Tecom, Inc. v. United States

86 Fed. Cl. 437, 2009 U.S. Claims LEXIS 72, 2009 WL 807571
CourtUnited States Court of Federal Claims
DecidedMarch 25, 2009
DocketNo. 00-475C
StatusPublished
Cited by6 cases

This text of 86 Fed. Cl. 437 (Tecom, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tecom, Inc. v. United States, 86 Fed. Cl. 437, 2009 U.S. Claims LEXIS 72, 2009 WL 807571 (uscfc 2009).

Opinion

OPINION AND ORDER

WOLSKI, Judge.

Tecom, Inc. brought a certified claim under the Contract Disputes Act of 1978, 41 U.S.C. § 601, et seq. (“CDA”), on behalf of its subcontractor Fleetpro, Inc. Tecom contracted with the United States Department of the Air Force (“Air Force”) to provide, among other things, vehicle maintenance services at Peterson Air Force Base (AFB), [439]*439Colorado and at the related facilities Cheyenne Mountain Air Station and Falcon AFB. On motions for summary judgment, the Court had already found the defendant liable on a cause of action for breach of contract. See Tecom v. United States, 66 Fed.Cl. 736, 756-57, 776 (2005). The Air Force was contractually required to pay Tecom special compensation if the Peterson AFB Complex vehicle fleet was in such a condition that more than 355 labor hours’ worth of repairs were inherited by Tecom as of December 1, 1996. As it was undisputed that the required repairs at the contract start date were significantly in excess of this amount, and the government only paid Tecom special compensation for a fraction of this work, the Court formd liability established for breach of contract. Id. at 757. A trial on damages was then held, and as is described in detail below, the Court finds that Tecom has proven damages totaling $818,256.87, plus interest.

I. BACKGROUND

A. Prior Proceedings

Plaintiff’s First Amended Complaint (“Complaint”) asserted five causes of action against the government: (1) an equitable adjustment for a constructive change to the contract, based on the vehicle fleet being in much worse condition than the contract indicated, see Compl. ¶¶ 34-37; Tecom, 66 Fed.Cl. at 742, 774-75; (2) breach of contract, for failure to pay additional compensation for an excess backlog of required maintenance, see Compl. ¶¶ 38-39; Tecom, 66 Fed.Cl. at 742, 749-57; (3) breach of the implied duty of cooperation, see Compl. ¶¶ 40-42; Tecom, 66 Fed.Cl. at 742, 772-73; (4) breach of the duty not to hinder or interfere with performance, see Compl. ¶¶ 43-45; Tecom, 66 Fed.Cl. at 742, 772-73; and (5) wrongful termination for default. See Compl. ¶¶ 46-47; Tecom, 66 Fed.Cl. at 742, 775-76.

The contract at issue, number F05604r-97-C-9001, plaintiffs trial exhibit (“PX”) 1, was awarded to Tecom on October 21, 1996. See Tecom, 66 Fed.Cl. at 739. This lawsuit concerns the Vehicle Operations and Maintenance portion of the contract. Under a “firm fixed price” provision, Tecom was to receive $76,282 per month during an initial, ten-month term, for maintaining a base fleet of 563 vehicles. PX 1 at 3, ¶ 7AA; Tecom, 66 Fed.Cl. at 739. The contractor was required to meet two separate standards in maintaining the fleet — the percentage of vehicles out-of-commission at any one time could not exceed the vehicle out-of-commission (“VOC”) rate established for each vehicle category, and a certain number of each type of vehicle had to be in working order at all times to satisfy Minimum Essential Levels (“MELs”). Tecom, 66 Fed.Cl. at 739. Fleetpro was the subcontractor performing the vehicle maintenance work under the contract, until the subcontract was terminated by Tecom on June 2, 1997. See id. at 742.

In the context of summary judgment motions, the Court interpreted the key provisions of the contract and found certain facts established beyond dispute. The critical contract provisions are contained in the “Performance Work Statement for Vehicle Operations and Maintenance Services for Peterson Air Force Base Complex Colorado” (“PWS”). The most important paragraph reads:

On the contract start date, the required maintenance actions will not exceed 25 labor hours per 100 vehicle equivalents and there will not be any overdue scheduled/preventive maintenance and special inspeetions/test. If either of these standards are exceeded, the incoming contractor shall reduce this backlog and will be compensated for this initial reduction LAW the over and above hourly rate and material costs as verified by invoices input into the OLVIMS. The contractor shall have thirty (30) days to meet the performance requirements for these services. This compensation does not apply to the incumbent contractor.

PX 1 at 88 (PWS ¶ 5.5.1).

The parties were in agreement that “25 labor hours per 100 vehicle equivalents” translated into 355 labor hours, given the size of the fleet. Tecom, 66 Fed.Cl. at 740. The Court found that this provision was intended “to have the Air Force bear the risk of excessive maintenance work inherited by the incoming contractor.” Id. at 753. The “OLVIMS” referenced was the Air Force’s [440]*440On-Line Vehicle Interactive Management Service (OLVIMS).1 See PX 1 at 68 (PWS ¶ 2.2.28). The Court rejected the government’s interpretation of this provision as limiting the backlog to the required maintenance actions that were entered into OLVIMS by Tecom’s predecessor. Tecom, 66 Fed.Cl. at 753.

From the second week of November through November 26, 1996, inspections of the vehicle fleet conducted jointly by representatives of Fleetpro, the Air Force, and outgoing contractor LB & B Associates, Inc. (“LB & B”), assessed the condition and maintenance status of 286 of the 563 vehicles in the fleet. Id. at 744. The government’s litigation position was that these inspections were unauthorized or wrongful, but the Air Force personnel involved at the time called them the “assessment” or “joint assessment” required by a contract clause contained in both the outgoing incumbent’s contract and that of Tecom. See id. at 740 & n. 6, 744-46, 754, 756. This clause, entitled “Vehicle Assessment,” reads: “At contract termination, the incumbent contractor, incoming contractor, and FAC shall jointly assess all vehicles to be transferred to the new contract or Government for quantity, condition, and maintenance status.” PX 1 at 88 (PWS ¶ 5.5.2). The Court found that the joint inspections were conducted under the vehicle assessment clause. Tecom, 66 Fed.Cl. at 754-56.

These joint inspections revealed that an alarming amount of repairs was needed for the fleet, including severe safety issues with vehicles upon which maintenance work had recently been performed. Id. at 744. Undisputed facts established “that labor hours far in excess of 355 were needed to make the inherited repairs.” Id. at 757. Based on just the 236 vehicles assessed, the Air Force’s own documents estimated that 2500 to 3000 maintenance hours were needed above the 355 labor hour threshold of the contract, and acknowledged that the total backlog could exceed 6000 hours. Id. at 745-46. The VOC rate for the vehicle fleet at contract turnover was also far in excess of the limit, and the VOC rates applying to at least five categories of vehicles were exceeded. See id. at 746, 775. As the contract entitled Tecom to additional compensation for reducing a maintenance backlog exceeding 355 labor hours of repair work, and Te-com was only paid for a fraction of this reduction, the government was found liable for breach of contract and summary judgment was granted to Tecom on its second cause of action. Id. at 757. The Court also granted summary judgment in favor of the government on the wrongful termination claim. Tecom,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Athey v. United States
123 Fed. Cl. 42 (Federal Claims, 2015)
Hernandez, Kroone & Associates, Inc. v. United States
95 Fed. Cl. 395 (Federal Claims, 2010)
Entergy Nuclear Fitzpatrick, LLC v. United States
93 Fed. Cl. 739 (Federal Claims, 2010)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Reunion, Inc. v. United States
90 Fed. Cl. 576 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
86 Fed. Cl. 437, 2009 U.S. Claims LEXIS 72, 2009 WL 807571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tecom-inc-v-united-states-uscfc-2009.