Davidson & Jones, Inc. v. North Carolina Department of Administration

337 S.E.2d 463, 315 N.C. 144, 1985 N.C. LEXIS 2000
CourtSupreme Court of North Carolina
DecidedDecember 10, 1985
Docket511PA84
StatusPublished
Cited by15 cases

This text of 337 S.E.2d 463 (Davidson & Jones, Inc. v. North Carolina Department of Administration) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davidson & Jones, Inc. v. North Carolina Department of Administration, 337 S.E.2d 463, 315 N.C. 144, 1985 N.C. LEXIS 2000 (N.C. 1985).

Opinion

FRYE, Justice.

Petitioner has presented two essential questions for our review. The first is whether the Court of Appeals correctly held that a contractor in a civil action, pursuant to G.S. 143-135.3, may not recover duration-related costs incurred as the direct result of an unexpected overrun exceeding 400% in the amount of rock to be excavated under a construction contract with the State of North Carolina. For the reasons stated hereinafter, we conclude that the Court of Appeals erred in so holding. As to the second, *146 we agree with the trial court and the Court of Appeals that plaintiff may not recover extra home office expenses. Other questions decided by the Court of Appeals in reversing the trial court’s award of financing costs and interest costs to the plaintiff were not briefed or argued before this Court, and we express no opinion thereon.

Plaintiff contracted with defendants North Carolina Department of Administration and the University of North Carolina to build an addition to Wilson Library on the University’s Chapel Hill campus. As the project progressed, plaintiff encountered a massive overrun in the amount of rock to be excavated and requested compensation for certain extra costs. Defendants rejected part of this request. After the project was completed, plaintiff brought suit for relief pursuant to G.S. 143-135.3 on grounds of mutual mistake and implied warranty. The trial court found in favor of the plaintiff and awarded it (1) payment at the contract’s unit price for all rock excavated, (2) duration-related costs, (3) financing costs, and (4) interest on the entire award, but denied plaintiffs request for reimbursement for extra home office costs. Defendants appealed to the Court of Appeals, which affirmed the first part of the award and reversed the remainder. Plaintiff contends before this Court that the Court of Appeals erred in its interpretation of both G.S. 143-135.3 and the contract between the parties.

The bidding documents for the Wilson Library Project, which were made part of the contract, included a “rock clause” instructing the bidder to include 800 cubic yards of rock excavation in its base bid. The documents also requested a unit price, per cubic yard, for computing adjustments to the contract for rock above or below this quantity. Plaintiff included in its proposal a unit price of $55 per cubic yard and proposed a completion time of 540 days for the entire project. In computing the amount of time to complete the project, plaintiff had allowed eight weeks for rock removal based on the 800 cubic yard quantity given in tire- bidding documents.

The anticipated amount of rock turned out to be grossly erroneous. Plaintiff had submitted a schedule to the project architect which called for completing all excavation by 10 October 1975. By that date, plaintiffs subcontractor had already removed *147 over 800 cubic yards of rock, and an unknown quantity still remained. Plaintiff began petitioning for additional compensation and time to complete the project. Not until April of the following year (1976) was all of the rock that needed to be removed excavated. The quantity totaled 3714 cubic yards.

Defendants did not respond to plaintiffs requests for additional payment until February 1976, when plaintiff threatened to stop working if no agreement was reached. On 2 March 1976, representatives of the plaintiff and the defendants met to discuss plaintiffs claims. Plaintiff was by that time seeking not only payment for extra rock excavation at the unit price but also for the duration-related costs it expected to incur after the originally scheduled completion date. At this meeting, defendants’ representatives agreed to pay plaintiff for some of the requested items but instructed plaintiff to pursue the statutory disputes resolution process for payment on the other items when the project was finished.

As a result of this meeting, plaintiff continued to work on the project, completing it within the time extensions granted. It then followed the procedures outlined in G.S. 143-135.3, in applying for additional compensation. After the required hearing before the North Carolina Department of Administration, plaintiff filed a civil action in Superior Court, Wake County, on 11 September 1978. After making detailed and extensive findings, the trial court concluded that plaintiff was entitled to payment at the unit price for all rock excavated; $110,710 for duration-related expenses; $2,369 for interest obligations incurred due to the State’s tardy payments; and interest on the total award at the rate of five percent per year from 31 March 1976. The trial court denied plaintiff s claim for payment for home office expenses attributable to the extension of the project.

On appeal, the Court of Appeals reversed the trial court’s decision as to the duration-related expenses, the financing expenses, and the interest on the total award. It affirmed the denial of reimbursement for home office expenses. Plaintiffs petition for a writ of certiorari to review the Court of Appeals’ decision was allowed by this Court on 8 January 1985.

The trial court held in its conclusions of law that plaintiff was entitled to relief “pursuant to the Contract, Articles 15 and *148 16, and because of mutual mistakes . ...” We note that it is unclear whether the court was basing its decision on two separate grounds (provisions of the contract and the equitable ground of mutual mistake) and saying that an award could be based on either, or whether the court meant that plaintiff was entitled to relief as provided by Articles 15 and 16 because of mutual mistake of fact.

Without drawing any distinctions between these two interpretations, the Court of Appeals concluded that plaintiff was not entitled to recover anything beyond the unit price for rock excavation for which the State had not yet paid. The court quoted part of G.S. 143-135.3, which outlines the procedures to be followed “should the contractor fail to receive such settlement as he claims to be entitled to under terms of his contract,” N.C. Gen. Stat. § 143-135.3 (Cum. Supp. 1983). 1 Citing Middlesex Construction Corp. v. State ex rel. Art Museum Bldg. Comm., 307 N.C. 569, 299 S.E. 2d 640 (1983), reh’g denied, 310 N.C. 150, 312 S.E. 2d 648 (1984), the court said:

[W]e hold that the State’s waiver of sovereign immunity in a breach of contract action is valid only to the extent expressly *149 stated in the statute, and that the plaintiffs remedy here must be found exclusively within the express terms of the statute. The statute is clear in limitation of recovery except as otherwise provided ‘under the terms of his contract.’

Davidson and Jones v. N.C. Dept. of Administration, 69 N.C. App. at 570, 317 S.E. 2d at 723.

If the Court of Appeals meant by these words to suggest that a contractor with the State has no remedy for a breach by the State of a specific contractual obligation unless the contract itself specifies a remedy for such a breach, we disagree. See Middlesex Construction Corp. v. State ex rel. Art Museum Bldg. Comm., 307 N.C. 569, 574, 299 S.E. 2d 640, 643 (1983),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crescent Univ. City Venture, LLC v. Ap Atl., Inc.
2019 NCBC 46 (North Carolina Business Court, 2019)
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
Southern Seeding Service, Inc. v. W.C. English, Inc.
719 S.E.2d 211 (Court of Appeals of North Carolina, 2011)
Companies v. North Carolina Department of Transportation
587 S.E.2d 426 (Court of Appeals of North Carolina, 2003)
Battle Ridge Cos. v. Dept. of Transp.
587 S.E.2d 426 (Court of Appeals of North Carolina, 2003)
RPR & Associates, Inc. v. University of North Carolina-Chapel Hill
570 S.E.2d 510 (Court of Appeals of North Carolina, 2002)
Southern Furniture Hardware, Inc. v. Branch Banking & Trust Co.
526 S.E.2d 197 (Court of Appeals of North Carolina, 2000)
Faulkenbury v. Teachers' & State Employees' Retirement System of North Carolina
510 S.E.2d 675 (Court of Appeals of North Carolina, 1999)
Faulkenbury v. TEACHERS'& STATE EMP. RET.
510 S.E.2d 675 (Court of Appeals of North Carolina, 1999)
APAC-Carolina, Inc. v. Greensboro-High Point Airport Authority
431 S.E.2d 508 (Court of Appeals of North Carolina, 1993)
Ruby-Collins, Inc. v. City of Charlotte
740 F. Supp. 1159 (W.D. North Carolina, 1990)
Thompson-Arthur Paving Co. v. North Carolina Department of Transportation
387 S.E.2d 72 (Court of Appeals of North Carolina, 1990)
Bolton Corp. v. State
383 S.E.2d 671 (Court of Appeals of North Carolina, 1989)
Bolton Corp. v. T. A. Loving Co.
380 S.E.2d 796 (Court of Appeals of North Carolina, 1989)
Pitts v. Broyhill
364 S.E.2d 738 (Court of Appeals of North Carolina, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
337 S.E.2d 463, 315 N.C. 144, 1985 N.C. LEXIS 2000, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davidson-jones-inc-v-north-carolina-department-of-administration-nc-1985.