United States Ex Rel. Johnson v. Morley Const. Co.

98 F.2d 781, 1938 U.S. App. LEXIS 4691
CourtCourt of Appeals for the Second Circuit
DecidedJuly 29, 1938
Docket182
StatusPublished
Cited by73 cases

This text of 98 F.2d 781 (United States Ex Rel. Johnson v. Morley Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Johnson v. Morley Const. Co., 98 F.2d 781, 1938 U.S. App. LEXIS 4691 (2d Cir. 1938).

Opinion

L. HAND, Circuit Judge.

The original defendants, the Maryland Casualty Company and the Morley Construction Company, appeal from a judgment against them, entered upon the verdict of a jury of one, in an action upon a construction contract between the Morley Company and the Veterans Administration of 'the United States, for the erection of a hospital at Batavia, N. Y. The Maryland Casualty Company was the surety upon this contract; the plaintiff, Johnson, was a sub-contractor of the Morley Company, doing the roofing and other parts of the building: Rupp, Harrington’s testator, was the sub-contractor for the grading: the Concrete Engineering Company furnished temporary forms for setting the concrete: J. S. Thorn Company furnished the window frames for the buildings: and Marcus Bonsignore and twenty-seven others were laborers engaged upon the work. Johnson originally brought the action against the Morley Company and the surety, and the other parties mentioned intervened; still other parties also intervened, but the surety thereafter paid their claims, as well as the plaintiff’s, and took an assignment of them: it now presses them against the Morley Company. These assigned claims are admittedly good in substance; but the Morley Company disputes their collection by the surety and in this action. The litigation divides itself into two parts: (1) The main action against the Morley Company upon the assigned claims; (2) the several claims of the four intervenors whom we have mentioned (counting Bonsignore and the other laborers as one).

(1) Liability of the Morley Company to the Surety, as Assignee of the Intervenors’ Claims.

As we have said, the Morley Company does not dispute that the surety’s assignors had sub-contracts with it which they performed in accordance with their terms: it does dispute its liability in this action and to the surety. It says that the action was premature, and that, if not, the surety has lost its rights, either as assignee, or in subrogation. The facts are as follows. The writ was served on Morley Company-on May 28, 1934: it appeared on June 23d; and filed an answer: on August 31, 1935, it attempted “to appear specially” in order to object to the jurisdiction of the court, and to strike out the pleading of the surety. There can be no doubt as to the jurisdiction of the district court. The final settlement of the Veterans Administration with the Morley Company was on November 13, 1933, and § 270 of Title 40, U.S. Code, 40 U.S.C.A. § 270, allowed the action to be brought at any time between six months and a year “after performance and final settlement”. But the Morley Company says that, regardless of this, the action was premature under the terms of' Johnson’s sub-contract. That provided that the Morley Company should pay Johnson monthly as it received its own payments from the Administration at the rate of 85% of the work completed each month,. *785 and that “the final payment shall be made upon completion and acceptance of the work * * * and upon receipt by the contractor of the final payment from the Veterans Administration”. The Veterans Administration issued its final warrant to the Morley Company in November, upon which the .United States Treasury issued its cheque thereafter. The surety brought a suit in equity against the Morley Company in the Western District of Missouri to enjoin the payment of this cheque and succeeded; and the Morley Company argues that for this reason there has never been “final payment” by the Veterans Administration; and that, if the action was premature as to Johnson, it was premature as to all the intervenors. United States v. McCord, 233 U.S. 157, 158, 34 S.Ct. 550, 58 L.Ed. 893. The question turns upon the meaning of the phrase, “final payment”, in Johnson’s contract. This could scarcely have referred to anything but the warrant, issued by the Administration, for that body could go no farther; could make no actual “payment”. But the point is bad for another reason. The Treasury did deliver the cheque to the Morley Company and the stipulation was of course designed to protect the Morley Company until then — that is, until it had control of the money — but there was no reason to postpone the sub-contractors thereafter. The Missouri suit was in substance an attachment, and obviously sub-contractors were not to wait while the Morley Company arranged its affairs with its other creditors; if these tied up its funds, it was no affair of the sub-contractors. The argument takes another and obscurer form on the theory that the surety made payment impossible by attaching the cheque. This is spoken of as the prevention of a “condition precedent”; but that is meaningless. The doctrine invoked excuses performance of a condition precedent to an obligee’s right of action: here the surety is the obligee and the Morley Company the obligor; it is the surety which must show performance of the condition precedent, and it did so when it proved that the intervenors had performed their sub-contracts. Moreover, the Missouri suit ended in the surety’s favor (Morley Construction Co. v. Maryland Casualty Co., 8 Cir., 90 F.2d 976) ; and it is absurd to assert that the prosecution of a valid claim could affect the surety’s power to prosecute the assigned claims. If the Morley Company had not enough money to meet all its debts, that was its misfortune.

The only other point which needs discussion is that the surety filed no supplemental pleadings after taking the assignments. At common law the transfer of a cause of action, pendente lite, was cause for abatement, if the defendant raised it by the plea, puis darrein continuance, but the action could be revived by the transferee by scire facias. Nome & Sinook Co. v. Ames Mercantile Co., 9 Cir., 187 F. 928. This action is at common law (Illinois Surety Co. v. United States, to Use of Peeler, 240 U.S. 214, 223-225, 36 S.Ct. 321, 60 L.Ed. 609), and under the Conformity Act, 28 U.S.C.A. § 724, it is governed by the New York practice. In New York in case of a transfer of interest, pendente lite, the action is to be continued unless the court directs the transferee to be substituted. § 83 of the New York Civil Practice Act. Therefore no supplemental pleading was necessary.

(2) Rupp’s Claim.

Rupp’s administrator presses this claim against the surety under Rupp’s sub-contract. (It will be more convenient to disregard the administrator and speak as though Rupp were the claimant.) He had a sub-contract to do all the grading and excavating, and substantially all of the concrete work on the job: his claim is in three parts. First, he claims the balance of the contract price which he had never received. Against this the surety asserts set-offs and that Rupp wrongfully abandoned the job and disqualified himself from recovery. Second, he claims for extra work in regrading a part of the surface, made necessary, as he says, by a mistake in the plans. Third, he claims as extra work certain rock excavation for which the Morley Company had been paid, although he did the work. We shall begin with the two claims for extra work.

(2a) Cost of Regrading.

The contract required Rupp to grade an oval in front of the main hospital building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyndon Property Insurance v. Eastern Kentucky University
200 F. App'x 409 (Sixth Circuit, 2006)
US EX REL. TENN. VALLEY MARBLE v. Grunley Const.
433 F. Supp. 2d 104 (District of Columbia, 2006)
New Mexico Department of Labor v. A.C. Electric, Inc.
1998 NMCA 141 (New Mexico Court of Appeals, 1998)
Sloan v. Kubitsky
712 A.2d 966 (Connecticut Appellate Court, 1998)
Kelley Marine Transport Corp. v. Boston Sand & Gravel
2 Mass. L. Rptr. 545 (Massachusetts Superior Court, 1994)
Rhode Island Hospital Trust v. Martin Trust, No. 700674 (Feb. 18, 1992)
1992 Conn. Super. Ct. 1844 (Connecticut Superior Court, 1992)
Schenley Affiliated Brands Corp. v. Mar-Salle, Inc.
703 F. Supp. 744 (N.D. Illinois, 1989)
In Re Merritt Commercial Savings & Loan, Inc.
766 F.2d 850 (Fourth Circuit, 1985)
Merritt Commercial Savings & Loan, Inc. v. Guinee
766 F.2d 850 (Fourth Circuit, 1985)
United States v. Avanti Constructors, Inc.
750 F.2d 759 (Ninth Circuit, 1984)
In Re Braniff Airways, Inc.
42 B.R. 443 (N.D. Texas, 1984)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Continental Group, Inc. v. Justice
536 F. Supp. 658 (D. Delaware, 1982)
Barabas v. Prudential Lines, Inc.
577 F.2d 184 (Second Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
98 F.2d 781, 1938 U.S. App. LEXIS 4691, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-johnson-v-morley-const-co-ca2-1938.