Northern States Power Co. v. United States

224 F.3d 1361
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 31, 2000
DocketNo. 99-5096
StatusPublished
Cited by32 cases

This text of 224 F.3d 1361 (Northern States Power Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern States Power Co. v. United States, 224 F.3d 1361 (Fed. Cir. 2000).

Opinion

FRIEDMAN, Senior Circuit Judge.

This appeal presents the same basic issue as Maine Yankee Atomic Power Company v. United States, 225 F.3d 1336, decided simultaneously herewith: Whether an electric utility may maintain a damage suit based on the government’s alleged breach of a 1983 contract with it by which the government agreed, beginning no later than January 1, 1998, to dispose of the nuclear waste that the utility had generated, or was required first to file an administrative claim with the contracting officer under the contract’s disputes provision. In Maine Yankee, the United States [1364]*1364Court of Federal Claims denied the government’s motion to dismiss the complaint, holding that the utility could maintain the suit, a decision we today affirm.

In the present case another judge of that court held that the utility was required first to proceed administratively under the disputes clause of the contract, and dismissed the complaint on the government’s motion. We reverse.

I

The background facts are set forth in our opinion in Maine Yankee, and need not be repeated in detail here.

Because of concerns over the disposal of nuclear waste accumulating at nuclear power plants, Congress in the Nuclear Waste Policy Act of 1982 (“the Act”), 42 U.S.C. §§ 10101-10270 (1994), authorized the Secretary of the Department of Energy (“the Department”) to enter into contracts with utilities for the disposal of spent nuclear fuel (“SNF”) and high-level radioactive waste. See 42 U.S.C. § 10222(a)(1) (1994). The Act required that all such contracts “shall provide that” the Department will dispose of the waste “beginning not later than January 31, 1998.” Id. § 10222(a)(5)(B).

The Department promulgated a Standard Contract for Disposal of Spent Nuclear Fuel, 10 C.F.R. § 961.11 (1983). That contract required the utilities to pay a onetime fee, based on the amount of electricity generated prior to April 7, 1983, and an ongoing fee based on the amount of electricity generated thereafter. As the Act required, the contract (article II) obligated the Department to take title to, transport, and dispose of the nuclear waste beginning “not later than January 31,1998.”

The contract also contains several provisions dealing with delays, remedies and disputes. It provides that in case of “any delay in the delivery, acceptance or transport of SNF ... to or by DOE caused by circumstances within the reasonable control of either the Purchaser or DOE or their respective contractors or suppliers, the charges and schedules specified by this contract will be equitably adjusted to reflect any estimated additional costs incurred by the party not responsible for or contributing to the delay” (article IX.B); and that “[ejxcept as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer” (article XVI).

The appellee Northern States Power Company (Northern States) is an electric utility that has nuclear power generating facilities. It entered into a standard contract with the Department in 1983. In 1994, the Department announced that it could not begin disposing of nuclear waste by January 31, 1998, as the contract required, because the repository it planned to build to store the waste would not be available until at least 2010. See Notice of Inquiry, 59 Fed.Reg. 27,007, 27,007-08 (1994). One year later, in its “Final Interpretation of Nuclear Waste Acceptance Issues,” the Department stated that “it does not have an unconditional statutory or contractual obligation to accept [nuclear waste] beginning January 31, 1998 in the absence of a repository or interim storage facility constructed under the Act.” 60 Fed.Reg. 21,793 (1995).

Several utilities filed suit in the United States Court of Appeals for the District of Columbia Circuit challenging the Final Interpretation. That court held that the January 31, 1998 deadline was not conditioned on the availability of a repository, and vacated the Final Determination. See Indiana Michigan Power Co. v. Department of Energy, 88 F.3d 1272 (D.C.Cir. 1996). The Department then notified the utilities that it would not begin disposing of waste by the deadline. Citing the lack of a permanent repository or temporary storage facility, the Department characterized this failure to perform as an “unavoidable delay” under the contract, which was therefore not compensable.

Northern States and other utilities then filed in the District of Columbia Circuit a [1365]*1365petition for mandamus ordering the Department to meet the contractual deadline. The court refused to so order, stating that, if there were a delay, the utilities “must pursue the remedies provided in the Standard Contract in the event that DOE does not perform its duty to dispose of the SNF by January 31, 1998.” Northern States Power Co. v. U.S. Department of Energy, 128 F.3d 754, 759 (D.C.Cir.1997). The court, however, issued a writ of mandamus prohibiting the Department from relying on the unavoidable delays provision of the contract:

[W]e preclude DOE from concluding that its delay is unavoidable on the ground that it has not yet prepared a permanent repository or the that it has no authority to provide storage in the interim.
This necessarily means, of course, that DOE not implement any interpretation of the Standard Contract that excuses its failure to perform on the grounds of “acts of Government in either its sovereign or contractual capacity.” 10 C.F.R. § 961.11, Art. IX.A.

Id. at 760.

Northern States then filed a complaint in the United States Court of Federal Claims seeking damages for the Department’s alleged breach of “its essential contractual obligation to begin disposing of SNF by January 31, 1998,” which it stated “constitutes a material partial breach of its Standard Contract with NSP, for which NSP may seek recovery of its damages without exhausting any administrative remedies.” Count I of the complaint alleged a partial breach of the standard contract, and count II alleged a breach of an “implied covenant of good faith and fair dealing” that the standard contract contains, “by failing and refusing to make any effort to meet the contractual deadline for beginning to dispose of SNF.”

On the government’s motion, the court dismissed the suit. It held that Northern States could not “seek to enforce its contract rights through a claim for breach damages in this court” because it “is obliged by the terms of its contract with DOE to pursue its demand for monetary relief at the agency level, i.e., through a claim for equitable adjustment submitted in accordance with the contract’s disputes clause.” Northern States Power Co. v. United States, 43 Fed.Cl. 374, 376 (1999).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
System Fuels, Inc. v. United States
666 F.3d 1306 (Federal Circuit, 2012)
Entergy Nuclear Fitzpatrick, LLC v. United States
101 Fed. Cl. 464 (Federal Claims, 2011)
Rochester Gas & Electric Corp. v. United States
99 Fed. Cl. 369 (Federal Claims, 2011)
Arizona Public Service Co. v. United States
93 Fed. Cl. 384 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Vermont Yankee Nuclear Power Corp. v. United States
84 Fed. Cl. 339 (Federal Claims, 2008)
Boston Edison Co. v. United States
80 Fed. Cl. 468 (Federal Claims, 2008)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Dominion Resources, Inc. v. United States
77 Fed. Cl. 151 (Federal Claims, 2007)
Pseg Nuclear, l.l.c. v. United States
465 F.3d 1343 (Federal Circuit, 2006)
Sacramento Municipal Utility District v. United States
70 Fed. Cl. 332 (Federal Claims, 2006)
Energy Northwest v. United States
69 Fed. Cl. 500 (Federal Claims, 2006)
System Fuels, Inc. v. United States
65 Fed. Cl. 163 (Federal Claims, 2005)
Boston Edison Co. v. States
64 Fed. Cl. 167 (Federal Claims, 2005)
Commonwealth Edison Co. v. United States
56 Fed. Cl. 652 (Federal Claims, 2003)
Alabama Power Co. v. United States Department of Energy
307 F.3d 1300 (Eleventh Circuit, 2002)
Tennessee Valley Authority v. United States
51 Fed. Cl. 284 (Federal Claims, 2001)
Roedler v. Department of Energy
255 F.3d 1347 (Federal Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
224 F.3d 1361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-states-power-co-v-united-states-cafc-2000.