Propellex Corporation v. Les Brownlee, Acting Secretary of the Army

342 F.3d 1335, 200 A.L.R. Fed. 757, 2003 U.S. App. LEXIS 18647, 2003 WL 22076597
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 9, 2003
Docket02-1358
StatusPublished
Cited by35 cases

This text of 342 F.3d 1335 (Propellex Corporation v. Les Brownlee, Acting Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Propellex Corporation v. Les Brownlee, Acting Secretary of the Army, 342 F.3d 1335, 200 A.L.R. Fed. 757, 2003 U.S. App. LEXIS 18647, 2003 WL 22076597 (Fed. Cir. 2003).

Opinion

SCHALL, Circuit Judge.

Propellex Corporation (“Propellex”) appeals from the final decision of the Armed Services Board of Contract Appeals (“Board”) that sustained the final decision of the contracting officer denying in part Propellex’s claim for additional compensation under two contracts between Propel-lex and the Department of the Army’s Armament, Munitions and Chemical Command (“Army”) for the production and delivery of gun primers. Propellex Corp., ASBCA No. 50,203, 02-1 B.C.A. (CCH) ¶ 31,721, at 156,730-31, 2001 WL 1678757 (Dec. 27, 2001). Propellex sought recovery under a modified total cost method. The Board denied Propellex’s appeal because it concluded, inter alia, that Propellex had failed to establish that it was impracticable for it to prove its actual losses directly, which is one of the requirements for recovery under the total cost method. Id. at 156,730. Because the decision of the Board is supported by substantial evidence and is free of legal error, we affirm.

BACKGROUND

I.

The Army awarded Propellex two fixed price contracts, contract no. DAAA09-88-C-0817 (the “817 contract”) and contract no. DAAA09-90-C-0455 (the “455 contract”), for the production and delivery of a specified number of MK 45 primers. The 817 contract also called for the production and delivery of a specified number of MK 153 primers. A primer is a component of a gun shell. A shell generally includes a projectile and a propellant charge. The primer is an explosive device that ignites the propellant charge in the shell. The propellant charge in turn propels the projectile. A key component of a primer is black powder.

Both the contracts required that Propel-lex furnish the primers in lots. The 817 contract called for Propellex to furnish the MK 45 primers in nine separate lots and the MK 153 primers in one lot. The 455 contract called for Propellex to furnish MK 45 primers in five separate lots. Under each contract, before the Army would accept a lot for delivery, Propellex was required to submit samples of the primers in the lot to the Naval Surface Warfare Center (“NSWC”) in Indian Head, Maryland, for, inter alia, testing of the moisture content of the black powder contained in the primers. Under the contracts, the moisture content of the black powder in the primers could not exceed a certain level. To ensure compliance with this require *1337 ment, Propellex performed its own moisture analysis on the black powder before sending the primers to NSWC for testing.

In September of 1990, Propellex sent to NSWC for testing samples of primers from lot six of the 817 contract. Following testing, the Army determined that the sample primers did not comply with the requirements of the contract because the moisture content of their black powder exceeded what was allowed under the contract. As a result, the Army rejected the lot. The Army stated that the excess moisture in the primers was the fault of Propellex, and it directed Propellex to resolve the problem.

In response to the Army’s rejection, Propellex conducted an investigation to determine the cause of the alleged moisture in the primers. Although primer production continued during the investigation, Propellex diverted a number of its production employees to investigate the moisture problem. Propellex kept records of the tests it performed. However, the records did not include the number of employees, labor hours, or amount of materials involved in the testing. During the investigation, which spanned a period of two years, the Army also rejected lots 1, 2, and 8 of the 455 contract for excess moisture and other defects.

On February 16, 1993, after Propellex had completed its investigation, it notified the Army that it had not found any evidence indicating that the moisture content of the black power in its primers was above the level specified as acceptable in the contracts. It suggested that the Army determine if there was a defect in its testing procedures.

On April 7, 1993, Propellex’s consultant, Edward Williams, and the Defense Contract Management Agency’s quality assurance engineer, Bryan Nussbaum, observed NSWC’s testing of samples from lot five of the 455 contract. Over the next few months, they further observed and analyzed NSWC’s testing procedures. As a result of their observations and analysis, they found defects in the procedures. Eventually, the Army accepted all of the primers that Propellex produced under the contracts.

On September 16,1994, Propellex filed a claim with the contracting officer, seeking an equitable adjustment under the 817 and 455 contracts in the total amount of $1,790,065. In its claim, Propellex sought to recover the costs it incurred in conducting the moisture investigation, as well as certain costs it incurred in testing the moisture content of its primers prior to delivery to the Army. 1 It also sought to recover unabsorbed overhead costs, claim preparation costs, and consulting expenses. The contracting officer acknowledged that NSWC had committed errors in its testing of primer samples and that the Army was therefore responsible for some of the additional costs Propellex had incurred. The contracting officer determined that Propel-lex was entitled to a recovery in the amount of $77,325. However, she denied the balance of Propellex’s claim:

Based on a review of the Request for Equitable Adjustment, the supporting documentation available to the Contracting Officer and all other relevant facts, it is the Contracting Officer’s decision that the Government was and is responsible for only a small portion of the claimed amounts. Based on insufficient data to further support damages claimed by Propellex, the Contracting Officer finds an Equitable Adjustment in the amount *1338 of $77,325.00 due to Propellex as a result of the Equitable Adjustment Claim under contracts DAAA09-88-C-0817 and DAAA09-90-C-0455.

Propellex timely appealed the contracting officer’s final decision to the Board under the provisions of the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (“CDA”).

II.

Following a hearing, the Board granted Propellex’s appeal with respect to entitlement, finding that NSWC had not conducted the primer acceptance tests in accordance with contract testing requirements. Propellex, 02-1 B.C.A. at 156,729. As a result, the Board awarded Propellex $33,110, plus interest, for claim preparation costs and consulting expenses. Id. at 156,730. However, the Board denied in toto Propellex’s claims for the cost of the moisture investigation and for unabsorbed overhead costs. Id.

In denying Propellex’s claim for the cost of the moisture investigation, the Board observed that Propellex had advanced the claim using a modified total cost method. Id. at 156,729.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers
930 F.3d 1354 (Federal Circuit, 2019)
Missouri Department of Social Services
Armed Services Board of Contract Appeals, 2019
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2018
BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
EJB Facilities Services
Armed Services Board of Contract Appeals, 2015
Tecom, Inc. v. United States
86 Fed. Cl. 437 (Federal Claims, 2009)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
342 F.3d 1335, 200 A.L.R. Fed. 757, 2003 U.S. App. LEXIS 18647, 2003 WL 22076597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/propellex-corporation-v-les-brownlee-acting-secretary-of-the-army-cafc-2003.