Thomas E. White, Secretary of the Army v. Delta Construction International, Inc.

285 F.3d 1040, 2002 U.S. App. LEXIS 4784, 2002 WL 398251
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 12, 2002
Docket01-1253
StatusPublished
Cited by25 cases

This text of 285 F.3d 1040 (Thomas E. White, Secretary of the Army v. Delta Construction International, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas E. White, Secretary of the Army v. Delta Construction International, Inc., 285 F.3d 1040, 2002 U.S. App. LEXIS 4784, 2002 WL 398251 (Fed. Cir. 2002).

Opinion

FRIEDMAN, Senior Circuit Judge.

In this appeal the government challenges the theory upon which the Armed Services Board of Contract Appeals (“Board”) determined the damages resulting from the government’s breach of a contractual provision obligating the government to provide a contractor with work of a specified minimum dollar amount. The Board awarded the contractor the difference between the dollar amount of work the government actually ordered and the total minimum dollar amount the contract obligated the government to order. We conclude that this was an impermissible basis for calculating damages, because it would put the contractor in a more favorable position than it would have been in if the government had performed rather than breached its contractual commitment. The proper basis for damages in this case is the loss the contractor suffered as a result of the government’s breach, not the total amount it would have received without the breach. Accordingly, we vacate the decision of the Board and remand.

I

A. The appellee Delta Construction International, Inc. (“Delta”) entered into a contract with the Army to “furnish all labor, materials, equipment and transportation necessary to perform all work related to REPLACE ROTTEN LUMBER, GOVERNMENT FACILITIES, VARIOUS POSTS, PACIFIC AREA, PANAMA.” The “base” period of the contract *1042 was the last nine months of 1997, and the government had the option to extend the contract for two additional one-year periods. The government provided estimates of the dollar value of its anticipated total orders for each of these three periods, as well as estimates for particular items of the work. The contract warned that “Government estimated quantities may change drastically,” and that “[t]he quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.”

The contract stated:

This is an indefinite-quantity, indefinite-delivery contract with a guarantee minimum of $200,000.00 and a maximum of $1,300,000.00 for the base and option periods.

The contract also provided that “[t]he Contractor shall posses sufficient capability to accomplish a daily rate of work in monetary value of a minimum of $3,000.00 when single or multiple delivery orders have been issued and accepted.”

B. The government exercised its option to continue the contract for the first additional year, 1998, but declined to exercise its option for the second year. During 1998, Delta complained to the government about the lack of work and its idle work force. In May 1998, Delta submitted a claim to the contracting officer based on the government’s failure to provide the guaranteed minimum amount of work. The contracting officer denied the claim because it “is premature and lacks merit.” She stated: “It is premature to project that the Government will not order the guaranteed minimum. Furthermore, should the Government fail to order the guaranteed minimum, Delta Construction International, Inc. is not entitled to an adjustment on the basis of actual costs; the entitlement is the difference between the actual dollar volume ordered and the guaranteed minimum of $200,000.00.”

In January 1999, shortly after performance of the contract ended, Delta submitted to the Contracting Officer a claim for $125,965.46, which represented the difference between the dollar amount of the work the government had ordered and the guaranteed minimum of $200,000.00. A different Contracting Officer rejected the claim. He ruled that although

the Government did not order the guarantee minimum, nevertheless, the contractor is not entitled to be put in a better position than it would have been if it had performed and had to bear the expense of full performance. It is my decision that the contractor is entitled to recover a reasonable profit which it would have earned had he performed, based on the guarantee minimum, the overhead costs incurred on the guarantee minimum, and any reasonable, allo-cable, and allowable cost incurred based on guarantee minimum.
The government has provided a fair and reasonable consideration in issuing a unilateral modification (P00005 dated 12 March 99) to compensate the contractor in the amount of $11,216.00 for a reasonable profit, incurred overhead, and all reasonable cost based on the guarantee minimum.
On Delta’s appeal, the Board h[e]ld that Delta is entitled to recover the difference between $200,000 and the $86,323.07 in orders performed, or $113,676.93.

The Board stated that the difference between cases that permitted recovery of the difference between the guaranteed minimum and the work actually provided and those that limited damages to the contractor’s actual losses was that in the former cases “the contractor both ‘was required to and did maintain the capability *1043 of providing the minimum services set in the contract’ in return for the minimum guaranteed payment” but that in the latter cases “both of those factors were [not] present.”

II

A. The primary objective of damages for breach of contract is to place the non-breaching party “in as good a position pecuniarily as he would have been by performance of the contract.” Miller v. Robertson, 266 U.S. 243, 257, 45 S.Ct. 73, 69 L.Ed. 265 (1924). As this court has stated, “[t]he general rule is that damages for breach of contract shall place the wronged party in as good a position as it would have been in, had the breaching party fully performed its obligation.” Mass. Bay Transp. Auth. v. United States, 129 F.3d 1226, 1232 (Fed.Cir.1997) (citing prior cases of this court and its predecessor, the Court of Claims). Commentators and the Restatement of Contracts also have consistently recognized this principle. Arthur Linton Corbin, Corbin on Contracts § 992, at 5 (1964); E. Allan Farnsworth, Famsluorth on Contracts § 12.3, at 157 (2d ed. 1998); Charles T. McCormick, Damages § 137, at 561 (1935); Restatement (Second) of Contracts § 344 cmt. a (1979).

A corollary of that principle is that the non-breaching party is “not entitled to be put in a better position by the recovery than if the [other party] had fully performed the contract.” Miller, 266 U.S. at 260, 45 S.Ct. 73. As the First Circuit stated the rule, the non-breaching party “should on no account get more than would have accrued if the contract had been performed.” DPJ Co. v. FDIC, 30 F.3d 247, 250 (1st Cir.1994).

The Board’s decision here violates these established principles by awarding Delta the full amount it would have received if the government had not breached the contract. If the government had provided Delta with the $200,000 of work it had contractually guaranteed to provide, Delta would have been required to perform that work. To so perform, Delta would have incurred the additional costs of doing the additional work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Timothy Coan v. Department of Veterans Affairs
Merit Systems Protection Board, 2022
Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2021
Boaz Housing Authority v. United States
994 F.3d 1359 (Federal Circuit, 2021)
Englewood Terrace Ltd. Partnership v. United States
113 Fed. Cl. 718 (Federal Claims, 2013)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Dalles Irrigation District v. United States
88 Fed. Cl. 601 (Federal Claims, 2009)
Yankee Atomic Electric Co. v. United States
536 F.3d 1268 (Federal Circuit, 2008)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Dominion Resources, Inc. v. United States
77 Fed. Cl. 151 (Federal Claims, 2007)
Pacific Gas & Electric Co. v. United States
73 Fed. Cl. 333 (Federal Claims, 2006)
Spodek v. United States
73 Fed. Cl. 1 (Federal Claims, 2006)
Hi-Shear Technology Corporation v. United States
356 F.3d 1372 (Federal Circuit, 2004)
Alaska Pulp Corp. v. United States
59 Fed. Cl. 400 (Federal Claims, 2004)
Robert F. Christian, II v. United States
337 F.3d 1338 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
285 F.3d 1040, 2002 U.S. App. LEXIS 4784, 2002 WL 398251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-e-white-secretary-of-the-army-v-delta-construction-international-cafc-2002.