Portland General Electric Co. v. United States

100 Fed. Cl. 46, 2011 U.S. Claims LEXIS 1798, 2011 WL 3796290
CourtUnited States Court of Federal Claims
DecidedAugust 26, 2011
DocketNo. 04-09C
StatusPublished
Cited by3 cases

This text of 100 Fed. Cl. 46 (Portland General Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland General Electric Co. v. United States, 100 Fed. Cl. 46, 2011 U.S. Claims LEXIS 1798, 2011 WL 3796290 (uscfc 2011).

Opinion

OPINION

BRUGGINK, Judge.

This is an action for partial breach of contract by plaintiffs, electrical utilities, against the government, acting through the Department of Energy, for failing to begin picking up spent nuclear fuel from plaintiffs’ nuelear-fueled electric generation facilities on January 31,1998. A number of related cases are pending at the court. The government raises a contractual provision as its first affirmative defense. Plaintiffs have moved to dismiss, strike, and for judgment on the pleadings with respect to that affirmative defense. As part of its motion, plaintiffs request an in limine order to preclude the government from offering evidence at trial in support of the affirmative defense.

The matter is fully briefed. Oral argument was held on July 22, 2011, at which time we announced our decision to grant the [47]*47motion. See Portland Gen. Elec. Co. v. United States, No. 04-09 (Fed.Cl. Jul. 22, 2011) (order granting motion to strike). As we explain below, defendant’s affirmative defense of unavoidable delays is proscribed as a matter of law, and we therefore strike it. Accordingly, we also grant an in limine order prohibiting the government from offering any evidence at trial in support of that defense.

FACTUAL BACKGROUND

Plaintiffs operated the Trojan Nuclear Power Plant near Rainier, Oregon from 1975 until its shutdown and defueling in January 1993. In 1982, Congress enacted the Nuclear Waste Policy Act (“NWPA”), 42 U.S.C. §§ 10101-10270 (2006). The NWPA codified the federal government’s “responsibility to provide for the permanent disposal of high-level radioactive waste and such spent nuclear fuel as may be disposed of in order to protect the public health and safety and the environment.” Id. § 10131(a)(4). The NWPA provided a process for storage and disposal of high level waste and spent nuclear fuel (hereafter referred to collectively as “SNF”). The NWPA authorized the Secretary of Energy to enter into contracts with owners and generators of SNF to dispose of such material. Pursuant to section 302 of the NWPA, the Standard Contract for the disposal of SNF was developed; it is published at 10 C.F.R. § 961.11 (2011).

On June 13, 1983, Portland General Electric Company (“PGE”), on behalf of itself, the Eugene Water and Electric Board, and Pacific Power & Light (a predeeessor-in-inter-est of PacifiCorp), entered into a written contract with defendant known as the “Contract for Disposal of Spent Nuclear Fuel and/or High Level Radioactive Waste, U.S. Department of Energy Contract No. DE-CR01-83NE4406.” The material terms are published at 10 C.F.R. § 961.11. In this contract, plaintiffs agreed to purchase DOE’s services for disposal of SNF produced by the Trojan facility. The contract required defendant to begin disposing of SNF by January 31, 1998. Defendant has not yet begun disposal of SNF.

Article IX of the Standard Contract, entitled “DELAYS,” contains two clauses regarding delays. The first clause concerns unavoidable delays by the purchaser or DOE. It reads, in its entirety:

Neither the Government nor the Purchaser shall be liable under this contract for damages caused by failure to perform its obligations hereunder, if such failure arises out of causes beyond the control and without the fault or negligence of the party failing to perform. In the event circumstances beyond the reasonable control of the Purchaser or DOE — such as acts of God, or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes and unusually severe weather— cause delay in scheduled delivery, acceptance or transport of SNF and/or HLW, the party experiencing the delay will notify the other party as soon as possible after such delay is ascertained and the parties will readjust their schedules, as appropriate, to accommodate such delay.

10 C.F.R. § 961.11 (2011) (art. IX, cl. A).

The second clause concerns avoidable delays by the purchaser or DOE and reads, in its entirety:

In the event of any delay in the delivery, acceptance or transport of SNF and/or HLW to or by DOE caused by circumstances within the reasonable control of either the Purchaser or DOE with or their respective contractors or suppliers, the charges and schedules specified by the contract will be equitably adjusted to reflect any estimated additional costs incurred by the party not responsible for or contributing to the delay.

Id. (art. IX, cl. B).

LEGAL BACKGROUND

Courts have held that the NWPA created a duty on the part of the government to begin disposing of SNF. In Indiana Michigan Power Company v. Department of Energy, 88 F.3d 1272 (D.C.Cir.1996), utility companies challenged DOE’s interpretation of the NWPA The agency had taken the position that it would be unable to accept SNF by [48]*48early 1998 and that it had no duty to do so in the absence of a functioning nuclear repository. The D.C. Circuit disagreed and held that section 302(a)(5)(B) of the NWPA created an obligation on the part of DOE, reciprocal to the utilities’ obligation to pay, to start disposing of SNF by January 31, 1998. See id. at 1277.

Despite the ruling in Indiana Michigan, DOE informed utility companies that it would not begin to collect the SNF by the 1998 deadline. The companies then sought a writ of mandamus to compel DOE to dispose of the SNF. In Northern States Power Co. v. United States Department of Energy, 128 F.3d 754, 756 (D.C.Cir.1997) (“Northern States I”), the D.C. Circuit reaffirmed its ruling in Indiana Michigan, noting that “[petitioners have established that they have a clear right to relief.” Id. at 756 The court refused to grant the broader mandamus relief sought by the utilities, however, noting that the Standard Contract “provides a potentially adequate remedy if DOE fails to fulfill its obligations by the deadline.” Id. Nevertheless, the court held that the petitioners’ ability to enforce the contract “would be frustrated if DOE were allowed to operate under a construction of the contract inconsistent with [its] prior conclusion that the NWPA imposes an obligation on DOE “without qualification or condition.’ ” Id. at 759. Consequently, the court ordered “DOE to proceed with contractual remedies in a manner consistent with the NWPA’s command that [DOE] undertake an unconditional obligation to begin disposal of the SNF by January 31, 1998.” Id. at 760. The mandamus “preclude[d] DOE from concluding that its delay [was] unavoidable on the ground that it has not yet prepared a permanent repository or that it has no authority to provide storage in the interim.” Id.

The D.C. Circuit later clarified the scope of its Northern States I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entergy Nuclear Fitzpatrick, LLC. v. United States
711 F.3d 1382 (Federal Circuit, 2013)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Entergy Nuclear Fitzpatrick, LLC v. United States
101 Fed. Cl. 464 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
100 Fed. Cl. 46, 2011 U.S. Claims LEXIS 1798, 2011 WL 3796290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-general-electric-co-v-united-states-uscfc-2011.