Dallas-Fort Worth Regional Airport Board v. Combustion Equipment Associates, Inc.

623 F.2d 1032, 1980 U.S. App. LEXIS 14883
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 13, 1980
Docket78-2781
StatusPublished

This text of 623 F.2d 1032 (Dallas-Fort Worth Regional Airport Board v. Combustion Equipment Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dallas-Fort Worth Regional Airport Board v. Combustion Equipment Associates, Inc., 623 F.2d 1032, 1980 U.S. App. LEXIS 14883 (5th Cir. 1980).

Opinion

623 F.2d 1032

6 Fed. R. Evid. Serv. 1127

DALLAS-FORT WORTH REGIONAL AIRPORT BOARD, a Joint Agency of
the City of Dallas, Texas, and the City of Fort
Worth, Texas, Plaintiff-Appellee Cross-Appellant,
v.
COMBUSTION EQUIPMENT ASSOCIATES, INC. and Fidelity and
Deposit Company of Maryland, Defendants-Appellants
Cross-Appellees.

No. 78-2781.

United States Court of Appeals,
Fifth Circuit.

Aug. 13, 1980.

Harold Hoffman, Donald C. McCleary, Dallas, Tex., for Combustion equipment co.

James K. Peden, III, Frank L. Skillern, Jr., Dallas, Tex., for Fidelity and Deposit Co. of Maryland.

Charles C. Wells, C. Merrill Bierfeld, Asst. City Attys., Dallas, Tex., for plaintiff-appellee cross-appellant.

Appeals from the United States District Court for the Northern District of Texas.

Before FAY, KRAVITCH and RANDALL, Circuit Judges.

FAY, Circuit Judge:

This diversity action arose from a construction contract dispute between the Dallas-Fort Worth Regional Airport Board (Board) and Combustion Equipment Associates, Inc. (CEA). CEA had contracted to build an incinerator to burn the airport's solid wastes, but failed to fulfill its contractual obligations by the date initially specified in the written contract. The Board sued CEA for reimbursement of the payments made to CEA during the course of construction and for liquidated damages. CEA and its surety, Fidelity and Deposit Company of Maryland, now appeal from an adverse judgment of $816,987.41, granted to the Board after a month-long jury trial. On appeal, CEA claims that the Board, after waiving the written contract's specified completion date, breached the contract by evicting CEA from the jobsite without giving written notice and a reasonable time thereafter to complete construction. CEA also challenges several evidentiary rulings and jury instructions. Additionally, CEA claims that the evidence was insufficient to support either the verdict or the jury's responses to several interrogatories submitted to them by the court. Finally, CEA contends that the trial judge erred in selecting and computing prejudgment and postjudgment interest rates. On cross-appeal, the Board challenges the trial court's decision to overrule the jury's grant of liquidated damages to the Board. Because of conflicting jury responses to interrogatories, we reverse the trial court's denial of liquidated damages and remand for redetermination of whether CEA owes the Board contractual damages for the delay, and, if so, how much. Finding no reversible error in any of the other claims, we affirm the judgment in all other respects.

FACTS AND PROCEEDINGS

Following competitive bidding, CEA executed a construction contract with the Board1 on August 1, 1972. The contract required CEA to construct for the Board a solid waste disposal system in accordance with the job's plans and specifications. Incorporated by reference was CEA's bid proposal, which specified the composition of wastes to be incinerated by CEA's system. Thereafter, Fidelity and Deposit Company of Maryland issued a performance bond. On September 26, 1972, the parties executed a supplemental agreement, which modified the contract's requirements and reduced the contract price from $1,111,111 to $800,000. By June 25, 1973, the parties had reached a second supplemental agreement, which further modified the contractual requirements and extended the completion deadline to September 30, 1973. The second agreement also granted CEA an extra thirty days to make adjustments to comply with environmental protection regulations.

After construction began in late spring, 1973, the Board began making periodic payments which would eventually total $736,250. On January 18, 1974, long after the contract completion date, the Board notified CEA that no further payments would be forthcoming until CEA fulfilled its contractual obligations.

In response, CEA continuously reassured the Board that the incineration system would soon be operational. By May 1, 1974, however, CEA had begun to inform the Board that engineering problems spawned by installing an "innovative" system might delay completion. CEA nonetheless continued to promise full and prompt performance.

On May 11, 1974, however, a jobsite fire destroyed CEA's construction efforts. Notwithstanding CEA's renewed commitment after the fire to attain a functional system within eight weeks, CEA did not resume onsite construction efforts. Consequently, on June 28, 1974, the Board notified CEA and its surety of its intent to terminate the contract and turn construction responsibility over to the surety. At CEA's request, the parties conferred at the airport on July 26, 1974. At that conference they agreed that within fourteen weeks CEA would repair the fire damage and have the incineration system working.

By the fall of 1974, CEA had repaired the fire damage but had consistently refused to submit the incineration system to the Board's testing. By a letter dated December 12, 1974, the Board advised CEA that it would commence contract termination procedures immediately unless CEA's system passed the Board's testing, which was to be administered without fail on December 23, 1974. CEA agreed to the test. A full day of testing on the scheduled date revealed that the promised system still was not functional.

On February 5, 1975, the Board gave CEA and its surety notice of contract termination. On March 5, 1975, the Board evicted CEA from the jobsite.

The Board thereafter brought a diversity action against CEA and its surety. Pursuant to a jury verdict for the Board, the trial court granted the Board $636,000. Subtracting $100,000, the jury's estimate of the value of scrap left on the jobsite, from $736,000, the approximate sum of the periodic payments to CEA, gave that amount of recommended compensatory damages. Conflicting jury answers to interrogatories, however, led the trial court to overrule the jury's grant of $225,000 to the Board for liquidated damages. The court, granting both prejudgment and postjudgment interest on the Board's damages, rendered a final judgment against CEA totalling $816,987.41.

CONTRACT TERMINATION

On appeal, CEA challenges the trial court's denial of a directed verdict or judgment n.o.v. for CEA. CEA contends that the Board's waiver of the written contract's specified deadline and the subsequent failure to set a new completion date completely foreclosed lawful unilateral termination of the contract. Accordingly, CEA claims that the Board's decision to evict CEA from the jobsite on March 5, 1975,2 constituted a contract breach which prevented performance by CEA. Under CEA's rationale, the Board was responsible for CEA's failure to complete construction and should not collect damages from CEA, notwithstanding the eighteen-month delay from contractual deadline to final eviction.

In support of its contentions, CEA cites numerous cases which require one who has waived the initial completion date to give written notice of a new deadline and a reasonable time to complete before unilateral termination of the contract. In A. L. Carter Lumber Co. v. Saide, 140 Tex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. C. Allen v. A. G. Edwards & Sons, Inc.
606 F.2d 84 (Fifth Circuit, 1979)
United States Ex Rel. Johnson v. Morley Const. Co.
98 F.2d 781 (Second Circuit, 1938)
Ridglea Interests, Inc. v. General Lumber Company
343 S.W.2d 490 (Court of Appeals of Texas, 1961)
Pecos County State Bank v. El Paso Livestock Auction Co., Inc.
586 S.W.2d 183 (Court of Appeals of Texas, 1979)
Meyers v. Moody
475 F. Supp. 232 (N.D. Texas, 1979)
Zummo Cattle Company v. Millard
482 S.W.2d 17 (Court of Appeals of Texas, 1972)
Earl Hayes Rents Cars & Trucks v. City of Houston
557 S.W.2d 316 (Court of Appeals of Texas, 1977)
Hull v. Freedman