Sacramento Municipal Utility District v. United States

70 Fed. Cl. 332, 2006 U.S. Claims LEXIS 88
CourtUnited States Court of Federal Claims
DecidedMarch 31, 2006
DocketNo. 98-488C
StatusPublished
Cited by37 cases

This text of 70 Fed. Cl. 332 (Sacramento Municipal Utility District v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sacramento Municipal Utility District v. United States, 70 Fed. Cl. 332, 2006 U.S. Claims LEXIS 88 (uscfc 2006).

Opinion

[334]*334ORDER REQUESTING SUPPLEMENTAL EXPERT TESTIMONY

BRADEN, Judge.

Consistent with the March 31, 2006 Memorandum Opinion and Order issued, Plaintiff is ordered to submit Supplemental Direct Testimony from Mr. Brian P. Brinig, Brinig & Company, Inc., in the format of five tables and any supporting explanation:

1. Table A—a Summary of Costs by the categories listed in PX 1000 1120,1 for each of the following periods: January 1,1992 through May 14,1997; May 15, 1997 through May 31, 1997; June 1, 1997 through October 31, 1999; and November 1, 1999 through December 31, 2003.

2. Table B—including cost data from Table A, minus any costs attributable to the “dual-purpose” transportable features of the dry storage system.

3. Table C—including cost data from Table B, minus any costs attributable to a contract, lease, or other legal obligations executed by Plaintiff prior to May 15,1997.

4. Table D—including cost data from Table C, minus any costs attributable to one-twenty-second of the cost to construct the ISFSI.

5. Table E—including cost data from Table D, minus Packaging Technologies and Veetra charges attributable to on-site drop testing.

The court will convene a telephone conference on April 10, 2006 at 2:00 p.m. E.D.T. to discuss implementation of this Order, including the Government’s oversight and verification of the data reported in the Tables.

IT IS SO ORDERED.

MEMORANDUM OPINION AND ORDER

On January 19, 2005, the court held that the United States (“the Government”) is liable for the January 31,1998 partial breach of a June 14, 1983 Department of Energy Standard Contract (“Standard Contract”) with the Sacramento Municipal Unity District (“SMUD” or “the District”). See Sacramento Mun. Util. Dist. v. United States, 63 Fed.Cl. 495 (Fed.Cl.2005). On March 21-25, 2005 and March 28, 2005-April 1, 2005, the court convened an evidentiary hearing, wherein SMUD asserted that the partial breach caused SMUD to incur $78,558,212.00 in costs from January 1, 1992 to December 31, 2003. Post-hearing briefing was concluded on November 1, 2005. After evaluating the evidence proffered by the parties in light of Indiana Michigan Power Co. v. United States, 422 F.3d 1369 (Fed.Cir.2005), the court has determined that SMUD is entitled to damages, but only for certain costs incurred from May 15, 1997 to December 31, 2003.

An outline of this Memorandum Opinion and Order follows:

I. RELEVANT FACTS.......................................................336

A. In 1982, Congress Required The Department Of Energy To Provide For The Permanent Disposal Of Spent Nuclear Fuel And/Or High Level Radioactive Waste From All Domestic Utilities...................336

B. In 1983, The Sacramento Municipal Utility District Entered Into A Standard Contract With The Department Of Energy To Dispose Of Spent Nuclear Fuel And/Or High-Level Radioactive Waste..............339

C. In 1989, The Sacramento Municipal Utility District Decided To Shut Down The Nuclear Generating Plant..................................339

D. Actions Taken By The Sacramento Municipal Utility District To Decommission The Nuclear Generating Plant..........................340

1. In 1990...........................................................340

a. Options For Spent Nuclear Fuel Storage Were Evaluated......340

b. A “Dual-Purpose” Dry Storage Project Was Authorized.........342

[335]*335c. A Decision Was Made To Enter Into A Joint Dry Transfer Demonstration With The Department Of Energy..............342

2. In 1991...........................................................343

a. Initial Planning Was Started And Proposals For The “Dual-Purpose” Dry Storage Project Were Solicited...........343

b. Discussions About The Joint Dry Transfer Demonstration Began.....................................................345

3. In 1992........................................................... 346

a. Planning For The “Dual-Purpose” Dry Storage Project And Selecting A Vendor Continued...............................346

b. Discussions About The Joint Dry Transfer Demonstration Continued..................................................347

c. The Department Of Energy Announced That It May Not Be Able To Construct A Permanent Storage Facility By 1998......347

4. In 1993...........................................................347

a. Vendor Difficulties Delayed Implementation Of The “Dual-Purpose” Dry Storage Project...............................347

b. Concerns Arose About Whether The Department Of Energy Would Accept Spent Nuclear Fuel Stored In Canisters......347

c. Discussions About The Joint Dry Transfer Demonstration Continued..................................................348

5. In 1994...........................................................348

a. The Department Of Energy Raised Concerns About The Availability Of A Suitable Storage Facility....................348

b. The “Dual-Purpose” Dry Storage Project Continued To Be Implemented...............................................349

c. A Cooperative Agreement For A Joint Dry Transfer Demonstration Was Reached With The Department Of Energy......349

6. In 1995...........................................................349

a. The Department Of Energy Announced That It Would Not Begin Accepting Spent Nuclear Fuel In 1998..................349

b. Development Of The “Dual-Purpose” Dry Storage System Continued..................................................349

7. In 1996...........................................................350

a. Development Of The “Dual-Purpose” Dry Storage System Continued..................................’................350

b. Disposal Of Low-Level Radioactive Waste Around The Wet Pool Began................................................350

c. Received Legal Notice That Performance Would Not Begin Under The Standard Contract On January 31,1998............350

d. The “Dual-Purpose” Dry Storage Project Was Reevaluated......350

e. The Sacramento Municipal Utility District Sought To Amend The Cooperative Agreement For A Joint Dry Transfer Demonstration.....................................351

8. In 1997...........................................................351

a. Regulatory Problems And Vendor Bankruptcy Delayed Implementation Of The “Dual-Purpose” Dry Storage Project....................................................351

b. The “Dual-Purpose” Dry Storage Project Was Continued......352

9. In 1998...........................................................353

a. The Department Of Energy Did Not Begin Disposal Of Spent Nuclear Fuel And/Or High-Level Radioactive Waste, As Required Under The Standard Contract.............353

b.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entergy Nuclear Palisades, LLC v. United States
128 Fed. Cl. 120 (Federal Claims, 2016)
System Fuels, Inc. v. United States
120 Fed. Cl. 635 (Federal Claims, 2015)
Sacramento Municipal Utility District v. United States
120 Fed. Cl. 270 (Federal Claims, 2015)
Sacramento Municipal Utility District v. United States
566 F. App'x 985 (Federal Circuit, 2014)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
In Re Sacramento Municipal Utility District
395 F. App'x 684 (Federal Circuit, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Dominion Resources, Inc. v. United States
84 Fed. Cl. 259 (Federal Claims, 2008)
Carolina Power & Light Co. v. United States
82 Fed. Cl. 23 (Federal Claims, 2008)
Boston Edison Co. v. United States
80 Fed. Cl. 468 (Federal Claims, 2008)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
70 Fed. Cl. 332, 2006 U.S. Claims LEXIS 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sacramento-municipal-utility-district-v-united-states-uscfc-2006.