Durham Lumber Co. v. Wrenn-Wilson Construction Co.

107 S.E.2d 538, 249 N.C. 680, 1959 N.C. LEXIS 414
CourtSupreme Court of North Carolina
DecidedMarch 18, 1959
Docket667
StatusPublished
Cited by18 cases

This text of 107 S.E.2d 538 (Durham Lumber Co. v. Wrenn-Wilson Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Durham Lumber Co. v. Wrenn-Wilson Construction Co., 107 S.E.2d 538, 249 N.C. 680, 1959 N.C. LEXIS 414 (N.C. 1959).

Opinion

Bobbitt, J.

Where a building contract is substantially, but not exactly, performed, the amount recoverable by the contractor depends upon the nature of the defects or omissions. “Where the defects or omissions are of such a character as to be capable of being remedied, the proper rule for measuring the amount recoverable by the contractor is the contract price less the reasonable cost of remedying the defects or omissions so as to make the building conform to the contract.” Annotations: 134 Am. St. Rep. 678, 684; 23 A.L.R. 1435, I486; 38 A.L.R. 1383; 65 A.L.R. 1297, 1298.

In an action to recover the unpaid portion of the contract price, the defendant, under his denial of plaintiff’s alleged performance, may show, in diminution of plaintiff’s recovery, the reasonable cost of 'Supplying omissions, if any, and of remedying defects, if any; and, if such costs exceed the unpaid portion of the contract price, the defendant may, by counterclaim, recover the amount of such excess. Howie v. Rea, 70 N.C. 559; Moss v. Knitting Mills, 190 N.C. 644, 130 S.E. 635; Mason v. Andrews, 192 N.C. 135, 133 S.E. 402.

While under certain circumstances quantum meruit miay be the measure of recovery, Poe v. Town of Brevard, 174 N.C. 710, 94 S.E. 420, “when it is said that in cases of this character the plaintiff may recover on a quantum meruit or valebat, nothing more is intended than that he may recover whatever -he may be entitled to, not exceeding the price fixed by the special contract.” Annotation: 134 Am. St. Rep. 678, 685.

The general rule stated above is applicable here. Everything required to be done under the contract has been fully performed. If plaintiff breached its contract in respect of omissions or defects, defendant has supplied the omissions and has remedied the defects. The controversy turns on whether it had the right to do so for the *685 account of plaintiff. If so, defendant is entitled to “back charge” (defendant’s expression) all reasonable amounts expended for such pur--pose. .

The agreed case on appeal states: “The contract price between.the plaintiff and the defendant, including certain extras, amounted to $19,103.08. The defendant paid to said plaintiff or received credit for all of-said sum of money with the exception of $3,123.45.” (Note: The record discloses that plaintiff !bas • given defendant full credit for plaintiff’s failure to comply with the. contract in respect of certain items not involved in this controversy.)

Nothing else appearing, plaintiff was entitled to recover $3,123.45; but, under its (controverted) allegations, defendant was required to pay $3,774.48 to supply omissions and to remedy defects caused by plaintiff’s failure to perform its contract obligations.

Defendant’s assignments of error are based on exceptions to. the issues and to the court’s instructions ais to 'burden of proof and- other features.

G.S. 1-200 requires that the court submit such issues as are necessary to settle the material controversies arising on the pleadings, including new matter alleged in the. answer, so that the answers, thereto will support a final judgment. Coulbourn v. Armstrong, 243 N.C. 663, 91 S.E. 2d 912, and cases cited. “Ordinarily the form and number of the issues in the trial of a civil action are left to the sound discretion of the judge and a party cannot complain because a particular issue was not submitted to the jury in the form tendered by him.” Griffin v. Insurance Co., 225 N.C. 684, 36 S.E. 2d 225; O’Briant v. O’Briant, 239 N.C. 101, 79 S.E. 2d 252, and cases cited.

Whether, considering the pleadings 'and the agreed facts, the first issue was necessary, need not be decided. Suffice to say, the submission of the first issue and the court’s instructions thereon do-not disclose prejudicial error; for the court made it quite plain that the issues were interrelated and that the respective rights of the parties in relation to the six controverted items would foe determined, as was done, by the jury’s answers to the subsequent issues.

An answer ,to the single issue tendered by defendant would have determined what amount, if any, defendant was entitled to recover from plaintiff on its 'alleged counterclaim for $651.45. The burden of proving its counterclaim was on defendant. Wells v. Clayton, 236 N.C. 102, 72 S.E. 2d 16. If this single issue had been submitted, defendant, to be entitled to an answer in its favor, would have, been required to show that plaintiff had breached its contract in respect of one or more of said six specific items.and that the reasonable'cost of- *686 supplying the omissions and of remedying the defects exceeded $3,123.45. The mere fact that the court, in its discretion, submitted ■a separate issue as to each of the six specific items in controversy would seem insufficient -to affect the burden of proof; for these six issues, considered together, presented for determination the identical questions that would have been presented if the issue tendered by defendant had been submitted.

Here we need not determine the rule .applicable if defendant had alleged the .six controverted items solely as a def ense, that is, in diminution of the amount plaintiff was entitled to recover. The issues submitted (except the first) arise on the allegations of defendant’s “FURTHER ANSWER, DEFENSE AND COUNTERCLAIM” and plaintiff's reply thereto. The six controverted items are not alleged solely as a defense but are alleged as the basis for a recovery by defendant from plaintiff. Certainly the burden of proof is not divisible so that it would rest on plaintiff up to $3,123.45 and on defendant for any amount in excess of $3,123.45. Under the .pleadings and admitted facts, when defendant elected to allege and to prosecute .its counterclaim on the basis of the six controverted items, it thereby assumed the burden of proof with reference thereto for all purposes. Compare Ice Co. v. Construction Co., 194 N.C. 407, 139 S.E. 771.

In considering the court’s instructions relating to issues 2-7, inclusive, these facts are noted:

1. As to issues 2, 3, 4, 5 and 7, the court placed the burden of proof on defendant. As to issue 6, the court’s instructions as to burden of proof will be discussed below.

2. The items involved in issues 2, 3, 4, 5 and 7 relate to alleged omissions. The -item involved in issue 6 relates to alleged defective performance.

■3. The third issue was answered in defendant’s favor for the full amount ($243.87) alleged. The judgment gives defendant full credit therefor.

Unquestionably, as defendant contends, when the terms of a written contract are explicit, the legal obligations of the respective parties are determinable as questions of law. Howland v. Stitzer, 240 N.C. 689, 696, 84 S.E. 2d 167, and cases cited. The general rule, well established, is thus summarized in Wallace v. Bellamy, 199 N.C. 759, 763, 155 S.E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Ellis
633 S.E.2d 883 (Court of Appeals of North Carolina, 2006)
Davis v. Dennis Lilly Co.
411 S.E.2d 133 (Supreme Court of North Carolina, 1991)
Mason C. Day Excavating, Inc. v. Crowder Construction Co.
676 F. Supp. 670 (W.D. North Carolina, 1987)
Bob Tate Construction, Inc. v. Schultz
325 S.E.2d 45 (Court of Appeals of North Carolina, 1985)
FARMERS BANK, ETC. v. Michael T. Brown Distributors
298 S.E.2d 357 (Supreme Court of North Carolina, 1983)
Olive v. Williams
257 S.E.2d 90 (Court of Appeals of North Carolina, 1979)
Black v. Clark
243 S.E.2d 808 (Court of Appeals of North Carolina, 1978)
Hartley v. Ballou
209 S.E.2d 776 (Supreme Court of North Carolina, 1974)
Cape Fear Electric Co. v. Star News Newspapers, Inc.
207 S.E.2d 323 (Court of Appeals of North Carolina, 1974)
Link v. Link
179 S.E.2d 697 (Supreme Court of North Carolina, 1971)
Salem Towne Apartments, Inc. v. McDaniel & Sons Roofing Co.
330 F. Supp. 906 (E.D. North Carolina, 1970)
Johnson v. Lamb
161 S.E.2d 131 (Supreme Court of North Carolina, 1968)
Hunt v. Hunt
135 S.E.2d 195 (Supreme Court of North Carolina, 1964)
General Tire and Rubber Co. v. Distributors, Inc.
117 S.E.2d 479 (Supreme Court of North Carolina, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
107 S.E.2d 538, 249 N.C. 680, 1959 N.C. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durham-lumber-co-v-wrenn-wilson-construction-co-nc-1959.