Flatiron-Lane v. Case Atlantic Co.

121 F. Supp. 3d 515, 2015 U.S. Dist. LEXIS 102539, 2015 WL 4644727
CourtDistrict Court, M.D. North Carolina
DecidedAugust 4, 2015
DocketNo. 1:12cv1234
StatusPublished
Cited by3 cases

This text of 121 F. Supp. 3d 515 (Flatiron-Lane v. Case Atlantic Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flatiron-Lane v. Case Atlantic Co., 121 F. Supp. 3d 515, 2015 U.S. Dist. LEXIS 102539, 2015 WL 4644727 (M.D.N.C. 2015).

Opinion

MEMORANDUM OPINION AND ORDER

THOMAS D. SCHROEDER, District Judge. .

This case arises out of a dispute between the general contractor, Flatiron-Lane, a Joint Venture (“FLJV”), and Case Atlantic Company (“Case”), its subcontractor, over the construction of the foundation for a highway bridge. The subcontractor’s work took significantly longer than initially expected, and the parties dispute who is to blame for the delay.

A bench trial on the merits of all claims and counterclaims was conducted from April 6, 2015, through May 5, 2015. ■ FLJV presented nine witnesses; Case presented five. At the close of FLJVs case-in-chief, Case moved, for judgment pursuant to Rule 52(c) of the Federal Rules of Civil Procedure, though the court declined to enter judgment at that time. Following trial, the parties submitted proposed findings of fact and conclusions of law. (Docs. 135, 136.) The case is ready for resolution.

I. FINDINGS OF FACT

Pursuant to Rule 52(a) of the Federal Rules of Civil Procedure, the court enters the 'following findings of fact based upon an evaluation of the evidence, including the credibility of witnesses, and the inferences that the court has found reasonable to be drawn therefrom. To the extent any factual statement is contained in the conclusions of law, it is deemed a finding of fact as well.

FLJV’s Pursuit

1. In 2009, the North Carolina Department of Transportation (“NCDOT”) began formally soliciting design-build proposals to replace two bridges spanning the Yadkin River near the border of Davidson and Rowan Counties (the ‘Yadkin Project” or “Project”). The longer bridge, referred to as Bridge 2, comprised part of Interstate 85; the relatively shorter bridge, referred to as Bridge 3, was part of United States Highways 29 and 70.

[521]*5212. A design-build project is one in which the owner, here NCDOT, hires a general contractor both to design and construct the project. By contrast, some construction projects are bidrbuild projects (or design-bid-build projects), where the design is already complete when the owner hires a contractor to construct the project. Both Bridges 2 and 3 were part of a larger design-build project. .

3. Flatiron Construction and Lane Construction pursued the Yadkin Project as a joint venture, with 60%' and 40% stakes, respectively. As- noted, the joint venture is collectively referred to as “FLJV.”

, 4, FLJVs pursuit team was composed of FLJVs employees, as well as several entities with whom it subcontracted, STV/ Ralph Whitehead Associates, Inc. (“STV’), a professional engineering firm, was part of the pursuit team, serving as the Project’s head designer. Froehling and Robertson, Inc. (“F & R”), a geotechnical firm, was also part of the pursuit team, assisting with the design of the bridges as well as inspections and geotechnical engineering work. Preliminary design decisions-began being made during the pursuit phase.

- 5. The Yadkin Project contemplated the drilling of shafts into the ground— known as “drilled shafts,” “drilled piers,” and “caissons” — into which concrete would be poured. These drilled shafts would serve as the foundations for-Bridges 2 and 3. Very generally, .the shafts are excavated by drilling with large drill rigs inside of cylindrical steel casing, either permanent or temporary, .to protect the shaft from cave-ins during excavation. Once excavation is complete, the void is filled with rebar cages, and concrete is poured into the shaft up to a few feet above the surface level. Once this concrete cures, concrete vertical columns are formed on top of the piers. Each set of four drilled piers is known as a “bent.” Horizontal concrete caps are built on top of the columns for each bent of shafts. Girders are placed on top of,the caps, connecting bent-to-bent, upon which a concrete driving .surface is eventually poured. . :

6. FLJV originally planned to do much of the drilled shaft work itself. While pursuing the prime contract, it sought estimates from drilled shaft companies for the cost of the excavation work only.

7. In design-build projects, the design is often not finalized when contracts are awarded or even when construction commences, and the' design is subject to change throughout the construction phase.' For this reason, FLJV sought estimates based on “unit price’s.” As relevant here, for example, FLJV sought estimates on how much a drilled shaft contractor would charge per linear foot of drilling, with the final “units” or “quantities” — i.e;, the number of linear feet each shaft is drilled into the ground — to be determined1 once the drilled shaft is constructed.

8. In March 2010, FLJV sought and received an estimate from Case, a drilled shaft company, operating primarily in the southeastern United States. Case is a wholly owned subsidiary of Case Foundation, which is itself owned by the international Keller Group of companies. Nigel Osborn, who has served as its' president since the late 1990s, led a group of Case employees from the bidding of the Yadkin Project through Case’s ultimate execution of a subcontract with FLJV.

9. In April 2010, NCDOT awarded the Yadkin Projpct to FLJV, and the two executed the prime contract on May 24, 2010. (Ex.201.1)

[522]*522 Subcontract Negotiations

10. Theodore “Ted” Kirk participated in FLJV’s pursuit of the Yadkin Project, serving as its design build project manager. Once FLJV was awarded the prime contract, Kirk solicited several prospective drilled shaft contractors, including Case, to provide FLJV with an estimate for a fuller scope of work; that- is, not just drilling the shafts, but also providing and setting the casing and pouring the concrete. In general, drilled shaft contractors like Case prefer to do this expanded scope of shaft and pier work themselves.

11. Case began submitting several proposals to FLJV, providing updated unit price schedules for the fuller scope of work. On June 16, 2010, Case submitted a proposal offering to do the work in fourteen weeks, excluding holidays. (Ex. 227.).

12. FLJV and Case met to discuss this proposal on June 17, 2010, in FLJV’s Morrisville, North Carolina office. Kirk and another employee represented FLJV; and Andy Buck, Case’s estimator and later project manager, attended with Larry Blough, Case’s vice president of operations. The men discussed the details of what Case had included and excluded from its scope in the most recent proposal.

13. They also discussed Case’s- experience performing drilled shaft work in North Carolina. Buck and Blough represented that Case was experienced with the type of subsurface conditions at the.Project site and that Case was familiar with NCDOT’s specifications and requirements for drilled shaft contractors, as well as the standard practices and procedures employed in the Piedmont area of North Carolina in which the Project was located. In particular, Kirk gave Buck part of NCDOT’s Drilled Pier Inspection Manual, a publicly available document, which explains the standards and specifications NCDOT’s drilled shaft inspectors apply when approving drilled shafts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Llano County
103 F.4th 1140 (Fifth Circuit, 2024)
Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
121 F. Supp. 3d 515, 2015 U.S. Dist. LEXIS 102539, 2015 WL 4644727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flatiron-lane-v-case-atlantic-co-ncmd-2015.