Fidelity & Casualty Co. v. Copenhaver Contracting Co.

165 S.E. 528, 159 Va. 126, 1932 Va. LEXIS 179
CourtSupreme Court of Virginia
DecidedSeptember 22, 1932
StatusPublished
Cited by9 cases

This text of 165 S.E. 528 (Fidelity & Casualty Co. v. Copenhaver Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Casualty Co. v. Copenhaver Contracting Co., 165 S.E. 528, 159 Va. 126, 1932 Va. LEXIS 179 (Va. 1932).

Opinions

Gregory, J.,

delivered the opinion of the court.

The appellant, which was the complainant in the court below, is complaining of a decree wherein it was adjudged, among other things, that it deposit to the credit of the court, in the State-Planters Bank and Trust Company of Richmond, the sum of $62,700.00, together with six per cent interest thereon from October 3, 1928. The principal sum was the full penalty of a certain road contractor’s bond, which was executed by the appellant as surety, for the Copenhaver Contracting Company, Incorporated, under a [130]*130highway construction contract, entered into between the Highway Commission of Virginia and the Construction Company.

The Copenhaver Contracting Company, Incorporated, a North Carolina corporation, secured two contracts from the Highway Commission to construct, during 1928, two road projects in Franklin county, designated as Projects F520-B4C and F520A. The first of these projects was let under a contract of April 30, 1928, and the second under a contract of May 18, 1928. Under the first contract the Copenhaver Contracting Company agreed to grade and construct a part of the road, for a distance of seven miles, under the terms and conditions clearly set forth in the first contract. In order to secure the fulfillment of the first contract, which was in the usual form adopted by the Highway Commission, under authority of statute, the appellant executed its bond bearing date on May 28, 1928, in the penal sum of $62,700.00.

Under the second contract, embracing the second project, in which the Copenhaver Contracting Company undertook to construct another section of the same road, the Columbia Casualty Company executed its bond to secure the fulfillment of the second contract.

Within a very short time after the appellant had executed the bond mentioned under the first contract, which was the principal contract, the Copenhaver Contracting Company, by written contract, sub-let to the Crowell Contracting Company, Incorporated, another North Carolina corporation, a substantial portion of the work.

Before the completion of either project undertaken in either contract, the Highway Commission, in conformity with the privilege therein contained, declared both contracts forfeited by the Copenhaver Contracting Company and due notice was given the appellant surety company and the Columbia Casualty Company to elect between taking over the work and completing the same, or relinquishing the same in favor of the Highway Commission, to be com[131]*131pleted by said Commission at the risk of the two surety companies. The Columbia Casualty Company, elected to complete the contract embracing the project for which it was responsible and in accordance with said' election, did complete its contract and now has due it by the Highway Commission a balance of $6,851.13.

The appellant, which was the surety under the first contract, did not elect to complete the project embraced therein. This project was taken over by the Highway Commission and completed, and there is due the said Commission 'for this work approximately $18,000.00, which represents the additional cost and expense incurred, by reason of the default of the Copenhaver Contracting Company.

After the work under the main contract was taken over by the Highway Commission, numerous creditors who had furnished labor, supplies and certain equipment to both the general contractor, and the subcontractor, instituted actions against them and the appellant surety, in the Circuit Court of Franklin county, and later the Crowell Contracting Company, the subcontractor, instituted an attachment proceeding in the Circuit Court of the city of Richmond against the Copenhaver Contracting Company and the appellant as principal defendants. In the meantime several of the Franklin county actions had been removed to the District Court of the United States for the Western District of Virginia. Later, the appellant surety, instituted the present suit, in the Circuit Court of the city of Richmond, in which the various plaintiffs in the pending actions were made defendants. The State of Virginia was also made a defendant, as well as all of those who asserted claims against either the Copenhaver Contracting Company or the Crowell Contracting Company.

The purpose of this suit was to convene these parties in a single suit, in order that the rights and liabilities of the appellant, who was, in the lower court, the complainant, and others might be ascertained and determined in this [132]*132single cause; that the appellant might pay into court such sum as might be established as due by it under its obligation in the surety bond, and that such sum as might be found due by the appellant, be apportioned and applied in accord with the respective rights and priorities of the various creditors, as should be established by the court.

The circuit court entertained jurisdiction of the suit and enjoined the various creditors who had instituted actions, from further proceeding therein. Various answers and petitions were filed and the cause was referred to a commissioner in chancery by decree of December 3, 1929, wherein all matters and issues were submitted to the commissioner and he was directed to report to the court. On November 24, 1930, he returned this report, establishing therein the amounts due to the respective claimants. The aggregate amount found by the commissioner, to be due the various creditors, was $64,462.70. This was in excess of the full penalty of the bond, which was $62,700.00.

The commissioner reported a claim in favor of the Crowell Contracting Company, the subcontractor, of some $15,000.00, but held that the creditors of the subcontractor, whose claims aggregated some $10,000.00, were not protected by the bond and he refused to report in their favor.

The report came on for confirmation and numerous exceptions. were filed, among them, exceptions of the creditors of the subcontractor. The court, by decree, sustained the exceptions of certain creditors of the subcontractor and added their claims to the amount which had been established by the commissioner, increasing said amount to $74,413.96. This amount being far in excess of the full penalty of the bond, the appellant was directed by said decree to deposit in bank, to the credit of the court, the full penalty of the bond, or $62,700.00.

The decree further provided that when the appellant made the deposit as directed, it would be discharged of any and all liability upon the bond involved in this suit. The decree makes no adjudication, as to the distribution of the [133]*133fund. It has been suggested that all of the creditors of the Crowell Contracting Company are not before the court.

The appellant has made numerous assignments of error to the decree and the Crowell Contracting Company has assigned cross-error. Assignments of error numbers six and seven were abandoned by counsel for the appellant at the bar of this court.

The commissioner allowed the Crowell Contracting Company the sum of $15,725.82. This allowance was confirmed by the court. The appellant takes the position that no amount whatever should have been allowed that company, while on the other hand, the Crowell Contracting Company contends in cross-error, that the correct amount to which it is entitled is $39,190.56. Neither the trial court nor the commissioner agreed with either the appellant or the Crowell Contracting Company, as we have already seen from the allowance of $15,725.82 made to that company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Viasys Holdings, L.L.C. v. Virginia Department of Transportation
84 Va. Cir. 559 (Norfolk County Circuit Court, 2012)
Stromberg Sheet Metal Works, Inc. v. United States Fidelity & Guaranty Co.
71 Va. Cir. 122 (Fairfax County Circuit Court, 2006)
Interstate Equipment Co. v. Smith
234 S.E.2d 599 (Supreme Court of North Carolina, 1977)
Vulcan Materials Co. v. Betts
315 F. Supp. 1049 (W.D. Virginia, 1970)
National Bank & Trust Company v. Castle
85 S.E.2d 228 (Supreme Court of Virginia, 1955)
New Amsterdam Casualty Co. v. Moretrench Corp.
35 S.E.2d 74 (Supreme Court of Virginia, 1945)
Fidelity & Casualty Co. v. Lackland
8 S.E.2d 306 (Supreme Court of Virginia, 1940)
United States Fidelity & Guaranty Co. v. Carter
170 S.E. 764 (Supreme Court of Virginia, 1933)
American Surety Co. v. Plank & Whitsett, Inc.
165 S.E. 660 (Supreme Court of Virginia, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.E. 528, 159 Va. 126, 1932 Va. LEXIS 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-casualty-co-v-copenhaver-contracting-co-va-1932.