Consolidated Edison Co. of New York, Inc. v. United States

92 Fed. Cl. 466
CourtUnited States Court of Federal Claims
DecidedMay 17, 2010
DocketNos. 03-2622C, 04-33C
StatusPublished
Cited by17 cases

This text of 92 Fed. Cl. 466 (Consolidated Edison Co. of New York, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Edison Co. of New York, Inc. v. United States, 92 Fed. Cl. 466 (uscfc 2010).

Opinion

OPINION AND ORDER

WHEELER, Judge.

This case involves the damages claims of Plaintiffs Consolidated Edison Company of New York, Inc. (“Con Ed”) and Entergy Nuclear Indian Point 2, LLC (“Entergy”) caused by the failure of the Department of Energy (“DOE”) to collect and dispose of spent nuclear fuel. Under the terms of DOE’s June 1983 Standard Contract, DOE was to begin collecting spent nuclear fuel at the Indian Point nuclear facility (“Indian Point”) by January 31, 1998. Indian Point is a three-reactor nuclear power plant located on the Hudson River near Buchanan, New York, 25 miles north of New York City. Con Ed sold two of Indian Point’s reactors, Units 1 and 2, to Entergy on September 6, 2001. The claims of both Con Ed and Entergy arise from their ownership and operation of the same Indian Point nuclear facility. The Court therefore joined their claims together for trial and decision. Consol. Edison Co. of N.Y. v. United States, 83 Fed.Cl. 455, 459 (2008).

[474]*474The Court has jurisdiction over Plaintiffs’ claims pursuant to the Tucker Act, 28 U.S.C. § 1491(a) (2006). See PSEG Nuclear, LLC v. United States, 465 F.3d 1343, 1349 (Fed.Cir.2006). Defendant’s liability for partial breach of the Standard Contract is well established. Carolina Power & Light Co. v. United States, 82 Fed.Cl. 23, 26 (2008), aff'd in relevant part, 573 F.3d 1271 (Fed.Cir.2009) (citing Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1376-77 (Fed.Cir.2005)); Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268, 1272 (Fed.Cir.2008); Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1342 (Fed.Cir.2000) (“The breach involved all the utilities that had signed the contract — the entire nuclear electric industry.”). In this case, the Court previously granted summary judgment on liability for Entergy. Entergy Nuclear Indian Point 2, LLC v. United States, 64 Fed.Cl. 515 (2005). The Court also granted partial summary judgment in favor of Con Ed and Entergy regarding the rate at which DOE was required to accept spent nuclear fuel from utilities under the Standard Contract. Consol. Edison Co. of N.Y. v. United States, Nos. 03-2662C, 04-033C (Fed.Cl., May 18, 2009) (“Order, May 18, 2009”). Consistent with the Federal Circuit’s ruling in Pacific Gas & Electric Co. v. United States, 536 F.3d 1282, 1292 (Fed.Cir.2008), the applicable acceptance rate is found in DOE’s 1987 Annual Capacity Report and the 1987 Mission Plan Amendment.

Pursuant to Indiana Michigan, the Court must treat DOE’s failure to perform the Standard Contract as a partial breach. 422 F.3d at 1375-77. Although DOE has not commenced any spent nuclear fuel collection in the twelve years since its obligation arose, the parties have not repudiated the Standard Contract. Rather, DOE continues to collect the fees from plant owners required under the Standard Contract, and the parties expect that some day DOE will perform. The nuclear utilities may recover their incurred costs in mitigating the partial breach, but may not recover future expenses. Id. at 1377 (“If the breach of an entire contract is only partial, the plaintiff can recover only such damages as he or she has sustained, leaving prospective damages to a later suit in the event of future breaches.”) (citing 22 Am.Jur.2d Damages § 988 (2003)); see also Yankee Atomic Elec. Co., 536 F.3d at 1282.

The Con Ed portion of this case, involving a post-breach sale of a nuclear plant and alleged damages measured by a diminution in plant value resulting from DOE’s breach, is similar to Boston Edison Co. v. United States, 80 Fed.Cl. 468 (2008), appeal dismissed, 299 Fed.Appx. 956 (Fed.Cir.2008). Con Ed’s claims total $137,489,087, and are comprised of the following six items: (1) payments to external vendors and internal labor costs for studies relating to spent nuclear fuel storage alternatives ($871,634); (2) payments to Private Fuel Storage, LLC, a joint off-site venture for potential storage of spent nuclear fuel ($5,942,900); (3) additional decommissioning funds transferred to Enter-gy to account for spent nuclear fuel costs ($23,000,000); (4) diminished sales price due to DOE’s breach ($24,034,827); (5) a reduction in Entergy’s purchase price as a result of the unavailability of project debt financing ($64,874,776); and (6) over-funding of the decommissioning fund ($18,764,950). Conceptually, the first two items represent costs incurred when Con Ed owned Indian Point Units 1 and 2, and the remainder relate to damages that Con Ed allegedly suffered when it sold Indian Point Units 1 and 2 to Entergy. Defendant opposes Con Ed’s claims in their entirety.

Entergy’s claims total $136,811,374, and consist of the following ten items: (1) costs incurred in constructing and operating a dry storage facility for spent fuel ($21,934,275); (2) Unit 2 plant modification costs ($41,483,-226); (3) Unit 2 dry cask equipment costs ($11,790,480); (4) preparation and loading costs of dry cask storage at Unit 2 ($5,983,-644); (5) dry cask storage and equipment costs at Unit 1 ($26,501,939); (6) costs of continued operation and maintenance of the Unit 1 spent fuel pools ($9,158,553); (7) costs relating to the control and monitoring of spent fuel pool leaks at Unit 1 ($15,437,371); (8) payment of excess fees to the Nuclear Regulatory Commission (“NRC”) ($2,148,-901); (9) costs of participating in the Private Fuel Storage venture ($1,598,200); and (10) payment of additional property taxes due to [475]*475the construction of the dry storage facility at Unit 2 ($774,785). Entergy added a cost of capital element that would raise its total claim to $157,650,000. Entergy presented its damages claim for costs incurred through August 31, 2008. Defendant concedes liability to Entergy of $89,388,884, but opposes the balance of Entergy’s claims.

Defendant’s foremost objection to Con Ed’s and Entergy’s claims is that DOE signed one Standard Contract at Indian Point and committed one breach in failing to collect the plant’s spent fuel when required. Defendant asserts that neither Con Ed nor Entergy should receive additional damages merely because Con Ed sold Indian Point Units 1 and 2 to Entergy. In Defendant’s view, the damages consist of “one pie,” to be divided between the two plaintiffs. To the extent that the Court awards damages to Con Ed and Entergy in excess of the “pie,” Defendant says the Court would be imper-missibly allowing the damages to increase as a result of the sale. To avoid the possibility of a double recovery, the Court must be alert to any overlapping claims, and recognize when damages awarded to one plaintiff should be offset against the claims of the other.

Defendant also asserts that Con Ed and Entergy voluntarily divided their rights at the time of sale, with Con Ed retaining claims against DOE that accrued prior to the closing date, and Entergy receiving the right to bring claims accruing on or after the closing date. According to Defendant, Con Ed’s voluntary relinquishment of its rights prevents Con Ed from claiming damages against DOE for any diminished value in Indian Point’s sale price, or any other costs relating to the sale.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entergy Gulf States, Inc. v. United States
125 Fed. Cl. 678 (Federal Claims, 2016)
System Fuels, Inc. v. United States
125 Fed. Cl. 331 (Federal Claims, 2016)
Entergy Nuclear Indian Point 2, LLC v. United States
121 Fed. Cl. 667 (Federal Claims, 2015)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Portland General Electric Co. v. United States
100 Fed. Cl. 46 (Federal Claims, 2011)
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Entergy Nuclear Fitzpatrick, LLC v. United States
93 Fed. Cl. 739 (Federal Claims, 2010)
Consolidated Edison Co. v. United States
93 Fed. Cl. 492 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
92 Fed. Cl. 466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-edison-co-of-new-york-inc-v-united-states-uscfc-2010.