Southern Seeding Service, Inc. v. W.C. English, Inc.

719 S.E.2d 211, 217 N.C. App. 300, 2011 N.C. App. LEXIS 2432
CourtCourt of Appeals of North Carolina
DecidedDecember 6, 2011
DocketCOA11-381
StatusPublished
Cited by7 cases

This text of 719 S.E.2d 211 (Southern Seeding Service, Inc. v. W.C. English, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Seeding Service, Inc. v. W.C. English, Inc., 719 S.E.2d 211, 217 N.C. App. 300, 2011 N.C. App. LEXIS 2432 (N.C. Ct. App. 2011).

Opinion

HUNTER, JR., Robert N., Judge.

Southern Seeding Service, Inc. (“Plaintiff’) appeals the trial court’s dismissal of its breach of contract claim against W.C. English, Inc. (“English”) and its claim for damages against Liberty Mutual Insurance Company (“Liberty Mutual”) and Travelers Casualty & Surety Company of America (“Travelers Casualty”) (collectively, “the Sureties”). Plaintiff also appeals the trial court’s order denying its *301 motion to amend judgment and motion for a new trial. Plaintiff contends the trial court erred by (1) misconstruing “no damages for delay” and “equitable adjustment” clauses in the subcontract entered into between Plaintiff and English; and (2) concluding that Liberty Mutual and Travelers Casualty were not liable to Plaintiff as sureties on a statutorily required payment bond. After careful review, we reverse and remand.

I. Factual & Procedural Background

Plaintiff is a North Carolina corporation in the business of performing seeding, fertilizing, and mulching services. Plaintiff has conducted grassing work for various North Carolina Department of Transportation (“NCDOT”) projects since 1958. On 15 July 2003, NCDOT opened bidding for a project located in Greensboro (“the Project”). NCDOT’s project proposal described the Project as involving “widening, drainage, paving, [and] lighting” work in the Greensboro “Western Loop” area extending “from 1-40 to North of Bryan Boulevard.” NCDOT’s proposal specified 1 July 2007 as the completion date for the Project.

NCDOT awarded the principal contract on the Project to APACAtlantic, Inc., Thompson — Arthur Division (“APAC”). As required by N.C. Gen. Stat. § 44A-26, APAC executed a Contract Payment Bond (the “payment bond”) with NCDOT in the amount of $101,558,741.04, guaranteeing payment to all subcontractors and material suppliers on the Project. Liberty Mutual and Travelers Casualty signed as sureties on the payment bond.

APAC subcontracted the grading and grassing work for the Project to English. English, in turn, subcontracted a portion of the grassing work to Plaintiff. The subcontract, entered into between Plaintiff and English on 23 October 2003, included a $2,080 “unit price” for Plaintiff’s seeding and mulching services, and listed other specific grassing tasks with accompanying unit prices. Term 1 of the subcontract, titled “Work,” provides that Plaintiff must complete the work identified and described in Schedule A. Schedule A, Note 15 (hereinafter referred to as the “equitable adjustment clause” or “Note 15”) provides the following:

Unit prices herein quoted are based upon the assumption that the contract will be completed within time as specified in the specifications at time of bidding. Should our work be delayed beyond said time without fault on our part, unit prices herein quoted shall be equitably adjusted to compensate us for increased cost....

*302 A separate provision in the subcontract, Paragraph 7 (hereinafter referred to as the “no damages for delay clause” or “Paragraph 7”) provides:

Should [Plaintiff], without fault or neglect on its own part, be delayed in the commencement, prosecution, or completion of the Work by the fault or neglect of [English], [Plaintiff] shall be entitled to a reasonable extension of time, only. ... In no event shall [Plaintiff] be entitled to compensation or damages for any delay in the commencement, prosecution, or completion of the Work except to the extent that [English] shall receive such compensation or damages from Owner or other third party.

Plaintiff commenced work on the Project on or about 26 September 2003. Throughout the Project, APAC expressed concern regarding English’s inability to perform its grassing work in a timely manner. In a letter dated 13 July 2006, Plaintiff’s president, Ralph Stout, Jr., complained to English that Plaintiff had been “put to extreme extra expense in [its] work due to the manner in which” English had managed the erosion control work. Mr. Stout further stated “[w]e did not bid this job to perform our work under emergency circumstances.” When Plaintiff’s work on the Project continued past the Project’s scheduled completion date of 1 July 2007, Plaintiff informed English it was “keeping detailed records on all items, quantities, costs, etc. since July 1 [2007] in order to furnish the necessary information to make fair and equitable adjustments in [its] unit prices.”

Due to what the NCDOT described as “thirteen supplemental agreements,” the Project was not completed until 14 March 2008, 256 days beyond the Project’s scheduled completion date. Plaintiff did not complete its work on the Project until 21 March 2008. In a letter dated 17 July 2008, Plaintiff notified APAC of its right to an equitable adjustment pursuant to Note 15 of the subcontract for increased costs incurred after 1 July 2007. On 18 November 2008, Plaintiff invoiced English for these costs in the amount of $194,941.39. Additionally, in a letter dated 8 December 2008, Plaintiff notified the Sureties that it would be seeking this payment pursuant to the payment bond if English failed to fully compensate Plaintiff for its work. English proposed to pay Plaintiff $2,300.00, which would cover Plaintiff’s unit price increases incurred after 1 July 2007 but would not account for unit price increases incurred between the time Plaintiff commenced its work on the Project and 1 July 2007. Plaintiff rejected English’s proposal.

*303 On 23 September 2009, Plaintiff filed a complaint in Guilford County Superior Court alleging two claims for relief. Plaintiffs first claim alleges that English breached its subcontract with Plaintiff by failing to pay Plaintiff $194,941.39 under the equitable adjustment clause for the increases in its unit cost of labor and materials furnished for the Project after 1 July 2007. Plaintiffs second claim for relief alleges that Liberty Mutual and Travelers Casualty are liable to Plaintiff for payment under the payment bond because of English’s failure to fully compensate Plaintiff for its work on the Project.

On 2 September 2010, following a bench trial, Judge Joseph entered judgment denying Plaintiff’s requested relief. The trial court, “[g]iving effect to Paragraph 7 in conjunction with Note 15” and “construing the Subcontract as a whole,” concluded “an equitable adjustment in unit prices would be permitted to the extent English receives compensation of increased unit prices for delays in the work from any outside source, including NC DOT or APAC.” (Emphasis in original). However, “English was not obligated to equitably adjust [Plaintiff’s] unit prices for increased cost, if any, arising from working past 1 July 2007” because “English had no contractual remedy against APAC to receive adjustment in unit prices for delay beyond the original completion date.” The trial court dismissed Plaintiff’s claim against the Sureties as moot. Judge Joseph subsequently denied Plaintiff’s motion for a new trial and motion to amend judgment in an order entered 11 October 2010. Plaintiff filed its notice of appeal as to the trial court’s judgment and order on 3 November 2010.

II. Jurisdiction

Jurisdiction lies in this Court pursuant to N.C. Gen. Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Munn v. Rose
Court of Appeals of North Carolina, 2026
Aspen Specialty Ins. Co. v. Nucor Corp.
2025 NCBC 67 (North Carolina Business Court, 2025)
Law Offices of Peter H. Priest, Pllc v. Coch
2014 NCBC 54 (North Carolina Business Court, 2014)
Paradigm Fin. Grp., Inc. v. Church
2014 NCBC 16 (North Carolina Business Court, 2014)
Southern Seeding Service, Inc. v. W.C. English, Inc.
735 S.E.2d 829 (Court of Appeals of North Carolina, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
719 S.E.2d 211, 217 N.C. App. 300, 2011 N.C. App. LEXIS 2432, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-seeding-service-inc-v-wc-english-inc-ncctapp-2011.