vulcan, substantially all of the C.B.R. 30 Select Material, Type 1, stone it had contracted to prepare and supply to Oman. Vulcan acknowledged the order August 22, 1966. Consequently, Vulcan actually prepared to specifications the stone that was used in building the highway. Betts then hauled or caused the hauling of the stone to the spreader boxes at the grade site. Vulcan billed Betts and Betts billed Oman. Oman paid Betts for all materials delivered to the construction site until on or about April 17, 1967, at which time Oman was advised that Betts’ payments for the materials purchased from Vulcan were in arrears. Thereafter, Oman made two payments by checks aggregating $1,760.61 made payable to Betts, endorsed by Betts, and delivered to plaintiff by Oman, leaving a balance of $44,989.39 due plaintiff.

A default judgment has been entered against Betts, which failed to appear. Vulcan now seeks recovery against the prime contractor and its surety on the bond, the theory being that it has a direct statutory right of action against Oman and Reliance for failure to comply with 1950 Code of Virginia § 11-20 requiring bond of a subcontractor.

The pertinent portion of § 11-20 which applies to public highway construction contracts reads as follows:

“No contractor * * * shall subcontract any work required by the contract except under the following conditions: each subcontractor shall furnish and the contractor shall require * * * a payment bond with surety thereon * * * which shall be conditioned upon the payment to all persons who have, and fulfill, contracts which are directly with the subcontractor for performing labor and furnishing materials in the prosecution of the work provided for in the subcontract. ' Every such bond shall be construed, regardless of its language, as incorporating, within its provisions, the obligation to pay those persons who furnish labor or materials as aforesaid, provided, however, that subcontracts between the contractor and a manufacturer or fabricator shall be exempt from the provisions requiring a payment bond. * * *”

Oman did not require and Betts did not post bond according to the foregoing code section. It is settled in Virginia that the prime contractor and surety on the bond are liable for claims against a subcontractor for labor, material and supplies furnished, all of which were used in the construction of the road. Fidelity and Casualty Company v. Copenhaver, 159 Va. 126, 165 S.E. 528 [1051]*1051(1932); see Luck & Sons v. Boatwright, 157 Va. 490, 162 S.E. 53 (1932) (applying Maryland law). The bond in Copenhaver was identical to the one executed by Oman. The contractors were held liable in both Boatwright and Copenhaver, even though they did not directly incur the debt. The court, in Boatwright stated that the settled policy of the law is “to protect those who furnish labor, supplies and material used in and about the construction of public work, and, of this, contractors must take cognizance. Against the shortcomings of subcontractors, they and their sureties can be amply protected by proper bond.” 157 Va. 490, 505,162 S.E. 53, 58.

Although suppliers of subcontractors may recover on the bond of the prime contractor in Virginia, the statute makes no attempt to define the term “subcontractor”, nor has any Virginia case been found which turns on the meaning of the term “subcontractor.”

Defendants urge that plaintiff may not recover because Betts was only a materialman, not a subcontractor, since it only supplied gravel for the job. They support their contention by the opinion of the state highway commissioner that Betts was only a supplier. They also point to the conjunctive language of highway department regulations which mention “labor and materials” [italics added], and contend that to be a subcontractor a person must furnish both, but urge that Betts furnished only materials. A careful examination of the Oman-Betts contract discloses that Betts was a subcontractor.

First, the purchase order to Betts was in fact a contract for “Select Material, Type 1, Min. C.B.R. 30, 47,030 Tons”, which was all of a specific part (item 4) of the contract requirement according to the proposal dated November 10, 1965. MacEvoy Co. v. United States, 322 U.S. 102, 108, 109, 64 S.Ct. 890, 88 L.Ed. 1163 (1944). It was for the entire rock requirement under the contract. And that requirement was an integral part of the contract to build the road. See Miller Equipment Company v. Colonial Steel and Iron Company, 383 F.2d 669, 674 (4th Cir. 1967), cert. denied 390 U.S. 955, 88 S.Ct. 1049, 19 L.Ed.2d 1148 (1968). Second, in addition to being 100% of the rock requirement, the contract for the C.B.R. Material amounted to more than 9% of the total contract price on the entire project. Third, the work performed by Betts in preparing material to meet specific compaction requirements saved Oman labor it would otherwise have had to perform with its own machinery in meeting the compaction requirements of the State Highway Department. The uncontradicted evidence in the case discloses that compaction is ordinarily the responsibility of the prime contractor. Fourth, Betts either hauled the material or arranged to have it hauled to the grade site. Fifth, the agreement between Oman and Betts was of a continuing nature for a specific part jqf the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
315 F. Supp. 1049, 1970 U.S. Dist. LEXIS 10519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vulcan-materials-co-v-betts-vawd-1970.