Salus Corp. v. Olshan

831 F.2d 291, 1987 U.S. App. LEXIS 13542, 1987 WL 38652
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 9, 1987
Docket86-2060
StatusUnpublished

This text of 831 F.2d 291 (Salus Corp. v. Olshan) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salus Corp. v. Olshan, 831 F.2d 291, 1987 U.S. App. LEXIS 13542, 1987 WL 38652 (4th Cir. 1987).

Opinion

831 F.2d 291
Unpublished Disposition

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
SALUS CORPORATION, Plaintiff--Appellant
v.
Morton L. OLSHAN, Richard P. Steinberg, Vincent Guerriero,
Frank L. Flautt, W. Jefferies Mann, Wilton D.
Hill, Flautt & Mann Properties, Inc.,
Defendant--Appellees

No. 86-2060.

United States Court of Appeals, Fourth Circuit.

Argued: Jan. 7, 1987.
Decided: Oct. 9, 1987.

Before SPROUSE and ERVIN, Circuit Judges, and FRANK A. KAUFMAN, Senior United States District Judge for the District of Maryland, sitting by designation.

Edgar T. Bellinger (Elena W. King, Zucker, Scoutt, Rasenberger & Johnson, Alan B. Croft, Hazel, Beckhorn & Hanes on brief) for appellant.

Robert F. Condon (Mark London, Finley, Kumble, Wagner, Heine, Underberg, Manley & Casey on brief) for appellees.

PER CURIAM:

On May 11, 1983, Salus Corporation (Salus), the contractor, entered into a contract with Olshan, Guerriero, Steinberg, Flautt and Mann (Owners)1 for the construction of a Holiday Inn in Fairfax County, Virginia, using The American Institute of Architects Standard Form of Agreement Between Owner and Contractor (AIA Document A111) (the Agreement) and the General Conditions of the Contract for Construction (AIA Document A201) (the General Conditions). The parties agree that construction was to begin upon notice from the Owners to Salus to proceed, and that completion of the contract work was to be achieved within 455 days of such notice to Salus. After the Owners gave Salus notice to proceed as of May 25, 1983, Salus commenced work. The district court found that the original completion date, as extended because of change order 19, was August 4, 1984. However, in the fall of 1983, it became evident that the subcontractors hired by Salus were falling behind schedule in connection with structural concrete work. By June 1984, when it was clear that numerous delays in construction would preclude completion by August 4, 1984, the parties agreed to a new completion date, namely, October 15, 1984. Subsequently, by letter dated September 17, 1984, Salus informed the Owners that completion by October 15, 1984 could not be achieved. In that context, the parties discussed a partial opening date for the hotel around Thanksgiving. In fact, a partial opening occurred on December 10, 1984. By letter dated December 18, 1984, the Owners directed Salus to complete the contract forthwith and expressed serious concern about the delays. After Salus' president was unable to provide the Owners with a firm completion date, the Owners, by letter dated December 31, 1984, terminated the contract with Salus effective January 6, 1985. Work on the project by Salus stopped on January 2, 1985. The Owners thereupon undertook to complete the project, and finally achieved completion on February 15, 1985. Thereafter, Salus instituted the within case for breach of contract against the Owners. The latter denied the said allegations of Salus and, in addition, filed a counterclaim against Salus, alleging that it was Salus which had wrongfully breached the contract. Diversity of citizenship jurisdiction is present.

After a nonjury trial, the district court concluded that: (1) Salus breached the construction contract by failing, without justifiable excuse, timely to complete the project; (2) the Owners were accordingly justified in terminating the contract; (3) Salus was not entitled to recover on its complaint; and (4) the Owners were entitled to recover on their counterclaim. We affirm each of those determinations by the district court.

The district court, after making the above set forth determinations, awarded $930,397.05 in compensatory damages to the Owners. Later, the district court reduced that award to $875,031.23. For the reasons discussed infra, we hereby remand the within case to the district court for a redetermination of damages.

LIABILITY

The trial court made full and specific findings of facts concerning the events in this case, and found that while certain of the delays were the fault of the Owners, all of the critical delays were the responsibility of Salus. The trial court also concluded that the extensions granted by the Owners to Salus did not constitute a waiver of the right of the Owners to terminate the contract if Salus, despite the extensions granted to it, failed thereafter timely to complete the job. In point of fact, in this case, after more than one extension, Salus had still not completed its work. Also, there is more than sufficient evidence to support the finding of the district court that the Owners gave both reasonable opportunity to Salus to complete, and reasonable notice to Salus that the Owners would exercise the right to terminate if, despite the extensions, Salus continued its failure timely to perform all of its contractual obligations. That is all that the Owners were required to do under the contract documents and applicable Virginia case law.2

DAMAGES

Article 53 of the Agreement between the Owner and Contractor (A1A Document A111), (hereinafter called "Agreement"),4 provides as follows:

5.1 The Owner agrees to reimburse the Contractor for the Cost of the Work as defined in Article 8. Such reimbursement shall be in addition to the Contractor's Fee stipulated in Article 6.

5.2 The maximum cost to the Owner, including the Cost of the Work and the Contractor's Fee, is guaranteed not to exceed the sum of Seven Million Four Hundred Seventy-One Thousand Nine Hundred Dollars ($7,471,900.00); such Guaranteed Maximum Cost shall be increased or decreased for Changes in the Work as provided in Article 7.

At the completion of the work, coincident with the Contractor's Final Application for Payment, and upon receipt of an audit acceptable to the Owner, if the audited Final Total Cost of the Work and Contractor's Fee is less than the Guaranteed Maximum Cost, the savings (difference) shall be distributed as follows:

The Contractor shall receive as a bonus 25% of the savings; the remainder will be retained by the Owner.

Notwithstanding the foregoing, the Owner shall be entitled to one hundred percent (100%) of the savings resulting from any design or specification changes reducing the scope of the work, and the Contractor shall not receive any additional bonus attributable to such savings.5

Article 6.1 of the Agreement provides:

In consideration of the performance of the Contract, the Owner agrees to pay the Contractor in current funds as compensation for his services a Contractor's Fee as follows:

Fixed Fee of $374,000.00.

Article 15 of the Agreement states:

15.1 The Contract may be terminated by the Contractor as provided in the Contract Documents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roanoke Hospital Ass'n v. Doyle & Russell, Inc.
214 S.E.2d 155 (Supreme Court of Virginia, 1975)
Schulze v. KWIK-CHEK REALTY COMPANY
181 S.E.2d 629 (Supreme Court of Virginia, 1971)
Appalachian Power Co. v. John Stewart Walker, Inc.
201 S.E.2d 758 (Supreme Court of Virginia, 1974)
Pebble Building Co. v. G. J. Hopkins, Inc.
288 S.E.2d 437 (Supreme Court of Virginia, 1982)
Huselton v. Roop
207 S.E.2d 826 (Supreme Court of Virginia, 1974)
Kerner v. Gilt
296 So. 2d 428 (Louisiana Court of Appeal, 1974)
Formigli Corporation v. Fox
348 F. Supp. 629 (E.D. Pennsylvania, 1972)
Robinhorne Construction Corp. v. Snyder
265 N.E.2d 670 (Illinois Supreme Court, 1970)
Harmeyer v. Postal Life Insurance
3 Ohio App. 104 (Ohio Court of Appeals, 1914)
Cincinnati Traction Co. v. Burkhardt
4 Ohio App. 103 (Ohio Court of Appeals, 1915)
Gross v. Clauss
6 Ohio App. 140 (Ohio Court of Appeals, 1915)
McCord v. McCord
7 Ohio App. 129 (Ohio Court of Appeals, 1916)
Young v. Thedieck
8 Ohio App. 103 (Ohio Court of Appeals, 1918)
Smith v. State
10 Ohio App. 29 (Ohio Court of Appeals, 1918)
McClain v. Custer
11 Ohio App. 183 (Ohio Court of Appeals, 1918)
Caferelli v. State
12 Ohio App. 91 (Ohio Court of Appeals, 1919)
Hartman v. Braucher
16 Ohio App. 33 (Ohio Court of Appeals, 1921)
Tiedman v. American Pigment Corp.
253 F.2d 803 (Fourth Circuit, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
831 F.2d 291, 1987 U.S. App. LEXIS 13542, 1987 WL 38652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salus-corp-v-olshan-ca4-1987.