Interstate Equipment Co. v. Smith

234 S.E.2d 599, 292 N.C. 592, 1977 N.C. LEXIS 1141
CourtSupreme Court of North Carolina
DecidedMay 10, 1977
Docket56
StatusPublished
Cited by17 cases

This text of 234 S.E.2d 599 (Interstate Equipment Co. v. Smith) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interstate Equipment Co. v. Smith, 234 S.E.2d 599, 292 N.C. 592, 1977 N.C. LEXIS 1141 (N.C. 1977).

Opinion

MOORE, Justice.

Great American, as surety, contends that it cannot be held liable for the amounts alleged to be due Interstate from the principal Bollinger for rental payments, repairs, tire adjustments and interest, for the reason that the amounts claimed to be due are not “labor and materials” under the condition of its bond with Bollinger.

It has long been established that a third party, for whose benefit a contract has been made, may maintain an action for breach of that contract. See, e.g., Products Corp. v. Sanders, 264 N.C. 234, 141 S.E. 2d 329 (1965); Gorrell v. Water Supply Co., 124 N.C. 328, 32 S.E. 720 (1899). This principle also applies to the intended beneficiaries of a contractor’s or subcontractor’s bond, and such a beneficiary may maintain an action against the surety on the bond. Glass Co. v. Fidelity Co., 193 N.C. 769, 138 S.E. 143 (1927). The bond executed between Bollinger and Great American was a payment bond for the protection of those supplying labor and materials to Bollinger. Interstate, occupying the position of one who has supplied labor and materials to Bollinger, is an intended beneficiary of the bond agreement and may maintain this action against the surety.

In Overman v. Indemnity Co., 199 N.C. 736, 155 S.E. 730 (1930), Mulligan Construction Company entered into a contract with the State Highway Commission to build a road. Mulligan executed a bond which was conditioned upon Mulligan’s paying all persons furnishing labor and materials “for which the *596 contractor is liable.” The surety argued that the clause “for which the contractor, is liable” limited its obligation on the bond to the labor and materials for which the contractor was directly responsible, thus excluding all claims by those persons who had supplied labor and materials to the subcontractors. In rejecting this argument, the Court held that the obligation of a bond must be read in conjunction with the contract which the bond was given to secure. Further, the extent of the surety’s obligations is ordinarily measured by the terms of the principal’s agreement. Thus, since the contract between Mulligan and the State Highway Commission provided that all persons furnishing labor and materials in the construction of the roadway would be paid, the surety was properly held liable for claims against the subcontractors. See also Dixon v. Horne, 180 N.C. 585, 105 S.E. 270 (1920) ; Fidelity and Casualty Co. v. Copenhaver Contracting Co., 165 S.E. 528 (Va. 1932). Accordingly, this Court should construe the surety’s liability in conjunction with the contract underlying the bond.

In determining the extent of a surety’s obligation, we are guided by the statement of Chief Justice Stacy in Wiseman v. Lacy, 193 N.C. 751, 753, 138 S.E. 121, 123 (1927) :

“The principle to be deduced from these and other like decisions is that such bonds are construed liberally for the protection of those who furnish labor and materials in the prosecution of public works (Electric Co. v. Deposit Co., 191 N.C. 653), and it is not thought that the surety can complain at such holding, or that any hardship is imposed thereby, because in entering into the contract the surety is chargeable with notice, not only of the financial ability and integrity of the contractor, but also with notice as to whether he possesses the plant, equipment, and tools required in undertaking the particular work, or will be compelled to rent and hire the same, or some part thereof, all of which matters are factors to be considered in determining the risk, and upon which the surety fixes the premiums exacted for executing the bond. Sherman v. Amer. Surety Co., 173 Pac. (Cal.), 161.” See also Owsley v. Henderson, 228 N.C. 224, 45 S.E. 2d 263 (1947).

In Wiseman v. Lacy, supra, plaintiffs leased to the contractor a steam shovel and a boiler which were used by the contractor in the construction of the road in question. On appeal, *597 the contractor’s surety resisted liability on the ground that a bond conditioned upon the payment of all claims for “labor and material” would not cover rental payments for equipment. In rejecting this contention, the Court held:

“The renting of the machines in question was but the substitution of mechanical power for manual labor. Taylor v. Connett, 277 Fed., 945; Bricker v. Rollins & Jarecki, 173 Pac. (Cal.), 592; Hansen v. Remer, 200 N.W. (Minn.), 839; Multnomah County v. U.S.F. and G. Co., 180 Pac. (Ore.), 104.” 193 N.C. at 752, 138 S.E. at 122.

In United Bonding Insurance Co. v. M. D. Moody and Sons, Inc., 213 So. 2d 263 (Fla. App. 1968), Moody leased road building equipment to a subcontractor which was bonded by United, as surety. Upon default of the subcontractor, Moody instituted action against the subcontractor and its surety. The surety contended that rental payments for equipment were not covered by a bond obligating the surety to pay for “labor and materials.” The court held that rental payments were covered by such a bond since “[t]he fair rental value of equipment so furnished is as much incorporated in the job as the sweat of a laborer’s brow or the concrete from a supplier’s mixer.” 213 So. 2d at 264. In reaching this conclusion, the court reasoned that a surety is chargeable with notice of the extent of its principal’s plant and equipment, and of the principal’s capability of performing the contract. See also United Bonding Ins. Co. v. Donaldson Engineering, Inc., 222 So. 2d 447 (Fla. App. 1969) ; C. S. Luck and Sons v. Boatwright, 162 S.E. 53 (Va. 1932).

We find the reasoning of the above cited cases to be persuasive. A compensated surety is not a ward of the court and it must be charged with notice of its principal’s plant, equipment and financial integrity. The surety is further charged with notice of the contract between its principal and the contractor. This is particularly true in the case at bar, wherein the bond states: “Whereas the Principal [Bollinger] and the Obligee [Teer] have entered into a written contract . . . dated the 17th day of April 1974. ...”

*598 In the case at bar, the contract between Bollinger and Teer, in part, provided:

“You [Bollinger] will finance your operations in every detail and promptly, or upon demand, pay all indebtedness arising out of your operations hereunder. . . .
* * *
“You are to furnish us satisfactory Payment bond being in the full amount of this subcontract.
“ ... You shall have available the necessary workmen and equipment so as to be ready to begin work immediately following our direction to do so. . . .
* * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Seeding Service, Inc. v. W.C. English, Inc.
719 S.E.2d 211 (Court of Appeals of North Carolina, 2011)
County of Brunswick v. Lexon Insurance Company
425 F. App'x 190 (Fourth Circuit, 2011)
Sunbelt Rentals, Inc. v. Douglas Corbridge
171 F. Supp. 2d 14 (D. Maine, 2001)
Coston v. Coston
426 S.E.2d 460 (Court of Appeals of North Carolina, 1993)
Southeastern Steel Erectors, Inc. v. Inco, Inc.
424 S.E.2d 433 (Court of Appeals of North Carolina, 1993)
Symons Corp. v. Insurance Co. of North America
380 S.E.2d 550 (Court of Appeals of North Carolina, 1989)
Mason C. Day Excavating, Inc. v. Crowder Construction Co.
676 F. Supp. 670 (W.D. North Carolina, 1987)
Parker v. Lippard
359 S.E.2d 492 (Court of Appeals of North Carolina, 1987)
W. H. Dail Plumbing, Inc. v. Roger Baker & Associates, Inc.
338 S.E.2d 135 (Court of Appeals of North Carolina, 1986)
Wilkes Computer Services, Inc. v. Aetna Casualty & Surety Co.
295 S.E.2d 776 (Court of Appeals of North Carolina, 1982)
Noland Co., Inc. v. Poovey
295 S.E.2d 238 (Court of Appeals of North Carolina, 1982)
Lalanne v. Lalanne
279 S.E.2d 25 (Court of Appeals of North Carolina, 1981)
Smith v. King
277 S.E.2d 875 (Court of Appeals of North Carolina, 1981)
Stillwell Enterprises, Inc. v. Interstate Equipment Co.
254 S.E.2d 770 (Court of Appeals of North Carolina, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
234 S.E.2d 599, 292 N.C. 592, 1977 N.C. LEXIS 1141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interstate-equipment-co-v-smith-nc-1977.