S. J. Groves & Sons & Co. v. State

273 S.E.2d 465, 50 N.C. App. 1, 1980 N.C. App. LEXIS 3450
CourtCourt of Appeals of North Carolina
DecidedDecember 16, 1980
Docket8010SC60
StatusPublished
Cited by17 cases

This text of 273 S.E.2d 465 (S. J. Groves & Sons & Co. v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. J. Groves & Sons & Co. v. State, 273 S.E.2d 465, 50 N.C. App. 1, 1980 N.C. App. LEXIS 3450 (N.C. Ct. App. 1980).

Opinion

MORRIS, Chief Judge.

Plaintiff appellee has moved for the dismissal of this appeal on the ground that appellant has violated the requirement of Appellate Rule 10(c) that the “grouping of exceptions under given assignments of error” be confined to a single issue of law so far as practicable. The appellant has listed 167 assignments of error based upon 168 exceptions to the findings of fact and conclusions of law in the trial court’s order. Although the exceptions and assignments of error have been placed after each issue presented in its brief, appellant, for the most part, has neglected to identify or address them expressly in its argument under each issue. Thus it is virtually impossible to determine whether any exceptions have been abandoned for lack of argument. While we think plaintiff’s position is well taken, we have chosen to discuss the questions raised by this appeal on their merits.

From a substantial record, the court made lengthy and detailed *53 findings of fact. This Court must now determine whether those findings are supported by the evidence and whether they support the trial court’s conclusions of law and order. Graham and Son, Inc., v. Board of Education, 25 N.C. App. 163, 212 S.E. 2d 542, cert. den. 287 N.C. 465, 215 S.E. 2d 623 (1975).

Defendant has excepted to the trial court’s findings that on 15 August 1973 the plaintiff afforded the defendant ample written notice of its claim of a “changed condition” at the work site. Defendant appears to contend that the notice was deficient in that it did not sufficiently detail the nature of the changed condition and the alteration in work procedures which would be necessitated.

In Blankenship Construction Company v. Highway Commission, 28 N.C. App. 593, 222 S.E. 2d 452, disc, review denied 290 N.C. 550,230 S.E. 2d 765 (1976), this Court construed the notice requirement as contained in § 4.3A of the Standard Specifications for Roads and Structures (hereinafter “SSRS”), stating as follows:

In order to qualify for additional compensation under Sections 4.3A or 4.4(c), the Contractor is required to furnish the Engineer written notice of the alleged changed conditions....
While the form of the notice - written or oral - may not be critical, the content of the notice must satisfy the underlying purpose of the notice requirement ____In our opinion the purpose of the notice requirement of Section 4.3A is to apprise the Commission of the Contractor’s belief that he has encountered “work conditions at the site differing materially from those indicated in the contract” for which he is entitled to an “equitable adjustment.”

Id. at 607, 222 S.E. 2d at 461.

We find that the written notice given by plaintiff clearly apprised the defendant of the claim of a changed condition at the work site in compliance with § 4.3A of the SSRS. Plaintiff’s letter of 15 August 1973 explicitly advised the defendant of its claim and demand as follows:

Our contract with you has a changed condition clause. With the schedule demanded and the superior knowledge of *54 the Highway Commission and its design engineers, the contract was based on the fact that the soils could be compacted. We believe that the excessive moisture in the soils of this project created by excessive rain and other reasons, the drainage characteristics and soil conditions constitute a changed condition requiring that the Highway Commission grant us equitable adjustment and extension of time.
Pursuant to the specifications and in order to further protect our position in this matter we hereby notify the commission in writing that we are now having and have had since the beginning of this project, a changed condition of which employees of the commission have had knowledge.

In its letter plaintiff further requested a meeting to see if the parties could reach an agreement concerning an equitable adjustment and time extension for a changed condition.

By letter dated 18 September 1973 defendant advised plaintiff that it did not concur with the claim of a changed condition as presented in the 15 August 1973 letter (and as also presented in a joint meeting held 17 September 1973) and denied plaintiff’s request for an adjustment in unit prices or for a time extension. This letter is, of course, a written acknowledgment by the defendant that the plaintiff had informed it of the belief that there had been encountered work conditions at the site differing from those indicated in the contract for which the contractor was entitled to an equitable adjustment.

We find nothing in § 4.3A, or in its interpretation by the Blankenship Court, which would support the defendant’s contention that the contractor in this initial notice was required to spell out in detail the exact nature and extent of the unclassified excavation work it was claiming under a changed condition. At this point in its claim, plaintiff was not required to itemize the fine points and particulars which subsequently would be necessary in the proof of its claim. All that was necessary at this juncture was a “forceful indication of changed conditions and demand for equitable compensation.” Blankenship Construction Company v. Highway Commission, supra. The plaintiff’s letter of 15 August 1973 fully supports the trial court’s *55 finding that ample written notice was provided in accordance with the contract.

Defendant next argues that the trial court erred in granting plaintiff recovery on the basis of “changed conditions” when different theories and claims were presented to the State Highway Administrator. Defendant is correct in its contention that this Court in Inland Bridge Company, Inc. v. Highway Commission, 30 N.C. App. 535, 227 S.E. 2d 648 (1976), held that under N.C.G.S. 136-29, a party may not develop theories of recovery in Superior Court in addition to those set forth in the claim filed with the State Highway Administrator. However, the defendant’s reliance upon the opinion in Inland Bridge is misplaced. The Court’s decision in that case was based upon the following:

Plaintiffs’ whole claim before the Commission was for misrepresentation. Had they desired to sue under the provisions in the SSRS incorporated into the contract, which provides for claims based on changed conditions, extra work, or reclassification of materials, it was necessary for them to elect to do so prior to the trial in the Superior Court. Construction Co. v. Highway Comm., 28 N.C. App. 593, 222 S.E. 2d 452 (1976).

Id. at 547, 227 S.E. 2d at 655.

Unlike the contractor in Inland Bridge, in the case at hand the plaintiff contractor did submit in its verified claim letter dated 6 October 1975 a claim for increased compensation due to the encountering of changed conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Seeding Service, Inc. v. W.C. English, Inc.
719 S.E.2d 211 (Court of Appeals of North Carolina, 2011)
Pritchett & Burch, PLLC v. Boyd
609 S.E.2d 439 (Court of Appeals of North Carolina, 2005)
State v. Hill
449 S.E.2d 573 (Court of Appeals of North Carolina, 1994)
Golden Rule Insurance v. Long
439 S.E.2d 599 (Court of Appeals of North Carolina, 1993)
State v. Almond
435 S.E.2d 91 (Court of Appeals of North Carolina, 1993)
State v. Turner
406 S.E.2d 147 (Court of Appeals of North Carolina, 1991)
State v. Smart
394 S.E.2d 475 (Court of Appeals of North Carolina, 1990)
Ruby-Collins, Inc. v. City of Charlotte
740 F. Supp. 1159 (W.D. North Carolina, 1990)
Thompson-Arthur Paving Co. v. North Carolina Department of Transportation
387 S.E.2d 72 (Court of Appeals of North Carolina, 1990)
Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Byrne v. Bordeaux
354 S.E.2d 277 (Court of Appeals of North Carolina, 1987)
State v. Morrison
351 S.E.2d 810 (Court of Appeals of North Carolina, 1987)
Davis v. Taylor
344 S.E.2d 19 (Court of Appeals of North Carolina, 1986)
Davidson & Jones, Inc. v. North Carolina Department of Administration
337 S.E.2d 463 (Supreme Court of North Carolina, 1985)
Craven v. Chambers
287 S.E.2d 905 (Court of Appeals of North Carolina, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
273 S.E.2d 465, 50 N.C. App. 1, 1980 N.C. App. LEXIS 3450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-j-groves-sons-co-v-state-ncctapp-1980.