Phillips & Jordan, Incorporated v. United States

CourtUnited States Court of Federal Claims
DecidedFebruary 28, 2022
Docket15-1301
StatusPublished

This text of Phillips & Jordan, Incorporated v. United States (Phillips & Jordan, Incorporated v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips & Jordan, Incorporated v. United States, (uscfc 2022).

Opinion

In the Cited States Court of Federal Claims

No. 15-1301 Filed: February 28, 2022

PHILLIPS & JORDAN, INC., Plaintiff,

v.

THE UNITED STATES,

Defendant.

James W. Copeland, Copeland Law Firm, LLC, Atlanta, Georgia, for Plaintiff.

Jimmy S. McBirney, Ashley Akers, Trial Attorneys, Claudia Burke, Assistant Director, Patricia M. McCarthy, Commercial Litigation Branch, Brian M. Boynton, Acting Assistant Attorney General, Civil Division, U.S. Department of Justice, Washington, D.C., Amber Jackson, U.S. Army Corps of Engineers, for Defendant.

POST-TRIAL OPINION AND ORDER

TAPP, Judge.

This South Florida construction contract case involves two differing site condition claims and a subcontractor’s entitlement to damages. Although Phillips & Jordan, Inc. brings this action, the real party in interest is its subcontractor, Optimum Services, Inc. (‘OSI’). At trial, though OSI attempted to prove a differing site condition with respect to the soil content, OSI failed to establish several elements of that claim, principally whether the contract represented that the contractor would encounter a particular percentage of shell content. OSI also attempted to prove that it remains undercompensated for a differing site condition the United States previously acknowledged. However, OSI failed to establish uncompensated liability. Even if it had, OSI’s method of calculating damages is overly speculative.

I. Background

On July 14, 2011, the United States Army Corps of Engineers (“Army Corps”) awarded Phillips & Jordan, Inc. a $32.4 million contract to construct the first phase of the C-44

' Because this is a subrogated claim, the Court often uses “Plaintiff” where the distinction is immaterial and the respective companies’ names where more clarity is necessary. Reservoir/Stormwater Treatment Area Project in Martin County, Florida. (Joint Stipulations of Fact (“JSOF”) at § 2, ECF No. 87; PX014.005, .213; PX016).

~ if A 7 St. Lucie County 7 Martin County pos: o> ft fap : D< ae salman \ \ \ |e Fn B55 C-44 BASIN Re / ae \ ee eee ; a ora Prim Beach County oi TeRaee cai ae tamara | Pe VICINITY MAP

Phillips & Jordan, Inc. v. United States, 15-1301 Trial Exhibit: PX015.002

Several months later, Phillips & Jordan subcontracted intake canal excavation, embankment, and demolition work to OSI. That subcontract was worth $5,515,769.86. (JSOF at 4 3). Excavation and embankment were part of the prime contract, contract line-item number (“CLIN”) 0005. (PX014.007).

Approximately a year and a half later, the Army Corps revised the scope of its contract with Phillips & Jordan to address shortages of material in the intake canal and requested that Phillips & Jordan revise its pricing to accommodate those revisions to CLIN 0005. (JSOF at § 4). Accordingly, Phillips & Jordan submitted a Request for Equitable Adjustment (“REA”) totaling $5,461,937.87—1most of which ($4,784,584.79) would be passed through to OSI. (/d. at § 5).

Just a few days later, Phillips & Jordan submitted a second response to the Army Corps’ scope revision, separate and distinct from its first REA, requesting an additional $4,961,623.29 for “Total Additional Cost[s] Due to Defective Spec[ifications]: Intake Canal Material Shortage.” (/d. at § 6). That second proposed scope revision would be largely passed through to OSI after Phillips & Jordan retained roughly $700,000 for its overhead and profit markup. (/d.).

In January 2014, the Army Corps and Phillips & Jordan bilaterally executed Contract Modification P00022, increasing the total contract price by $4,857,756.55 and extending the project completion date by 114 calendar days in response to, and as a final resolution of, Phillips & Jordan’s second response to the revised contract scope. (/d. at § 7). Contract Modification P00022 stated that the contract price increase and time extension “reflects all credits due the Government and all debits due the Contractor,” and that the adjustment “constitutes compensation in full on behalf of the Contractor and its Subcontractors and Suppliers for all costs and markups directly or indirectly attributable for the change ordered, for all delays related thereto, for all extended overhead costs, and for performance of the change within the time frame stated[.]” Ud.; PX243). Contract Modification P00022 caveated that it did “not include costs associated with the contractor’s pending REA, submitted under Serial Letter H-0076, [Phillips & Jordan’s first REA response].” (JSOF at 7 7; PX243).

In June 2014, Phillips & Jordan converted its first REA into a pass-through certified claim from OSI to the Army Corps. (JSOF at J 8). That certified claim sought $4,784,584.79 in compensation to be passed through to OSI and $21,577.88 in bonding costs to Phillips & Jordan. (/d.). That pass-through claim amount, $4,784,584.79, matches exactly the amount OSI sought to receive through Phillips & Jordan’s first REA. (See id. at | 5). On July 25, 2013, the Army Corps accepted Phillips & Jordan’s performance as complete. (/d. at § 9). Several months later, the Army Corps denied Phillips & Jordan’s certified claim. (/d. at J 10).

Two years later, in October 2016, Phillips & Jordan revised, certified, and submitted its claim to include OSI’s certified modified total costs calculations, that time seeking $4,653,512.68. (Vd. at § 11). If the Army Corps approved that certified claim, Phillips & Jordan intended to pass through $4,066,298.51 to OSI. (JSOF at ¥ 11). Phillips & Jordan now asks the Court to review the Army Corps’ original denial of Phillips & Jordan’s certified claim, as amended in October 2016. Ud. at J 12).

Plaintiff’ s four-count Complaint primarily raises two issues. First, Plaintiff contends that the soils it encountered on the site differed from the soils that the contract specified Plaintiff would encounter. (2d Am. Compl. at J 34-50, ECF No. 32). Plaintiff seeks damages for that difference, and couches that claim as a differing site condition, or alternatively, a defective specification. (/d.). Second, Plaintiff asserted that there was a material imbalance between excavation and embankment material quantities. /d. at J 14-33). In other words, the quantity of soil Plaintiff was required to excavate from the canal was insufficient to construct the embankment to the contract’s specifications. Plaintiff asserts entitlement to damages related to the imbalance, which Plaintiff characterizes as due to a differing site condition, or alternatively, a defective specification.’ (/d.).

Beginning August 16, 2021, the Court conducted a seven-day trial on these issues in West Palm Beach, Florida. During trial, the Court heard testimony from nine witnesses, including Daniel Eastman (the President of OSI), two former vice presidents of Phillips & Jordan, three Army Corps employees, an employee from OSI, and two expert witnesses.’ At the conclusion of the trial, on August 24, the parties agreed to simultaneously submit post-trial briefs

* Plaintiffs defective specification claims are based on an alleged breach of implied warranty of adequate design.

> A transcript of the trial is docketed at ECF Nos. 123-29. The Court will reference the witness’s name in trial citations to reflect their time on the stand (e.g., “(Eastman, TR at 164)”), but quotations may reflect questions or statements of counsel where appropriate. Discussions between attorneys and the Court will be noted as a “Colloquy.” “not later than close of business 40 days following the production of the [trial] transcript.” (Colloquy, TR at 1273:20-22).

After some unexpected delay, the transcript was filed in the Court’s CM/ECF filing system on September 27, 2021.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Farm Lines v. Black Ball Freight Service
397 U.S. 532 (Supreme Court, 1970)
Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Hometown Financial, Inc. v. United States
409 F.3d 1360 (Federal Circuit, 2005)
H. John Homan Co., Inc. v. The United States
418 F.2d 522 (Court of Claims, 1969)
The D.L. Auld Company v. Chroma Graphics Corp.
714 F.2d 1144 (Federal Circuit, 1983)
United States v. James C. Dunkel
927 F.2d 955 (Seventh Circuit, 1991)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
The Ravens Group, Inc. v. United States
112 Fed. Cl. 39 (Federal Claims, 2013)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
Bishop v. Smith
112 F. Supp. 3d 1231 (N.D. Oklahoma, 2015)
Willems Industries, Inc. v. United States
295 F.2d 822 (Court of Claims, 1961)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
Phillips & Jordan, Incorporated v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-jordan-incorporated-v-united-states-uscfc-2022.