T. C. Allen Construction Company v. Stratford Corporation, Stratford Corporation v. Allen Construction Company

384 F.2d 653, 1967 U.S. App. LEXIS 4878
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 12, 1967
Docket10964, 10965
StatusPublished
Cited by5 cases

This text of 384 F.2d 653 (T. C. Allen Construction Company v. Stratford Corporation, Stratford Corporation v. Allen Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. C. Allen Construction Company v. Stratford Corporation, Stratford Corporation v. Allen Construction Company, 384 F.2d 653, 1967 U.S. App. LEXIS 4878 (4th Cir. 1967).

Opinion

SIMONS, District Judge:

Plaintiff-appellant, T. C. Allen Construction Company, (hereinafter referred to as plaintiff) brought suit against defendant-appellee, Stratford Corporation, (hereafter defendant) to recover a retained balance due it under a contract for the construction of a Downtowner Motor Inn in Winston-Salem, North Carolina, together with interest thereon from July 25, 1964, the date of its alleged completion of its contract.

For a proper understanding of the issues the following brief summary of the proceedings in the court below is stated.

In its complaint plaintiff alleged that it had substantially completed all work required of it under the terms of a written contract between the parties executed during June 1963, as it was subsequently modified by mutual agreement, and was entitled to the balance of $58,042.61 due thereunder. During the trial plaintiff voluntarily reduced its demand by $1500, upon its admission that there existed certain minor defects in its concrete work which would require that amount to correct. Accordingly, it amended its complaint to demand the amount of $56,542.-61. 2

Defendant answered, asserting that it was not indebted to plaintiff in any amount because of the latter’s improper *655 and unworkmanlike manner of constructing the motel, that it had suffered damages as a result thereof far in excess of the balance due plaintiff, and counterclaimed for $75,000.00 damages allegedly resulting from plaintiff’s failure to complete the construction work in a good and workmanlike manner in accordance with the contract plans and specifications.

Defendant went into possession of the motel in July or August 1964 and has operated it continuously since then.

At trial the evidence was in sharp conflict as to the manner in which plaintiff had performed the construction. Plaintiff’s evidence supported its contentions that it had properly and substantially complied with its contract, and that $1500.00 was adequate to repair satisfactorily the minor defects or cracks in the cement work, which in no way affected the structural safety of the building. By the testimony of several expert witnesses defendant showed that plaintiff’s workmanship was so shoddy and defective that it would require the expenditure of approximately $58,000.00 or more to make the construction conform to the contract standards.

Defendant’s expert testimony established that the concrete construction work was primarily deficient in four general areas : 3 (a) That the topping in the basement was cracked and had failed to bond properly; the corrective measure recommended was to remove the topping and pour three to four inches of reinforced concrete; the estimated cost was $4-5,-000.00; (b) That the walkways were wavy, the aggregate showed in spots, and reinforcing rods were exposed; there was spalling on the outside walkways; as a corrective measure it was recommended that all of the topping be removed and replaced by an epoxy topping which would produce a finish reasonably comparable to a smooth concrete surface as required by the contract; the estimated cost was $18,000.00; (c) That the terrazzo in the lobby was cracked; and it could reasonably be corrected by the installation of a resilient floor covering at estimated cost of $1,100.00; (d) That the topping on the driveway and the main parking area was in an advanced state of cracking and coming up; to correct properly the topping should be removed and replaced by a neotex type of apoxy at a total cost of $80,000.00, which would not produce as satisfactory result as good finished concrete required by the contract, but was considered to be the only practical solution at that stage.

The foregoing testimony on behalf of defendant was admitted by the trial judge over plaintiff’s strenuous objection upon ground that the performing of such corrective measures would put the premises in different, more expensive, and better condition than the contract requirement. Plaintiff objected upon further ground that during the course of discovery, in answer to plaintiff’s interrogatories about the claimed defects and the mode and cost of correcting them, defendant professed to have no such information, and refused to reveal its position in reference thereto when in fact it had such information.

After a full and adequate charge, the trial judge submitted the following three issues to-the jury for its determination:

“(1) Has the plaintiff either fully or substantially performed its contract with the defendant?
(2) If so, what amount, if any, is the plaintiff entitled to recover of the defendant?
*656 (3) What amount, if any, is the defendant entitled to recover of the plaintiff?”

During his main charge and in an additional charge the trial judge emphasized that if the jury should find substantial performance of the contract, it should award plaintiff the balance due on the contract of $56,542.61, less the fair and reasonable cost of correcting and repairing any defects required “to make the premises comply with the contract”, which would put defendant “in the condition bargained for”.

Plaintiff’s counsel made several general objections to the court’s main charge without stating any definite or particularized reason or ground therefor. No exception was taken to the court’s additional charge when the jury returned to the courtroom during its deliberations with a request for additional instructions, which reiterated the same measure of damages outlined in the main charge.

Plaintiff admitted that at time of trial there was still due and owing by it to its subcontractors a total of $33,084.66. Upon oral argument before this court plaintiff’s counsel advised that about $26,000.00 still remained unpaid. The contract provided that final payment to plaintiff would not be made until defendant’s architect certified that all work required thereunder had been completed and accepted by him as satisfactory; further, that before the issuance of the architect’s final certificate it was incumbent upon the contractor to submit satisfactory evidence that all payrolls, material bills, and other indebtedness in connection with the work had been paid.

The jury by its verdict answered issue number one in the affirmative, thus finding that plaintiff had substantially performed its contract. In answer to issue number two it awarded plaintiff the sum of $28,000.00. Thereupon, plaintiff moved to set aside the jury verdict upon ground of inadequacy which was denied. No issue as to interest was submitted to the jury, and the court entered judgment on the jury verdict in favor of plaintiff for $28,000.00, together with interest from the date execution was issued thereon. The judgment further provided that no execution would issue until ordered by the court upon notice and a showing that the claims of subcontractors against the funds represented by the judgment had been satisfied. Plaintiff duly excepted to the judgment, alleging error in its failure to provide for interest on the jury award from August 1, 1964 (the approximate date plaintiff completed its contract and defendant went into possession of the motel).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salus Corp. v. Olshan
831 F.2d 291 (Fourth Circuit, 1987)
Thomas M. McInnis & Associates, Inc. v. Hall
349 S.E.2d 552 (Supreme Court of North Carolina, 1986)
Stuart v. Consolidated Foods Corp.
496 P.2d 527 (Court of Appeals of Washington, 1972)
Salem Towne Apartments, Inc. v. McDaniel & Sons Roofing Co.
330 F. Supp. 906 (E.D. North Carolina, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
384 F.2d 653, 1967 U.S. App. LEXIS 4878, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-c-allen-construction-company-v-stratford-corporation-stratford-ca4-1967.