Bes design/build, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedFebruary 27, 2025
Docket21-1273
StatusPublished

This text of Bes design/build, LLC v. United States (Bes design/build, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bes design/build, LLC v. United States, (uscfc 2025).

Opinion

In the United States Court of Federal Claims No. 21-1273 (Filed: February 27, 2025)

* * * * * * * * * * * * * * * * * * * * BES DESIGN/BUILD, LLC, * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * * * * * * * * * * * * * * * * * * ** *

Jerome E. Speegle, Speegle, Hoffman, Holman & Holifield, LLC, of Mobile, AL, for Plaintiff.

Ioana C. Meyer, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, with whom were Brian M. Boyton, Principal Deputy Assistant Attorney General, Patricia M. McCarthy, Director, and Steven J. Gillingham, Assistant Director, all of Washington DC, for Defendant, and Bailey Kapfer, District Contract Law National Practice Group, Office of General Counsel, Department of Veteran Affairs, of Washington, DC, of counsel.

ORDER AND OPINION

SOMERS, Judge.

This case concerns Plaintiff BES Design/Build LLC’s (“BES”) claims for delay damages that arose from two contracts it entered into with the Department of Veteran Affairs (“VA”). In 2012, BES and the VA entered into two indefinite-delivery, indefinite-quantity contracts, whereby BES was to provide a series of architectural and engineering design documents to the VA in preparation for the renovation of an existing VA medical center in North Little Rock, Arkansas. Per the contracts, BES was to submit five sets of documents to the VA according to a set timeline. After each submission, the VA was to provide comments that were to be resolved and then incorporated into the next submission. However, expectations quickly began to change in two ways. First, the VA submitted a series of comments requesting that BES include in its designs elements that BES claims were not within the scope of the contract. Second, the VA rejected submissions that did not integrate all of its comments instead of, as BES expected, allowing BES to integrate the VA’s comments and feedback into future designs for review at the final submission.

1 BES points to three changes that the VA requested over the course of its submissions that allegedly caused delay and expanded the scope of work agreed to in the original contracts. First, the VA claimed that BES was required to create designs for the demolition and replacement of all existing plumbing and fixtures in the basement bathrooms, which BES had instead designed to be reused. Second, the VA claimed that BES was required to create designs for the replacement of all existing electrical panels. Third, the VA initially requested that BES create designs for the building’s heating system to eradicate the steam-powered heating system, in favor of changing to a gas-powered boiler.

Throughout the rounds of comments and submissions, BES forged ahead with its subsequent submissions without incorporating all of the VA’s requested changes, given the dispute about whether the changes were contractually required. As the project dragged on over the course of three years, the VA began to reject BES’s submissions, and BES resubmitted revised versions, even integrating the changes that it believed to be outside of the scope of the project. The VA continued to pay BES according to its contractual agreement after each submission. Following BES’s final submission, the VA refused payment on the final payment application. It also refused to pay any damages for alleged VA caused delays on the project.

Soon thereafter, BES filed a certified claim with the VA, which the VA rejected, and this suit followed. BES has brought three causes of action for breach of contract. The government has moved for summary judgment on all three causes of action. For the reasons that follow, the Court grants in part and denies in part the government’s motion for summary judgment.

BACKGROUND AND PROCEDURAL HISTORY

A. Contract Structures and Agreement

On September 19, 2012, BES was awarded two contracts, one for architectural designs (VA256-12-D-0332) and one for engineering designs (VA256-12-D-0333), in preparation for the partial renovation of a vacant VA medical center located in North Little Rock, Arkansas (Health Services Research and Development Building #58). See ECF No. 1 ¶¶ 6–7; ECF No. 36 at 2, 6. The contracts were to be performed concurrently over the course of 180 days, beginning on May 6, 2016, when the Notice to Proceed (“NTP”) took effect. See ECF No. 1-4 at 1; ECF No. 36-9 at 2. According to the project schedule, BES’s performance would consist of five submissions to the VA, to be delivered on given dates throughout the 180-day performance period. See ECF No. 1-5 at 4.

BES was contracted to provide design services for the subsequent renovation of approximately 26,000 square feet of the building, which is over 43,000 square feet in total. Id. at 2. However, the Scope of Work did not specify which of the over 43,000 square feet of the existing building would be the subject of the renovation. That topic first arose in a meeting between BES and the VA on May 18, 2016, twelve days after the NTP took effect. See ECF No. 36-4. Following a walk-through of the building, the parties held a meeting. Id. In its meeting notes, the VA briefly describes the condition of each floor of the building and the predicted renovation requirements, concluding that“[w]hile certain areas have been identified as needing renovation, it is [BES’s] responsibility to determine which areas make the most sense

2 for renovation.” Id. ¶ 2(G) (emphasis added); see also id. ¶ 9. BES was effectively limited in the scope of its designs by the contractual scope of work, the VA’s direction, VA technical guidelines and minimum requirements, and the Estimated Cost of Construction (“ECC”), which had been set at $5.8 million. See ECF No. 36-1 at 42–43; ECF No. 1-2 at 1.

The contracts incorporated by reference several provisions of the Veterans Affairs Acquisition Regulation (“VAAR”), the Federal Acquisition Regulation (“FAR”), and provisions found within the VA’s Technical Information Library (“TIL”), such as design manuals, standards, criteria, and space requirements. See generally ECF No. 1-3; see also ECF No. 1-5 at 8–9. One specific guide, found in the VA’s TIL, that was incorporated into the contracts was the VA’s Program Guide known as PG-18-15, Volume C, which sets out “the minimum requirements for each submission in the production of VA Schematics, Design Development, and Construction Documents for Minor and NRM Construction Program for Medical Center Projects.” ECF No. 36-6 at 3. The contracts also incorporated a program guide known as PG- 18-3, Design and Construction Procedures, which were considered “the minimum acceptable standards for the design and construction of VA facilities,” ECF No. 36-5 at 3, as well as PG-18- 10, a Plumbing Design Manual, ECF No. 36-65.

BES delivered its first of the five submissions—consisting of a Signature Page with a set of drawings, space criteria, and cost estimates—on June 8, 2016, four days after the contractual deadline of June 4, 2016. 1 See ECF No. 1-2 at 1; ECF No. 36-12. On June 24, 2016, BES sent the VA a payment application for $69,941.30 for the Signature Page submission, and the VA paid it. See ECF No. 36-64 at 2. This first, non-substantive submission posed no issue for either party, despite the delay.

Required Submission Deadline Contractual Submission Date post-NTP Deadline Signature Page 30 days June 4, 2016 June 8, 2016 Schematic 74 days July 18, 2016 July 26, 2016 Design Document 120 days September 2, 2016 September 16, 2016 Construction Document 160 days October 12, 2016 December 2, 2016 (and five other undefined dates) Final Document 180 days November 1, 2016 June 2018 (and five other undefined dates)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Dawco Construction, Inc. v. The United States
930 F.2d 872 (Federal Circuit, 1991)
Hi-Shear Technology Corporation v. United States
356 F.3d 1372 (Federal Circuit, 2004)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Trinco Investment Company v. United States
130 Fed. Cl. 592 (Federal Claims, 2017)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Morganti National, Inc. v. United States
49 Fed. Cl. 110 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Bes design/build, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bes-designbuild-llc-v-united-states-uscfc-2025.