Turner v. Ellis

633 S.E.2d 883, 179 N.C. App. 357, 2006 N.C. App. LEXIS 1905
CourtCourt of Appeals of North Carolina
DecidedSeptember 5, 2006
DocketCOA05-1527
StatusPublished
Cited by3 cases

This text of 633 S.E.2d 883 (Turner v. Ellis) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turner v. Ellis, 633 S.E.2d 883, 179 N.C. App. 357, 2006 N.C. App. LEXIS 1905 (N.C. Ct. App. 2006).

Opinion

TYSON, Judge.

Douglas E. Ellis (“defendant”) appeals from judgment entered after a jury returned a verdict in favor of Kevin Turner (“Turner”) and Lara Turner (collectively, “plaintiffs”) and from orders granting plaintiffs’ motion for directed verdict on defendant’s counterclaim, denying defendant’s motion for directed verdict and judgment notwithstanding the verdict, and disbursing funds and setting costs. We affirm.

I. Background

In 1980, Turner bought a 1.8 acre tract in the Upper Crabtree Community of Haywood County. In 1986, Turner purchased an adjoining parcel. The two parcels combined equaled ten acres. A portion of the property was graded to allow a residence to be built. Turner had served as a church pastor in the Piedmont area and had been given several tobacco bams, which he dismantled and transported to Haywood County. Turner reassembled the pieces into a tobacco barn with the intent to eventually renovate the structure and use it as his home. From 1981 until 1999, the barn was used for storage and occasionally as a campsite.

In 1999, Turner parked a camper on the property and applied for a building permit to prepare the site to construct a permanent residence. A septic system was installed, a well was dug, and temporary electricity was installed.

In 2000, Turner married Lara Gravely. Plaintiffs finalized plans for their residence and began to search for construction financing. Mountain Bank, now known as Carolina First, agreed to provide a construction loan, if plaintiffs hired a general contractor.

In late 2001, Turner attempted to contact defendant, an extended family member and a licensed general contractor. No communication occurred between Turner and defendant until October 2002. Plaintiffs provided house drawings to defendant and later met with defendant at his home to discuss the project. Defendant agreed to serve as general contractor, but stated he did not build log homes. Defendant told *359 plaintiffs they would have to hire a subcontractor to complete that portion of the job. Defendant recommended Mitchell Langford (“Langford”), an individual he had recently worked with to construct a log home. Defendant showed plaintiffs a house he and Langford had recently built together. Defendant and plaintiffs discussed aspects of the construction, such as materials to be used to construct the residence.

Defendant quoted plaintiffs $185,000.00 as the cost required to build their home. This quote included a $9,000.00 contracting fee. Plaintiffs contracted with Langford to separately complete the log work. Langford recommended plaintiffs obtain blueprints of the house. On 1 November 2002, a copy of the blueprints were given to defendant and Langford with some modifications from plaintiffs’ original handwritten plans. No changes were quoted to the original cost to build the home.

Before signing the loan agreement, an itemized construction cost breakdown and a construction timetable of nine to twelve months was presented to plaintiffs by defendant. Mountain Bank issued the loan commitment after plaintiffs and defendant signed a Construction Loan Agreement on 19 November 2002. The parties agreed the cost to build the house was $185,000.00 and would not exceed $225,000.00. Plaintiffs obtained a construction loan for the maximum amount of $225,000.00. Plaintiffs planned to use excess loan funds to reimburse costs expended on the original structure and for sufficient funds for cost overruns and closing fees.

In December 2002, an excavator began to prepare the site and foundation blocks were laid the following May. By September 2003, most of the logs were installed. After October, plaintiffs became frustrated because defendant could not locate a contractor to install the metal roof. Water began to seep into the structure. During late December 2003 and early January 2004, financial difficulties arose and work ceased.

Mountain Bank inspected the property to ensure funds were being expended appropriately as construction progressed. Mountain Bank discovered construction was not progressing at a rate that matched the expenditure of the funds. Mountain Bank informed plaintiffs that no additional loan funds would be advanced due to the level of construction completed. Turner discussed the situation with defendant, who informed him of cost overruns. Turner told defendant that he “couldn’t figure that [they] could finish the house with the *360 amount of money that [he] was borrowing from the bank.” Defendant told Turner that he would complete the construction on the house for $105,600.00, if $20,912.97 currently owed was paid. Plaintiffs agreed.

Plaintiffs did not have available funds to finish the project. Plaintiffs returned to Mountain Bank and requested a second construction loan. Plaintiffs and defendant met with officials of Mountain Bank. A document was prepared by defendant itemizing the cost to complete the project. The document contained a clause that stated, “Costs to complete home not to exceed $105,600[.00].” The document was signed by both plaintiffs and defendant. Plaintiffs rolled their first loan into a larger loan totaling $300,000.00. Work resumed on the house after the document was signed.

Plaintiffs demanded a strict accounting of funds being spent. Originally, all invoices approved by defendant would go to Turner and he would write a check to defendant. The check was drawn on an account opened with funds solely to be used for construction.

Plaintiffs changed the method of how payments on invoices would be made. All further invoices were to be submitted directly to Mountain Bank. After submission, an invoice amount would be placed under a certain line item on a document signed by plaintiffs and defendant. Plaintiffs told Mountain Bank that anytime one line item exceeded the amount designated, defendant would have to pull from a different line item so the total cost to complete construction would not exceed $105,600.00. After an invoice was submitted, Mountain Bank would issue payment to defendant.

Styrofoam insulating blocks were installed in preparation for the metal roof and work continued inside the residence. In April 2004, a rainstorm caused significant water damage to the inside of the house. Turner told defendant it was his responsibility to repair the damage. Defendant responded that he was not the general contractor and that he had only agreed to help them. This was the first time defendant stated he was not the general contractor for the construction. Defendant issued Turner an invoice for $14,348.00 over the revised maximum cost. Plaintiffs wrote defendant a letter which discussed the water damage to the house and plaintiffs’ expectations for defendant to prevent additional water damage in the future. The letter referred to their agreement that the cost to complete the house would not exceed $105,600.00.

Plaintiffs and defendant met to discuss the letter. Defendant gave Wayne Miller’s (“Miller”) telephone number to plaintiffs and told them *361 Miller could install the roof, but defendant “wasn’t going to have anything to do with it.” Defendant stated he would meet with plaintiffs to discuss how to finish the house at the agreed cost. Defendant did not appear at the meeting. Plaintiffs were later served with a $27,000.00 lien on their house filed by defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Telerent Leasing Corp. v. Boaziz
686 S.E.2d 520 (Court of Appeals of North Carolina, 2009)
North Carolina Industrial Capital, LLC v. Clayton
649 S.E.2d 14 (Court of Appeals of North Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
633 S.E.2d 883, 179 N.C. App. 357, 2006 N.C. App. LEXIS 1905, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-v-ellis-ncctapp-2006.