J. W. Bateson Company, Inc. v. United States

308 F.2d 510, 1962 U.S. App. LEXIS 4043
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 26, 1962
Docket19392
StatusPublished
Cited by17 cases

This text of 308 F.2d 510 (J. W. Bateson Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. W. Bateson Company, Inc. v. United States, 308 F.2d 510, 1962 U.S. App. LEXIS 4043 (5th Cir. 1962).

Opinion

WISDOM, Circuit Judge.

This is an appeal from a judgment against J. W. Bateson Co. for $42,264.93, the amount was allegedly overpaid on a Government construction contract.

Although this controversy is concerned solely with the method of computing the-contract price for the construction of 250 houses and certain other buildings at Camp Pickett, Virginia, it is inextricably-interwoven with a second contract, also, held by Bateson, for construction at Camp Breckinridge, Kentucky. On May 8, 1953, the Government partially terminated this second agreement, under which Bateson was to construct 430 houses, nine *512 laundry buildings, and one community building. By a letter dated May 11,1953, Bateson was directed by the Contracting Officer in charge of both contracts to complete only 81 dwelling units at Camp Breckinridge, to cancel the contract with the subcontractor for the prefabricated building materials to be used at Camp Pickett, and to ship 250 of the Breckin-ridge units to Camp Pickett. The remaining 99 units at Breckinridge were shipped to Piketon, Ohio, for use by another contractor on a Government project there. A final settlement on the Breckinridge contract was made in October 1953. Under the terms of Change Order No. G-8, Bateson received a total profit of $95,812.76, 10.11’% of the cost ■on all the prefabricated material furnished under the Breckinridge contract: the 81 units completed at Breckinridge, the 99 surplus units diverted to Pikoton, and the 250 units subsequently erected at •Camp Pickett.

These steps required a modification of the Camp Pickett contract. Since the prefabricated materials used for the buildings there were being provided by the Government from the surplus units it had just purchased for Camp Breck-inridge, the parties agreed that the Government should receive a credit of $471,-'360.98, and Change Order No. G-2, executed in June, 1953, so provided. On October 14, 1953, Change Order No. G-7, making a further reduction of $30,212.05 in the contract price because of a final credit on the prefabricated material, was executed. The parties have stipulated that these credits given to the Government in the change orders did not include Bateson’s profit. In other words, the half-million dollar reduction in the Pickett contract sum offset only the can-celled purchase order to Bateson’s subcontractor; it did not take into account Bateson’s profit on the order, which amounted to $42,264.93, approximately 10% of the $427,752.00 which Bateson would have owed its Pickett subcontractor for 250 prefabricated dwelling units. These figures were computed in the first instance by Bateson and transmitted to the Contracting Officer, who incorporated them into the Change Orders No. G-2 and G-7. Thus, the end result of these two contract modifications was that Bate-son collected a profit on all 430 units which it furnished under the Breckin-ridge contract, and then received a second profit on the 250 units which were not used at Breckinridge, but shipped instead to Camp Pickett. The Government is now seeking to recover the $42,264.93, which, it claims, was erroneously paid on the Pickett contract.

Bateson’s first, and primary line of defense is that whereas the modification in the Breckinridge contract constituted a “partial termination,” governed by Section 12 of the General Provisions (which are identical in both contracts), the corresponding modification of the Pickett contract was merely a “change,” pursuant to General Condition 9. The key difference in these two clauses, insofar as we are here concerned, is that Section 12 provides that in making contract price adjustments for terminations or partial terminations, “the Contracting Officer shall give no consideration to claims for anticipated profits on the portion of the contract work which is not completed”; Section 9, however, stipulates that “if the net cost value of a change results in a credit from the Contractor or subcontractor, the credit given shall be the net cost without overhead or profit.” If, therefore, the cancellation of Bateson’s order of 250 prefabricated units from its subcontractor was a “change,” the allowance of a $42,264.93 profit was proper.

Bateson argues that the Breckinridge and Pickett contracts are two entirely separate matters, and that any connection between them is irrelevant. It concedes that the Government’s cancellation of the construction of 349 houses at Breck-inridge acted as a partial termination of that contract, but it points out that the work at Pickett was entirely performed, with only the slight variation from the original contract that the Government rather than an independent subcontractor furnished material for the 250 units. This, argues Bateson, was merely a *513 “change.” Bateson performed the same amount of work at Pickett with the Government furnishing the prefabricated material as it would have if the original subcontractor had done it. To clinch the argument, it points to Change Order No. G-2, which specifically stipulates that

“the following change is ordered in connection with Section 9 of the General Conditions:
“The Government will furnish to the Contractor, without cost, and the Contractor is relieved of the obligation to furnish, the materials listed and described on the Schedule attached hereto and made a part hereof as Exhibit ‘A’.”

The easiest answer to these arguments, however, is that the two contracts must be considered together. Whatever may have been their original status as entirely unrelated agreements, after the modification of the Breckinridge contract what was done at Breckinridge had a direct and corresponding impact on what was done at Pickett. Thus when the Director of the Field Office for the Public Housing Administration wrote Bateson on May 11 confirming the partial cancellation of construction at Camp Breckinridge, he treated both contracts as one. Bateson was instructed to “cancel the contract with the subcontractor for the furnishing of dwelling structures on Project VA-8D1, Camp Pickett, in its entirety,” and to “re-ship all of the units now on cars at Camp Breckinridge, or en route thereto,” to Camp Pickett. This same letter cancelling construction of prefabricated units at Camp Breckinridge cancelled the supply of prefabricated materials at Camp Pickett. Because of this interrelation of the modifications of both contracts, it is difficult to see how what was a “partial termination” in one case could be a “change” in the other. Indeed, the common-sense effect of these modifications was a partial termination of the construction aspect at Breckinridge and a corresponding termination of the supply aspect at Pickett. The use of a change order form by the Government cannot be decisive as to the legal nature of the modifications, for the modification of both contracts — and Bateson concedes that Breckinridge was partially terminated — was accomplished through change order forms.

Even if the Pickett contract is considered by itself, however, a construction of the terms of the contract and a comparison of these contractual terms with the magnitude of the elimination of the supply aspect indicates that the Pickett contract was “partially terminated” and not merely “changed.” The contract does not define “change order” or “termination order,” and as Judge Dooley, the district judge below, pointed out:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2021
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
Praecomm, Inc. v. United States
78 Fed. Cl. 5 (Federal Claims, 2007)
Barrett Refining Corp. v. United States
45 Fed. Cl. 166 (Federal Claims, 1999)
Houston v. Capps (In Re Capps)
193 B.R. 955 (N.D. Alabama, 1995)
Robinson Contracting Co. v. United States
35 Cont. Cas. Fed. 75,654 (Court of Claims, 1989)
Lumarose Equipment Corp. v. City of Springfield
446 N.E.2d 1087 (Massachusetts Appeals Court, 1983)
Universal Fiberglass Corp. v. United States
537 F.2d 400 (Court of Claims, 1976)
Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)
C. J. Langenfelder & Son, Inc. v. The United States
341 F.2d 600 (Court of Claims, 1965)
C. J. Langenfelder & Son, Inc. v. United States
341 F.2d 600 (Court of Claims, 1965)
State Ex Rel. Callaway v. Axtell
393 P.2d 451 (New Mexico Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
308 F.2d 510, 1962 U.S. App. LEXIS 4043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-w-bateson-company-inc-v-united-states-ca5-1962.