Donald H. Rumsfeld, Secretary of Defense v. Applied Companies, Inc.

325 F.3d 1328, 2003 U.S. App. LEXIS 7102, 2003 WL 1733711
CourtCourt of Appeals for the Federal Circuit
DecidedApril 2, 2003
Docket01-1630
StatusPublished
Cited by50 cases

This text of 325 F.3d 1328 (Donald H. Rumsfeld, Secretary of Defense v. Applied Companies, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donald H. Rumsfeld, Secretary of Defense v. Applied Companies, Inc., 325 F.3d 1328, 2003 U.S. App. LEXIS 7102, 2003 WL 1733711 (Fed. Cir. 2003).

Opinions

Opinion for the Court filed by Circuit Judge SCHALL. Opinion concurring-in-part and dissenting-in-part filed by Circuit Judge DYK.

ON PETITION FOR PANEL REHEARING.

ORDER

Applied Companies, Inc. (“Applied”) has petitioned for panel rehearing of the court’s December 10, 2002 decision. Rumsfeld v. Applied Companies, Inc., 318 F.3d 1317 (Fed.Cir.2002) (“Applied”).

This suit arises out of a requirements contract between the Defense Logistics Agency (“DLA”), a component of the Department of Defense, and Applied. Under the contract, during the specified period, DLA was to purchase from Applied all of its requirements for two types of refrigerant storage cylinders. After DLA terminated the contract for the convenience of the government, Applied submitted termination settlement and breach of contract claims to the contracting officer. Among other things, Applied alleged that DLA [1330]*1330had breached the contract by providing, in the request for proposals (“RFP”) furnished to prospective bidders, faulty estimates of the number of cylinders it would require during the contract period and then failing to inform bidders when it determined the estimates were inaccurate. Following the contracting officer’s denial of its claim for lost profits, Applied appealed to the Armed Services Board of Contract Appeals (“Board”) under the provisions of the Contract Disputes Act, 41 U.S.C. §§ 601-613. Id. at 1319.

Ruling on cross-motions for summary judgment, the Board concluded that DLA had breached the contract by negligently fading to inform Applied that the estimates in the RFP were inaccurate. In re Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-1 B.C.A. (CCH) ¶31,-325, at 154,729, 2001 WL 210655 (Feb. 26, 2001). The Board also concluded that, during quantum proceedings, Applied could seek to recover the profits it had anticipated making on the total number of cylinders that DLA estimated in the RFP. Id. at 154,734. The Secretary of Defense (“government”) appealed the Board’s decision. In our December 10 decision, we affirmed the Board’s ruling that DLA had breached its contract with Applied. Applied, 318 F.3d at 1323. However, we also stated that, as a matter of law, Applied was not entitled to recover its anticipated profits. Id. at 1324.

In its petition for rehearing, Applied argues first that our decision contains a factual error. Specifically, Applied asserts that we incorrectly state that DLA purchased a total of approximately 11,500 cylinders under the contract. According to Applied, while DLA did order that number of cylinders, the contract was terminated before any deliveries were made. Applied’s second point is that our conclusion that Applied is not entitled to recover its anticipated profits is incorrect as a matter of law. In its response to the petition, the government states that “[t]he record below does not reflect — either way — whether, in fact, Applied delivered any items pursuant to the contract.” As far as Applied’s second point is concerned, the government urges that our decision is free of legal error.

Having considered Applied’s petition and the government’s response, we conclude that, to the extent our decision states in definitive terms that there were deliveries under the contract, the decision is factually incorrect. Accordingly,

IT IS ORDERED THAT:

(1) The Petition for Rehearing is granted for the limited purpose of correcting factual misstatements in the court’s decision issued on December 10, 2002. That decision is hereby withdrawn and the decision attached to this Order is substituted in its place.

(2) In all other respects, the Petition for Rehearing is denied.

OPINION

SCHALL, Circuit Judge.

This suit arises from a requirements contract between the Defense Logistics Agency (“DLA”), a component of the Department of Defense, and Applied Companies, Inc. (“Applied”). Under the contract, among other things, DLA was to purchase from Applied all of its requirements for two types of refrigerant storage cylinders during the period from June of 1994 through June of 1995, with an option year. In its request for proposals (“RFP”), DLA estimated its annual requirements for the two types of cylinders at 62,945 and 56,550 units, respectively. Prior to contract award, DLA determined that the estimates in the RFP were greatly overstated. However, this information was not communicated to any of the offerors, including [1331]*1331Applied. Applied was awarded the contract, but after ordering only approximately 10% of the estimated quantity of cylinders, DLA terminated the contract for convenience on February 6,1995.

Following the denial of its termination for convenience settlement proposal and a claim for breach of contract, Applied appealed to the Armed Services Board of Contract Appeals (“Board”) under the provisions of the Contract Disputes Act, 41 U.S.C. §§ 601-613 (“CDA”). Ruling on cross-motions for summary judgment, the Board concluded that DLA had breached the requirements contract by negligently failing to inform Applied that the estimates of its cylinder requirements in the RFP were inaccurate. Determination of the amount of damages was reserved for further proceedings. In re Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-1 B.C.A. (CCH) ¶ 31,325, 2001 WL 210655 (Feb. 26, 2001) (‘‘Applied I”). DLA’s subsequent motion for reconsideration was denied. In re Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-2 B.C.A. (CCH) ¶ 31,430, 2001 WL 583462 (May 21, 2001) (‘Applied II’’). The Secretary of Defense (“government”) now appeals the Board’s decision. Because the Board did not err in holding that DLA had breached its contract with Applied, we affirm.

BACKGROUND

I.

The pertinent facts, which are not in dispute, are set forth in Applied I. They are as follows:

The requirements contract stemmed from a procurement for cylinders to store R-12 and R-114 refrigerants, which are classified as “Class I Ozone Depleting Substances,” or “ODSs.” Applied I, 01-1 B.C.A. at 154,730. DLA, which was charged with building and maintaining a stockpile of ODSs for the Department of Defense, assessed the existing inventories of ODSs, the amount of ODSs likely to be used and recycled, and the amount of ODSs needed to ensure availability for mission critical uses. In June of 1993, based on its assessment, DLA developed estimates of the amount of R-12 and R-114 refrigerants that it needed to acquire and, by extension, the number of cylinders that would be required to store those refrigerants. Id. On July 14, 1993, DLA issued the RFP for the requirements contract. DLA estimated in the RFP that 62,945 cylinders would be needed for the storage of R-12 refrigerants and that 56,-550 cylinders would be needed for the storage of R-114 refrigerants, for a total of approximately 120,000 cylinders during the one year term of the contract.1 Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peraton, Inc.
Armed Services Board of Contract Appeals, 2025
Sheffield Barbers, LLC
Armed Services Board of Contract Appeals, 2025
Vectrus Systems Corporation
Armed Services Board of Contract Appeals, 2025
D2 Government Solutions
Armed Services Board of Contract Appeals, 2024
MPG West
Armed Services Board of Contract Appeals, 2022
MPG West, LLC
Armed Services Board of Contract Appeals, 2020
Burnham Associates, Inc.
Armed Services Board of Contract Appeals, 2017
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)
United Healthcare Partners, Inc.
Armed Services Board of Contract Appeals, 2016
Palafox Street Associates, L.P. v. United States
122 Fed. Cl. 18 (Federal Claims, 2015)
Nycal Offshore Development Corp. v. United States
743 F.3d 837 (Federal Circuit, 2014)
Englewood Terrace Ltd. Partnership v. United States
113 Fed. Cl. 718 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
325 F.3d 1328, 2003 U.S. App. LEXIS 7102, 2003 WL 1733711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donald-h-rumsfeld-secretary-of-defense-v-applied-companies-inc-cafc-2003.