Mason C. Day Excavating, Inc. v. Crowder Construction Co.

676 F. Supp. 670, 1987 U.S. Dist. LEXIS 12282, 1987 WL 30651
CourtDistrict Court, W.D. North Carolina
DecidedDecember 9, 1987
DocketC-C-87-084-P
StatusPublished

This text of 676 F. Supp. 670 (Mason C. Day Excavating, Inc. v. Crowder Construction Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mason C. Day Excavating, Inc. v. Crowder Construction Co., 676 F. Supp. 670, 1987 U.S. Dist. LEXIS 12282, 1987 WL 30651 (W.D.N.C. 1987).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

ROBERT D. POTTER, Chief Judge.

THIS MATTER is before the Court following a bench trial held on November 23, 1987. The main parties are a contractor, Crowder Construction Co., Inc., and a subcontractor, Mason C. Day Excavating, Inc. The subcontractor sued the contractor for monies due and owing under a subcontract for grading and excavation work. The contractor counterclaimed for a declaratory judgment establishing the rights and liabilities of the parties, and for a set-off of certain expenses.

*672 I. FINDINGS OF FACT

Based upon the evidence presented at trial and the record in this case, the Court makes the following findings of fact:

(1) Plaintiff is Mason C. Day Excavating, Inc. (“Mason Day”), a Virginia corporation with its principal place of business in Virginia. Plaintiff is a grading contractor. Defendant Crowder Construction Co., Inc. (“Crowder”) is a North Carolina company with its principal place of business in North Carolina. Defendant Crowder is a construction company. The Aetna Casualty & Surety Co. (“Aetna”) is a Connecticut corporation. Defendant Aetna is an insurance company which issues, among other types of policies, performance and payment bonds for construction companies.

(2) Defendant Crowder was awarded the prime contract for the state highway project known as the “East-West Durham Freeway” in Durham County, N.C. Crowder subcontracted the clearing and grading portion of the contract to Plaintiff Mason Day. The subcontract incorporated the contract between Crowder and the state in its entirety. Defendant Aetna provided Crowder with a payment bond to secure payment by Crowder to its subcontractors. Plaintiff Mason Day sued Aetna on the theory that Mason Day is a third-party beneficiary of the Aetna-Crowder payment bond.

(3) The subcontract between Mason Day and Crowder required that Mason Day provide Crowder with a performance bond to secure performance of the subcontracted work. Mason Day began work on the project in September, 1986, without obtaining a performance bond. Although Mason Day assured Crowder that a performance bond was imminent, Mason Day was never able to obtain a bond. Accordingly, Crowder terminated the subcontract, pursuant to its terms, on Oct. 17, 1986. Termination is governed by Article 8 of the subcontract, which reads:

Should the Subcontractor at any time ... fail in the performance of any of the agreements herein contained, ... the Contractor may, at his option, terminate the employment of the Subcontractor for the said work, and shall have the right to enter upon the premises and take possession, for the purpose of completing the work included under this Subcontract, of all the materials, tools and appliances thereon, and may employ any other person or persons to finish the work and provide the materials therefor; and in case of such discontinuance of the employment by the said Contractor, said Subcontractor shall not be entitled to receive any further payments under this Subcontract until the work shall be wholly finished, at which time, if such expenses shall exceed the unpaid balance, the Subcontractor shall pay the difference to the Contractor, but if the unpaid balance of the amount to be paid under this Subcontract exceeds the expenses incurred by the Contractor in finishing the work, such excess shall be used first to pay the Subcontractor for his materials and equipment so used and any amount thereafter remaining shall be apportioned between the Contractor and the Subcontractor in ratio to the percentage of work completed by each party. The expense incurred by the Contractor, as herein provided, either for furnishing materials or for finishing the work, and any damages incurred by such [subcontractor’s] default shall be changeable to, and paid by, said Subcontractor____

(4)Prior to termination, Mason Day performed certain work on the project. The parties filed a stipulation delineating the work performed by Mason Day and the value thereof, as follows:

Clearing and grubbing............ $ 54,450.00
Unclassified excavation........... 46,355.40
Borrow excavation................ 326,927.00
Drainage ditch excavation......... 4,625.50
Cleaning out silt basins........... 97.00
54-inch perforated CS pipe elbow 737.42
54-inch CS pipe culvert........... 932.68
Erosion control stone class B..... 972.61
TOTAL:...................... $435,097.61

Crowder does not contend that the work performed by Mason Day was substandard.

(5)The DOT has paid Crowder $412,-894.63 for work done by Mason Day. Crowder already has advanced $147,053.53 *673 to Mason Day, leaving a net sum of $288,-044.08 claimed by Mason Day to be due and owing for work previously performed. Crowder opened an escrow account into which it deposited all sums received by it for Mason Day’s work. Crowder has withdrawn sums from the account to pay expenses it contends are reasonably related to its termination of Mason Day and completion of the subcontract work.

(6) After terminating the Mason Day contract, Crowder sought a replacement grading and excavating contractor. Time was of the essence in this search, so that Crowder could meet the state deadlines for completing portions of the work. Crowder reviewed the bid from the construction company which had submitted the next lowest bid on the entire subcontract during the initial bidding for the project contract. (The lowest bid was the Mason Day bid.) Crowder also solicited quotes on the “takeover price” — the price to finish the grading and excavation — from two companies with which it was familiar. After determining that the quote from S.T. Wooten Construction Co. (“Wooten”) was the lowest of the three, Crowder contracted with Wooten for the completion of the grading and excavating work.

(7) Crowder claims that it was required to pay Wooten $181,995.59 more than it would have cost Crowder had Mason Day been able to perform the subcontract. Crowder claims that it is entitled to set off this sum against any payment due to Mason Day. Crowder also claims set-offs for the following expenses attendant upon Mason Day’s termination:

Duke Power...................... $ 84.20
Damage to equipment............ 400.00
Robert Akers..................... 25.00
Crowder labor and equipment..... 5,727.44
Chandler Concrete................ 162.86
McCaskill Welding................ 25.00
Check printing charges ........... 39.90
West Durham Lumber............ 153.20
Crowder labor.................... 504.30
Crowder legal fees ............... 14,866.48
Potential liability to Harry Curry.. 40,099.20

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Interstate Equipment Co. v. Smith
234 S.E.2d 599 (Supreme Court of North Carolina, 1977)
Stillwell Enterprises, Inc. v. Interstate Equipment Co.
266 S.E.2d 812 (Supreme Court of North Carolina, 1980)
Yeargin Construction Co. v. Futren Development Corp.
225 S.E.2d 623 (Court of Appeals of North Carolina, 1976)
Durham Lumber Co. v. Wrenn-Wilson Construction Co.
107 S.E.2d 538 (Supreme Court of North Carolina, 1959)
Overman & Co. v. Great American Indemnity Co.
155 S.E. 730 (Supreme Court of North Carolina, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
676 F. Supp. 670, 1987 U.S. Dist. LEXIS 12282, 1987 WL 30651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mason-c-day-excavating-inc-v-crowder-construction-co-ncwd-1987.